Construction-Manager CMAA Certified Construction Manager (CCM) Free Practice Exam Questions (2025 Updated)
Prepare effectively for your CMAA Construction-Manager Certified Construction Manager (CCM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
When applying BIM to a project, which method checks for interferences by searching for intersecting volumes?
Which of the following would MOST likely help provide benchmarking for a sustainable project?
Lifecycle analysis of a project will provide the greatest impact during which of the following phases?
A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner's risk, the CM should recommend that the owner
A CM team on a new project which is in the pre-design phase is planning their climate resiliency strategy. Which of the following is the team's BEST first step in this process?
When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must
A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that
Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?
Which of the following is a key element of a safety culture?
An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?
During the design phase of a CM agency project, the designer submits several design options for the stakeholders to review and provide input on. Whose responsibility is it to ensure that the stakeholders are able to provide input on the designs?
= P × [(C + T + Q) + 3]
P is Probability
C is Cost
T is Time
Q is Quality
This equation best describes a(n)
A written safety program should include all applicable laws, codes, and regulations, and must
A project manager is working on a new transit station project. This client has never used an agency CM before. The project manager wishes to engage the client in defining the scope, budget, schedule, environmental conditions, and basic systems to be utilized. Which of the following would be MOST useful in engaging the client and defining the project requirements?
As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?
The narrative accompanying a CM-developed construction cost estimate during the design phase should include which of the following?
The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on. What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?
When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor's lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate; and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because: