Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

ASF Exin Agile Scrum Foundation Free Practice Exam Questions (2025 Updated)

Prepare effectively for your Exin ASF Agile Scrum Foundation certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 1
Total 59 questions

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

A.

Keeping high priority features at the top of the Product Backlog.

B.

Not allowing changes to the Product Backlog once the Sprint begins.

C.

Supporting the team's decisions and resolving the team's issues.

What is the expected outcome of the first Sprint on a project?

A.

A few working, tested features from the Product Backlog

B.

Architecture and high-level design of the Product

C.

Assignment of the team, Product Owner and Scrum Master

D.

A well-defined release plan for the Product

Which statement describes Release Planning?

A.

After looking at all the stories in the backlog, the team estimates their effort in detail.

B.

The team meets with the customer to negotiate the scope, cost and time of the release.

C.

The team and the Product Owner agree on an initial plan for the delivery of features.

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.

Which statement is true regarding this scenario?

A.

Points are assigned by the Scrum Master, not by the team.

B.

Points are assigned for the overall Story, not for parts of the Story.

C.

Points are never estimated, but always determined beforehand.

D.

The team forgets to ask the Product Owner about the estimate.

Why does the Daily Scrum need to be held at the same location and time?

A.

The booking of a room needs to be done in advance for the duration of the Sprint.

B.

The constant time and place is best for continuity of the Scrum framework.

C.

The Project Manager needs to get the status updates at a given time every day.

Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?

A.

The Product Owner

B.

The Scrum Master

C.

The team

Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?

A.

If more details are needed during Sprint Planning

B.

If there is a large number of stories to estimate

C.

If there is a small number of stories to estimate

Which means of communication is the most preferable to clarify the interpretation of a requirement?

A.

E-mail

B.

Face-to-face

C.

Instant messaging

D.

Telephone

How does Agile bring predictability to the Planning process?

A.

By allowing the customers to review the progress often.

B.

By assigning most of the responsibility to the Product Owner.

C.

By making the team self-organized and self-planning.

D.

By providing early visibility into the team's progress.

A team decided to install a large traffic light in the team hall to indicate whether the latest build was healthy (green), failing a few tests (orange) or failing high priority tests (red).

What term can be used to describe the traffic light?

A.

Information radiator

B.

Osmotic communication

C.

Triangulation

Collaboration is the most important parameter for the success of an Agile team.

What term best describes this type of interaction?

A.

Distributed team working.

B.

Information radiator sharing.

C.

Osmotic communication.

During a Sprint Planning session, the team argues about the work estimates for a particular story.

    The Product Owner estimates five days.

    The Lead Architect estimates two days.

    The Scrum Master estimates eight days.

    The team member working on it estimates seven days.

What value (in days) should be used for planning?

A.

2

B.

5

C.

7

D.

8

Why is planning poker an effective estimation technique?

A.

It generates a lot of useful discussion and gets team buy-in.

B.

It results in lower estimates as team members will estimate individually.

C.

It triggers a more detailed and task oriented break-up of the story.

What is an "escaped defect"?

A.

A defect that was found by the customer.

B.

A defect that was planned to be fixed, but not fixed in a Sprint.

C.

A defect the Continuous Integration System failed to catch.

A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.

What is the most likely reason that the team did not meet the Sprint objectives?

A.

The Product Owner is unable to prioritize.

B.

The team is lacking skills.

C.

The team did not plan the Sprint effectively.

D.

The team is over-worked.

A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.

What would be the elapsed time required to complete the Story?

A.

One day and two hours

B.

Two days

C.

Five hours

Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan.

What term best describes the multi-level planning?

A.

Planning Onion

B.

Planning Poker

C.

Sprint Planning

Page: 1 / 1
Total 59 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved