Prepare effectively for your Exin SIAMP EXIN SIAM Professional Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 1
Total 56 questions

The ZYXS IT Director has proposed to the CIO that ZYXS should be the service integrator in the new SIAM model. The CIO wants to validate if the necessary capabilities exist in ZYXS. The CIO has asked SIAMRUS to perform the assessment.

What is the first activity that SIAMRUS should carry out?

A.

Compare the ZYXS service integration capabilities with the SIAM objectives and the target SIAM model

B.

Assess the existing capabilities of each team in ZYXS and determine if they are at the required maturity

C.

Identify and then map the stakeholders, process owners and managers for all services across ZYX

D.

Prepare a heat map to provide a graphical summary of capabilities and show it to the CIO

What is unlikely to be included in the outline business case for NEWGEN?

A.

Boundanes of responsibilities

B.

Measurements of benefits

C.

Procedures from internal providers

D.

Proposed future services

The SIAM Project Board has decided that a big bang implementation approach is unsuitable for ZYX

What is the most likely reason for this decision?

A.

Agile methods cannot be applied to a big bang implementation approach.

B.

The current service provider contracts have different termination periods.

C.

The service levels must be maintained throughout the entire transition

D.

The ZYXUK Directors want to use the approach suggested by SIAMRUS

The outline SIAM model has been determined.

-SIAMRUS will be the service integrator.

-The development teams from ZYXS and ZYXUK will merge to provide global application development and support services

-ZYXS will also provide a centralized service desk, desktop support, and field engineer support.

-OUTSCO will provide hosting e-mail services, the wide area network, and local area networks under new contracts

-All services currently hosted by ZYXS or ZYXD will transfer to OUTSCO

The strategy is to transfer the current services to these named service providers as the legacy contracts expire

The merger with the Tokyo-based competitor has started and is expected to complete in 3 months' time. As part of the merger the services currently provided by the Tokyo-based internal functions will transfer to ZYXS and ZYXUK. The planning for this has only just started, there is insufficient time to create and test a detailed plan

What is the most appropriate implementation approach for the ZYX SIAM model?

What is the most appropriate implementation approach for the ZYX SIAM model?

A.

Big bang with all service providers onboarded at once

B.

Phased approach by ZYX organization and location

C.

Phased approach by service or group of services

D.

Phased approach by incumbent service provider

One year ago. OUTSCO was appointed as the service integrator for ZYX. ZYXH provides the retained capabilities.

After a year of operating the SIAM model, OUTSCO has noticed that the 99 5% availability service level target for NEWBNK has been consistently overachieved by 0.4% every month.

In order to provide better value to ZYX and to challenge the service providers in their delivery, ZYXH would like to increase the availability target to 99 9% as soon as possible.

What is the best way of doing this?

A.

Ascertain the cost of the change from ZYXS, ZYXD and NETSCO and base the decision to proceed on a cost-benefit analysis

B.

Hold a meeting with ZYXS to discuss the feasibility of the increase and base the decision to change the target on their views

C.

Send an e-mail from OUTSCO to all service providers that the NEWBNK availability target is going to increase with immediate effect

D.

Tell ZYXS. ZYXD and NETSCO that the target is increasing and give them 3 months to make the necessary changes

A consequence of ZYX’s SIAM transition is that the small IT team of 5 staff within ZYXUK, who currently develop and support small stand-alone applications, are being displaced, with their roles outsourced to a new external service provider. This external service provider will provide a standardized approach to the development and B support of bespoke applications across all of the ZYX organizations It is hoped that this will allow similar requirements from different ZYX organizations to be identified a more manner

The impacted staff is expected to be reluctant to transfer to the new service provider, who is based outside of the UK and has a very different organizational culture B I he project team is concerned that these staff members may either be reluctant to pass on their knowledge of the existing applications, or may leave before knowledge transfer can take place

What would be the most effective strategy for handling this risk?

