Prepare effectively for your PMI PMI-SP PMI Scheduling Professional certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 5
Total 323 questions

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

A.

Project Schedule Management Plan

B.

Project Staffing Management Plan

C.

Project Human Resources Management Plan

D.

Project Communications Management Plan

There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?

A.

Scope baseline

B.

Activity attributes

C.

Activity list

D.

Activity resource requirements

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

A.

It is derived from the constraints of the project.

B.

It is assigned to the project by management.

C.

It is created by the stakeholders.

D.

It is developed from the schedule network analysis.

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's planned value?

A.

$2,025,000

B.

There is not enough information to know

C.

$4,500,000

D.

$2,250,000

You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?

A.

Activity attributes

B.

Project management plan

C.

Schedule Management Plan

D.

Roles and Responsibilities Matrix

If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?

A.

You have added lag time to the project activities.

B.

You have added management reserve to the project activities.

C.

You have added lead time to the project activities.

D.

You have added float to the project activities.

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

A.

Schedule data

B.

Work performance information

C.

Project management plan

D.

Project schedule

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what your schedule variance is. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450. What is the schedule variance for this project?

A.

-$45,789

B.

-$56,790

C.

There is not enough information to know.

D.

-$30,268

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

A.

Project document updates

B.

Scope baseline

C.

Cost performance baseline

D.

Project funding requirements

Amy works as a project manager for BlueWell Inc. Her organization wants her to create a new warehouse. Which of the following documents will she create to define the business needs, the project justification, and the current requirements?

A.

Project scope

B.

Feasibility study

C.

Project charter

D.

Work breakdown structure

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

A.

Project scope statement

B.

Milestone list

C.

Project schedule network diagrams

D.

Activity list

Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

A.

$35,000

B.

$41,700

C.

$6,700

D.

$14,000

You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?

A.

Parametric modeling

B.

Analogous

C.

Top-down

D.

Bottom-up

A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.

A.

Performance control

B.

Execution scheduling

C.

Leadership

D.

Feasibility planning

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

A.

Stakeholders are usually identified through a stakeholder register.

B.

Stakeholders are identified by the project team, project sponsor, and management.

C.

Stakeholders are identified through the project customers.

D.

Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.

Which of the following is NOT an output of the control schedule process?

A.

Organizational process assets

B.

Change requests

C.

Project termination request

D.

Project document updates

Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?

A.

- $210,000

B.

- $720,000

C.

- $250,000

D.

- $270,000

Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

A.

Risk response

B.

Team development

C.

Risk mitigation

D.

Corrective action

Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

A.

Risk owner

B.

Harry

C.

Project sponsor

D.

Subject matter expert

Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?

A.

Crash the project.

B.

Add more risk mitigation.

C.

Reduce the amount of labor.

D.

Reduce the project scope.