CDCS Exin EXIN EPI Certified Data Centre Specialist Free Practice Exam Questions (2025 Updated)

Prepare effectively for your Exin CDCS EXIN EPI Certified Data Centre Specialist certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 1
Total 60 questions

You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?

A.

No, there is a significant difference in the formula for the different types of fire suppression gases.

B.

Yes, as long as you take the difference between the net and gross volume into account.

C.

Yes, as long as you use the same units of measure, i.e., kg/m³ or lbs/ft³.

D.

Yes, as long as you change the 'S' factor of the formula to reflect the gas type used.

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

A.

PUE does not indicate efficiency

B.

Data center A

C.

Data center B

D.

Data center C

What mainly affects the cooling capacity of a raised floor tile?

A.

Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle

B.

Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile

C.

Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

D.

Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile

The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.

Taking energy efficiency as the highest priority, which cooling system should you recommend?

A.

Standard air conditioning units, as spares might not be readily available

B.

Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment

C.

Waterside economizer

D.

Airside economizer

The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.

What action, if any, should you recommend for the computer room?

A.

Maintain the current wet pipe system.

B.

Replace the wet pipe system with a deluge system.

C.

Replace the wet pipe system with a dry pipe system.

D.

Replace the wet pipe system with a pre-action system.

What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?

A.

It can only be used in computer rooms which have sufficient air changes per hour.

B.

The gas containers need to be close to the hazard area.

C.

It can only be used in non-continuous occupied areas.

D.

It can only be used in computer rooms where you have sufficient positive pressure.

It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.

Where should you recommend the shielding material to be installed?

A.

As close as possible to the computer room

B.

As close as possible to the transformer room

C.

It does not matter, either close to the transformer room or the computer room is okay as there is no impact to cost or shielding material performance

D.

Shielding is not required to be installed as 100mG is within the acceptable levels for computer rooms

You are allowed to use a calculator for this question.

A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.

The temperature is 20 °C / 68 °F.

The required design concentration is 7%.

The S-Factor is 0.1359 (metric) / 1.885 (imperial).

Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

A.

Approximately 410 kg / 900 lbs

B.

Approximately 820 kg / 1,800 lbs

C.

Approximately 1,390 kg / 3,000 lbs

D.

Approximately 1,640 kg / 3,600 lbs

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Do you need to consider blast protection when designing a data center?

A.

No, there is no reason for implementing blast protection as nobody can predict the impact of a bomb explosion.

B.

Yes, if the data center is a potential target or the building is located within the vicinity of (close by) a potential target.

C.

No, blast protection is not a requirement of ANSI/TIA-942.

D.

Yes, blast protection is a requirement of ANSI/TIA-942.

A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.

Should the supplier of the fire suppression system be informed on the design of the racks?

A.

No, cooling and design of racks have no influence on the fire suppression system design.

B.

Only when the rack height obstructs a potential fire suppression release point.

C.

Yes, the design of the racks has an influence on the fire suppression system design.

D.

Only when the racks might block access to the fire panel.

You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.

Which location for the temperature/humidity measurement should you recommend for the audit?

A.

At the back/rear of the server at 50 mm/2 inch

B.

At 1.5 meters/5 feet above the floor in the middle of the cold aisle

C.

At the front/intake of the server at 50 mm/2 inch

D.

At 1.5 meters/5 feet above the floor in the middle of the hot aisle

Smoke sensors need to be tested to ensure that they pick up a potential fire in the data center.

What should you recommend?

A.

Test the sensors by injecting smoke or simulated smoke directly into the sensor

B.

Press the self-test button on each sensor in the data center

C.

Inject smoke at the floor level

D.

Test the sensors according to the vendor specification

What should be considered when installing overhead data cabling?

A.

To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.

B.

Copper data cabling should not be placed in metal cable trays.

C.

Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

D.

All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.

You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.

A.

12 Amperes

B.

30 Amperes

C.

60 Amperes

D.

80 Amperes

You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6-Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.

What should you recommend?

A.

Nothing, the UPS will be able to take care of the right levels of THDi

B.

Install a passive harmonic filter on the UPS

C.

Install an active harmonic filter on the UPS

D.

Install an isolation transformer rated at K13 or K20

When shielding material reaches its saturation point, what will be the impact?

A.

The shielding material will reach its optimal shielding performance state.

B.

The shielding material will no longer be able to attenuate (reduce) additional EMF.

C.

The shielding material will increase its permeability factor.

D.

The shielding material will reach its maximum electrically charged state.

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

A.

Pre-terminated cabling is already factory tested and saves installation time.

B.

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.

Pre-terminated cabling has a higher fire rating.

D.

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.