A.

identify the one or two key members of the team, who have the greatest knowledge of the applications Find these individuals suitable alternative roles within the retained IT capability, to ensure that the knowledge does not leave the organization

B.

identify a minimum set of documentation. Task the impact team to produce or update these documents for each application. Put in place a handover process which includes formal review and sign-off of the documents by the new service provider

C.

Provide clear communication to the impacted staff regarding why the change is happening, the implications for themselves and the timescales involved. Incentivize some or all of the impacted staff to remain throughout the handover and early life support phases.

D.

Take immediate steps to embed staff from the new service provider, to work alongside the impacted staff members Initiate a coordinated exercise to ensure that all existing documentationregarding the applications is brought up to date.

The CIO is about to establish a project to transition ZYX to a SIAM operating model.

Which are the most important governance requirements to initially focus on, given the situation of ZYX?

A.

At this point in planning the transition project, the most important area for the CIO to focus on is strategic planning This includes building the SIAM business case reviewing legal requirements, identifying strategic nsks and ensuring a robust control structure is in place

B.

Before initiating the transition project designing and completing a detailed tooling strategy is critical for ZYX. This will help ZYX to select the service integrator and the service providers and will ensure a smooth onboarding of service providers into the integrated solution

C.

in order to ensure a smooth transition to the SIAM operating model, the CIO must focus on mitigating risks such as the ownership of tools, processes and data This is in order to prevent any loss of knowledge and skills as service providers are replaced

D.

The first task for the CIO is to establish governance over service levels and key performance indicators This will ensure that all contracts and agreements with SIAMRUS and the service providers are in place before transitioning to the SIAM operating model

ZYX has appointed a service integrator in addition to measunng specific service provider service levels, the ZYX Board of Directors also wants information on end-to-end process KPIs based on business outcomes

The KPIs that the ZYX Board would like are

-End-to-end availability of services supporting sales activity

-End-to-end resolution time for support requests received from users

-Timeliness of invoice production, distribution and payment

How should the service integrator implement these KPIs?

A.

Bring the providers together to map the services, and define and agree on the supporting measurements

B.

Engage a team of consultants from SIAMRUS to map the processes and define the calculations required

C.

Review the existing KPIs used by all providers to see which ones can be used as the new KPIs

D.

Request ZYX to produce data definitions and distnbute these to the service providers

Project NEWGEN is in the Discovery and Strategy stage. SIAMRUS is assisting ZYX with the design of the SIAM model ZYX has decided to use OUTSCO as an external service integrator but they have not yet been appointed.

The CIO is concerned that the retained capabilities might not have the necessary capability to perform their new role in the SIAM model

What is the best course of action?

A.

Ask the service integrator after they are appointed to create customized role profiles.

B.

Ask staff to apply for a new role with the service integrator in the new SIAM ecosystem

C.

Create a framework for generic role profiles for the retained capabilities

D.

-Ask staff to apply for a new role with the service providers in the new SIAM ecosystem O . Create customized role profiles for all parties in the new SIAM ecosystem

E.

Determine which staff has the right capabilities for their new role

F.

. Have the staff do assessments based on generic role profiles from a framework - Fire those staff from the original organization that are lacking SIAM skills

ZYX is initiating their NEWGEN SIAM transition project As part of the early planning, ZYX identifies key activities and milestones that must be included in the project plan.

What would be the best approach for ZYX to take in designing their SIAM governance framework?

A.

Define a framework of formally appointed governance boards with clearly documented terms of reference to act as decision making bodies, made up of representatives from all divisions of ZYX

B.

Ensure that the future service integrator's contract includes responsibility for establishing a governance framework that describes how the SIAM ecosystem will be managed and operated

C.

Establish a working group with representation from all ZYX divisions to review existing policies and practices, then define a framework of policies, standards processes, roles and structural elements

D.

