Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

EX0-008 Exin Agile Scrum Foundation Free Practice Exam Questions (2025 Updated)

Prepare effectively for your Exin EX0-008 Agile Scrum Foundation certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 1
Total 59 questions

A Project Manager wants to track not just the rate of progress against tasks, but also the overall morale and happiness of the Scrum team.

What device will help track morale and happiness?

A.

A Gross Happiness index

B.

A Niko-niko calendar

C.

An employee satisfaction survey

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.

What is the elapsed time required to complete the story?

A.

1.25 days

B.

1.33 days

C.

2 days

D.

This cannot be determined without knowing the velocity.

During a Sprint Planning session, the team argues about the work estimates for a particular story.

    The Product Owner estimates five days.

    The Lead Architect estimates two days.

    The Scrum Master estimates eight days.

    The team member working on it estimates seven days.

What value (in days) should be used for planning?

A.

2

B.

5

C.

7

D.

8

Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan.

What term best describes the multi-level planning?

A.

Planning Onion

B.

Planning Poker

C.

Sprint Planning

Why are estimates expressed in terms of story points difficult to explain outside of the team?

A.

It requires a comparison to a benchmark, which typically varies from team to team.

B.

It requires a deeper understanding of the technical approach to implement each story.

C.

It requires breaking the stories down into Sprint Backlog Items, which only the team can do.

Why is planning poker an effective estimation technique?

A.

It generates a lot of useful discussion and gets team buy-in.

B.

It results in lower estimates as team members will estimate individually.

C.

It triggers a more detailed and task oriented break-up of the story.

How should 'done' be defined when multiple teams are working on a single product?

A.

All teams must have the same definition of 'done'.

B.

Each team must define and use their own definition of 'done'.

C.

The Scrum Master defines when the item is 'done'.

In a Scrum project, when would a requirement get added to the Product backlog?

A.

When it is developed, but cannot yet be released.

B.

When the team works on it for a particular release.

C.

When the customer requests a new requirement.

A team decided to install a large traffic light in the team hall to indicate whether the latest build was healthy (green), failing a few tests (orange) or failing high priority tests (red).

What term can be used to describe the traffic light?

A.

Information radiator

B.

Osmotic communication

C.

Triangulation

Who knows most about the progress towards a business objective or a release?

A.

The Product Owner

B.

The Scrum Master

C.

The team

What is a Sprint?

A.

A brainstorming session in Extreme programming to generate design ideas.

B.

A race between two developers to see who can complete a feature fastest.

C.

One iteration in the Scrum methodology.

D.

The last iteration in the Scrum project, when the team works long hours to finish the project.

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

A.

Keeping high priority features at the top of the Product Backlog.

B.

Not allowing changes to the Product Backlog once the Sprint begins.

C.

Supporting the team's decisions and resolving the team's issues.

The team determines that it has over-committed itself for a Sprint.

Who should be present when reviewing and adjusting the Sprint work?

A.

The team, the Scrum Master and the Product Owner. The Stakeholders should be consulted.

B.

The team and the Scrum Master. The Product Owner should be consulted.

C.

The team only. The Product Owner should be consulted.

A Manager requests to attend the daily stand-up meeting so that he can be more responsive to the team by being aware of the team's progress and issues.

As the Scrum Master, what should you do?

A.

Allow the Product Owner to participate in 'listen only' mode.

B.

Allow the Product Owner to participate like any other team member.

C.

Turn down the request as the daily stand-up is only for the team.

What is a characteristic of a well-designed Agile work space?

A.

It has a silent zone to facilitate concentration.

B.

There is enough space for information radiators.

C.

Work stations are personalized for team members.

What is time-boxing?

A.

A period of intense activity within a particular release.

B.

Setting an upper time limit and planning the activities within that limit.

C.

Tight planning focused on reducing the time required for any activity.

What is a Scrum-of-Scrums?

A.

A meeting for management to get insight into the working of teams.

B.

A meeting for Scrum Masters of international Scrum teams.

C.

A meeting to coordinate the work of multiple Scrum teams.

D.

A meeting to show the customer an update of the product.

Page: 1 / 1
Total 59 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved