Prepare effectively for your PMI PMI-PBA PMI Professional in Business Analysis certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?
The best way to ensure the integrity of requirements is to:
A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?
A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.
Where can the business analyst best reflect the intangible costs associated with this change?
A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.
From the business analysis perspective, the main reason for this business failure was a failure to:
A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?
A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.
Which of the following is the best strategy to define the appropriate acceptance criteria?
The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?
A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?
A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?
During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?
What should the business analyst do during the first steps of a project?
A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.
Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that
those issues are resolved?
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
The business analyst tells the stakeholder that the requirement status was changed to "deferred ”
What could have prevented the stakeholder from being surprised about the status change?
A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?
A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.
How would the business analyst define the scope of this project?
Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?
A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.
Which technique will allow the business analyst to determine this information?