Update the responsibilities of the IT Steering Group to include responsibility for ensuring that the SIAM ecosystem is implemented in accordance with defined plans and objectives

Previously, there was no common set of performance targets and metrics used across all ZYX companies ZYXH Contract Governance is concerned about this. They would like to see metrics that drive improvement once the transition has been made to a SIAM model.

ZYXS provide a range of services to some ZYX companies The ZYX IT steering group meets every 4 months chaired by the ZYXS IT Director It is attended by representatives from each ZYX company SIAMRUS provided a report for ZYXUK. This included a set of metrics that SIAMRUS have used before with other organizations. ZYXS has been selected to be the internal service integrator in the new SIAM model The ZYXS IT director has provided a set of metrics from an organization that she previously worked for

What is the best way for ZYX to ensure effective metrics are in place to improve services?

A.

At the next IT steering group meeting, agree on a common set of metrics that all service providers must use.

B.

Proceed with the set of metrics that SIAMRUS has previously used with other service providers

C.

Run a pilot with metrics from the ZYXS IT director, involving ZYXS and all service providers

D.

Take the set of metrics currently used by ZYXS and apply them across all service providers

ZYX has used a phased approach for implementing the SIAM model

-ZYXS is the service integrator and provides the service desk for the SIAM ecosystem

-NETSCO had all network services transitioned to them

-OUTSCO has been selected to provide hosting services

The next phase is to transition all services currently hosted by ZYXS and ZYXD to OUTSCO Due to time pressures, it has not been possible to test how the services will perform after transition.

The ZYX CEO is concerned about the risks to the services and the ability of ZYX to be able to carry out its business activities She wishes that an early life support (ELS) function is implemented

What approach should be taken to resolve incidents and problems caused by the transition of services?

A.

Complete the transition over a weekend when the number of people using the services will be low

B.

Ensure that the ZYXS service desk is fully briefed and ready to handle any increase in call and incident volumes

C.

Establish a data room containing all information about the services so that facts and data can be quickly checked

D.

Set up a short-term function with staff from BANKSCO, ZYXS. ZYXD: ZYXG. NET$CO and OUTSCO

The ZYX Board of Directors is considering which SIAM structure should be selected for the ZYX SIAM model

What is most likely to influence the selection?

A.

Planned expansion of ZYX into other countries

B.

The attitude of the ZYXUK Directors

C.

The content of the report from SIAMRUS

D.

Understanding existing capabilities in ZYX

ZYX has decided to create an internal service provider for application development and support This new service provider is formed by merging relevant staff from every ZYX company with the necessary capabilities and skills.

This internal service provider will operate from multiple locations, which enables the provision of year-round 24-hour support.

A capability framework for application development and support is drawn up for the new internal service provider

What will the development of the capability framework help to address?

A.

Establish a process forum for application development and support

B.

Map skill levels for application development and support roles

C.

Support effective working between staff in the different locations

D.

Understand the boundaries and interactions with other service providers

SIAMRUS has created a report that suggests moving to several contracted service providers and an external service integrator ZYX has decided to separate the services into providers for.

-hosting

-networks

-application development and support

-desktop and laptop support

In order to avoid reliance on single providers, the CEO wants to use two different providers for each of these types of services. The CEO also wants to ensure that the costs for the service integrator are as low as possible

It is clear that there is a single structure needed for the service integrator contract.

Which contract structure is the most appropriate for ZYX?

A.

Adopt the same structure for the service provider contracts

B.

Adopt a single structure for the service provider contracts.

C.

Adopt a few different structures for the service provider contracts

D.

Adopt custom structures for each service provider contract

There are many factors that can influence the design of a SIAM model

Which factor will most influence the choice of the SIAM structure for ZYX?

A.

Capabilities of the staff working in the ZYX organizations

B.

Multiple geographical locations of ZYX companies

C.

The report and proposed SIAM strategy from SIAMRUS

D.

Willingness of service providers to be part of the SIAM model