Prepare effectively for your IIBA CBAP Certified Business Analysis Professional certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 7 / 8
Total 497 questions

A large company has thousands of geographically dispersed employees and dozens of IT systems. Multiple business analysts (BAs) work in parallel on various requirements with different stakeholders. When considered in isolation, the requirements look meaningful and valuable to those who approved them. However, when it comes to implementation, some of the requirements appear to be contradicting each other. A lead BA recognizes that adding some traceability information would help uncover such conflicts early in the process.

To what should the BA trace the requirements?

A.

Stakeholder tasks

B.

Business needs

C.

Organizational functions

D.

Solution components

A business analyst (BA) has been coordinating several meetings with stakeholders to reach consensus regarding the solution design to implement a global currency exchange system for an international bank. Consensus has not been reached yet, although BA has great communication skills and is trusted by all stakeholders. The stakeholders formally approved the business need initially.

Why is there disagreement?

A.

The requirements are interpreted differently by each stakeholder.

B.

The requirements are incorrectly traced.

C.

The approval authority for the solution is unclear.

D.

More solution alternatives need to be generated.

Which of the following directs the improvement efforts to those areas that will have the biggest impact?

A.

Flowchart

B.

Gantt chart

C.

Pareto diagram

D.

User Documentation

Which of the following stages of a project defines the number of risks and opportunities, including intense planning and anticipation of risk events?

A.

Planning

B.

Executing

C.

Initiation

D.

Closing

Which of the following requirement attributes lacks any ambiguous characteristics?

A.

Understandable

B.

User Requirements Document (URD)

C.

Unambiguous

D.

Urgency

A multi-domain project has stakeholders with different technical backgrounds. The presentation prepared by the business analyst (BA) for domain 1 was also used for domain 2 but the presentation was not clear and caused concerns for stakeholders in domain 2.

What can the BA do to alleviate the concerns of the stakeholders in domain 2?

A.

Create a survey applicable for the stakeholders in domain 2.

B.

Produce an estimation applicable for the stakeholders in domain 2.

C.

Present a model applicable for the stakeholders in domain 2.

D.

Develop a backlog applicable for the stakeholders in domain 2.

When does the lessons learned document is updated?

A.

At planning phase.

B.

At execution phase.

C.

At closing phase.

D.

Throughout the project lifecycle.

Which of the following software development life cycles is a methodology that divides the project into phases, and the project manager focuses on control of time, cost, and scope?

A.

Spiral

B.

Agile

C.

Waterfall

D.

Incremental

The business process model is also known as.

A.

Organization model

B.

Activity model

C.

Relational model

D.

Data flow model

The business analyst (BA) is facilitating a requirements workshop with a large group of diverse stakeholders, some of whom are not entirely familiar with the goals and objectives of the project.

The BA must understand the business domain, corporate culture, group dynamics, and expected outputs to adequately communicate the:

A.

change strategy.

B.

requirements prioritization.

C.

elicitation scope.

D.

enterprise architecture.

A company that specialized in manufacturing vending machines for books has been in business for 10 years. As the e-book and online retailing grow, the company perceived that a change is required to respond to the new emerging market forces. However, the change should focus on reusability as much as possible to reduce expenses. After analyzing the current state with the business subject matter experts, the business analyst

(BA) proposed investing in a new business line of vending machines that sell pay per use mobile device phone fast charging stations.

Due to the urgency of this change, the BA was asked to finalize requirements elicitation in the shortest possible time.

Customers who want to utilize the pay per use mobile device fast charging stations may choose one of two features: fully charged (F1) or partially charged (F2). If partially charged is selected, the customer needs to specify their charging needs.

What is the relationship between F1 and F2?

A.

Validate

B.

Derive

C.

Depends

D.

Satisfy

A business analyst (BA) at a regional bank has recently been assigned to assist on a project to expand into new markets. The chief executive officer (CEO) envisions the bank as a national brand and has asked the chief financial officer (CFO) to monitor project progress closely. The project manager (PM) has asked the BAs on the team to recommend an appropriate business analysis approach.

Based on the nature of the project and the industry, which approach should they recommend?

A.

An unstructured approach utilizing informal team interaction, model-driven documentation standards, and iterative requirements development

B.

An agile approach with frequent team interaction, adaptive documentation standards, and iterative requirements development

C.

A moderate approach utilizing the bank's existing waterfall project lifecycle and documentation deliverables not requiring formal approval

D.

A formal approach with planned team interaction, agreed upon documentation deliverables requiring formal approval, and front-loaded requirements development

A business analyst (BA) is working on a stakeholder collaboration plan. The main goal is to select the approaches that work best to meet the needs of external and internal stakeholders.

Which aspects should be taken into account?

A.

Collaboration skills of BA

B.

Solution design

C.

Timing and frequency of collaboration

D.

Business governance plan

The business analyst (BA) has been tasked with assessing and recommending the best solution that fits an organization's need for a new third-party sales tool.

What technique would be used for identifying suitable options?

A.

Balanced scorecard

B.

Decision analysis

C.

Vendor assessment

D.

Process analysis

Which of the following is the formal acceptance of the project?

A.

A project review

B.

A sign-off

C.

Risk assessment

D.

Inspection trend analysis

A business analyst (BA) has completed the prioritization of requirements with various risk-averse stakeholder groups. Several requirements conflict with a regulatory requirement that, if not implemented, will result in a fine from a regulatory body.

What should the BA do?

A.

Measure the value of the other requirements against the penalty of not meeting the regulatory requirement

B.

Compare the regulatory requirement to the recommended solution

C.

Determine a means to work around the regulatory requirement

D.

Inform the stakeholders that the regulatory requirement takes precedence over other requirements

Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?

A.

Resource breakdown structure (RBS)

B.

product breakdown structure (PBS)

C.

Budgeted Cost of Work Scheduled (BCWS)

D.

Work Breakdown Structure (WBS)

Which of the following is the comparison of planned project results with actual project results?

A.

Variance analysis

B.

Cost-benefit analysis

C.

Statistical Sampling

D.

Trend analysis

An online stock trading system is under implementation.

Which of the following events can be considered as a trigger for re-prioritization?

A.

A team member has left the project and is being replaced

B.

A new initial public offering in the stock market is introduced

C.

Further dependencies among solution components are uncovered

D.

Number of reported quality defects is growing through phases

Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?

A.

Project manager

B.

Subject matter expert

C.

Solution owner

D.

Stakeholder