Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-200 PMI Agile Certified Practitioner (PMI-ACP) Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMI-200 PMI Agile Certified Practitioner (PMI-ACP) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 6 / 8
Total 482 questions

A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.

What should the agile project leader do?

A.

Add more resources to projects to ensure work sharing.

B.

Encourage the resource to undergo time management training.

C.

Ask management to ensure that the resource is available to only one project at a time.

D.

Allow the resource to continue switching between projects to deliver high customer value.

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

An agile practitioner is in the process of refining requirements. The requirements keep changing based upon with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

A.

Ask the scrum master to help reduce the rate of change.

B.

Work with the agile coach to document the requirements in a collaborative way.

C.

Work with the stakeholder directly rather than go through different layers of people.

D.

Work with the development team to confirm the requirements.

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: "I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles."

What is the agile lead attempting to highlight?

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

The agile practitioner has determined that two different team members are working on addressing the same major issue on the project. How should the agile practitioner address this?

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the kanban board and assign the it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

A.

Communicate the importance of the business need to the team and refine the product backlog.

B.

Ask the team to discuss the changes to the features with the customer.

C.

Meet with the agile team lead to prioritize the requirements.

D.

Discuss and prioritize the requirements with the team.

An agile project leader notices that the team's velocity has decreased in examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses

What can happen as a result?

A.

The team will be unable to understand the iteration's status

B.

The team will be unable to judge the project design's validity

C.

The team cannot give accurate updates to management

D.

Team collaboration cannot be measured effectively

How can an agile team working on a new product ensure alignment with external stakeholders?

A.

Ask the product owner to provide a detailed product specification document

B.

Conduct story-mapping exercises to clarify deliverables and release priorities

C.

Hold a kick-off meeting to assign roles and responsibilities.

D.

Work with the scrum master and stakeholders to ensure agile principles are followed

An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.

How can the scrum master handle this situation?

A.

Work with the product owner to include fewer features in the next sprint planning.

B.

Hire more team members to elevate the team's velocity to increase performance.

C.

Tell the team members that changes are natural and welcome if the project is delivering value.

D.

Schedule more meetings with the team and the product owner to refine the backlog constantly.

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables: however, issues arise when the deliverables are integrated. What should the agile practitioner do?

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

During planning sessions an agile practitioner notices that some team members do not share common ideas What should the agile practitioner do?

A.

Ask the team if they would like to adopt alternative techniques

B.

Create a team norms document to set participation guidelines

C.

Ask the scrum master to resolve the issue at the stand up meeting

D.

Capture feedback during lessons learned at the end of the iteration

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate USS40.000 more than expected for the quarter. What should the agile team do?

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty.

What should the scrum master do?

A.

Explain to the SME the importance of being a team player, that the tasks are assigned by the scrum master, and work should not be refused.

B.

Acknowledge that the SME has a valid point from an efficiency point of view and will perform better staying as a specialist.

C.

Leverage a separate testing team altogether to assist with all testing to ensure consistent results.

D.

Explain to the team the importance of reducing team size by reducing specializations and bottlenecks and that every team member plays an equal part.

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.

How should the scrum master respond?

A.

Project velocity should be stable overtime.

B.

Moving velocity from 27 to 35 is a decrease in productivity.

C.

A burndown chart compares planned versus actual, not velocity.

D.

Velocity is iterative and will only be used for sprint numbers.

A product owner wants to create a release plan given the team is working in a chaotic environment. They want to set expectations about what is likely to be developed and in what timeframe for some of the stakeholders.

What should the product owner include in the release plan to achieve this?

A.

The objective, iterations and underlying features, iteration timelines, other pre-release activities, dependencies, and responsible team.

B.

The key objectives and a brief description of each user story to be delivered in each iteration release timelines and release dependencies

C.

The developer who will work on a specific feature and key DevOgs engineering activities to be performed during each iteration for the code integration.

D.

The sequence of user stories to be developed in each iteration, along with their start and end timelines, dependencies, and responsible team.

A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.

Is this agile strategy appropriate?

A.

Yes, this is a case of sequential development where working in parallel is an accepted strategy in agile to gain time.

B.

Yes, this is a case of hybrid development where a product is divided into components and agile is used for component development and integration.

C.

No, dividing the development team into three separate teams will diminish communication and result in delays.

D.

No the feedback loops are being altered, which can result in big failures and delays

During an interview for an agile team lead for a global company, a candidate is asked: "How do you ensure your project is aligned with the stakeholders' priorities?"

How should the candidate respond?

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Team A is working on the second sprint of a product release Team B which is an interdependent team located on the same floor, requires extensive and frequent information to complete its sprint goal.

What should the agile team lead do?

A.

Create a central repository for information, and provide access to team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide team B with the information on an "as needed" basis

Page: 6 / 8
Total 482 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved