PRINCE2-Agile-Practitioner PRINCE2 Agile Practitioner Project Management Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PRINCE2 PRINCE2-Agile-Practitioner PRINCE2 Agile Practitioner Project Management Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 1
Total 50 questions

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zerocost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information

The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.

The event village will comprise a number of work packages:

1. Event village design

2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities

3. Stalls which will be sold to local businesses to raise funds for the event:

Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.

There are 30 vendor stalls selling products related to the event.

The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.

4. A car park for 200 cars.

5. Temporary facilities including changing rooms, toilets and shower facilities.

6. Dismantling of the event village and clean up.

The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.

Using the Project Scenario and Event Village Additional information, answer the following question:

A local newspaper has reported the results of a survey. The survey indicated that local residents are concerned that costs from the event may be incurred by local tax payers.

Which action would have helped to avoid this situation?

A.

Publishing updated costs of the event estimated using a points system.

B.

Publishing regularly updated advertisements fisting the organizations that are sponsoring the event.

C.

Sharing the delivery team's updated burn-charts with the local newspaper before the results of the survey were published.

D.

Inviting a representative of the local press to participate and report upon a release review at the end of stage 4.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

Website showing the event details, competition rules, etc.

2. Team Registration functionality:

team name, player's names and ages;

contact information;

payment;

lunch pack requirements (includes any special dietary needs);

car parking requirements.

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

An online knowledge base about healthy lifestyles that includes a discussion forum.

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

The project manager facilitated a visioning workshop to develop the project product description.

Which statement, captured during the workshop, should be recorded in the project product description under the 'Composition' heading?

A.

Team registration should capture: team name, players' names and ages, main contact for team, registration fees, parking and lunch requirements as well providing confirmation of booking.

B.

The website must include the ability for teams to register for the football tournament (team registration).

C.

The website must comply with all relevant data protection legislation.

D.

As the organizer of the football tournament, I must be able to identify which teams have registered (under each age group) so that I can plan the tournament.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

Website showing the event details, competition rules, etc.

2. Team Registration functionality:

team name, player's names and ages;

contact information;

payment;

lunch pack requirements (includes any special dietary needs);

car parking requirements.

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

An online knowledge base about healthy lifestyles that includes a discussion forum.

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

The project manager is creating the stage plan for Stage 3. The project manager is trying to incorporate the Team Registration work package into the stage plan.

How should the stage plan be produced?

A.

Using the velocity from the previous stage, working together with the Scrum Master and team members.

B.

By the project manager, after discussing which website user stories should be delivered.

C.

Using rationalism to estimate the effort to deliver the website sprints during the stage.

D.

By pulling website tasks from the backlog dynamically into the work package as soon as there is capacity.

Which BEST describes an agile method or approach that can be integrated with PRINCE2 Agile?

A.

Encouraging system improvement through visualization and controlling work in progress.

B.

Providing guidance on tailoring any applicable principles, themes and processes.

C.

Reducing quality testing in order to deliver within agreed deadlines.

D.

Favoring processes and tools over individuals and interactions.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.

2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

advertisements:

a radio interview;

production of a hand-out/flyer;

banners and signs to put up around the town and at the event;

the provision of a website and social media content;

promotional posters to be displayed by local businesses.

Using the Project Scenario and Marketing Additional information, answer the following question:

When contributing to the development of the communication management approach, the Marketing Team felt that the only applicable agile technique to be included in the approach was the use of daily stand-ups.

Which reason BEST explains whether this is a suitable entry for 'tools and techniques' in the communication management approach?

A.

It is suitable because the marketing products do NOT suit the use of other agile techniques.

B.

It is suitable because the marketing products are already rich in communication.

C.

It is unsuitable because the other teams will need a means to be updated on progress and feedback.

D.

It is unsuitable because the daily stand-up is NOT a communication tool or technique.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre oftown has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

Website showing the event details, competition rules, etc.

2. Team Registration functionality:

team name, player's names and ages;

contact information;

payment;

lunch pack requirements (includes any special dietary needs);

car parking requirements.

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

An online knowledge base about healthy lifestyles that includes a discussion forum.

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

The following assessment was made initially during the 'starting up a project' process:

'The Website Team is already using Scrum and it is expected that this team will be familiar with agile techniques. However, the Staff Training Team is less familiar with the agile ways of working.'

Training on agile techniques was given to the Staff Training Team as a result of this assessment.

As part of the 'closing a project" process, the following observation was made:

'The Staff Training Team gained more understanding of what to fix and what to flex as the project moved into Stage 3.'

Why should this observation appear in the end project report?

A.

The end project report should sum up the results of each timebox and stage.

B.

The end project report should hand over the remaining Could Haves to operational staff.

C.

The end project report should review the use of the Agilometer and the agile ways of working.

D.

The end project report should review how much scope was delivered by the project.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

Website showing the event details, competition rules, etc.

2. Team Registration functionality:

team name, player's names and ages;

contact information;

payment;

lunch pack requirements (includes any special dietary needs);

car parking requirements.

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

An online knowledge base about healthy lifestyles that includes a discussion forum.

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

The Apps and Social Media work package includes the following requirements:

1. Fitness app - Must Have

2. Healthy eating app - Should Have

The burn-down chart is showing an ever-increasing negative gap between the ideal rate of progress and what has actually been delivered. The team manager decided not to deliver the healthy eating app. However, it is still forecast that requirement 1 cannot be completed within the current timebox.

The team manager escalated the issue to the project manager who instructed the team manager to immediately remove the burn-down chart from the information radiator.

What BEST explains how this approach applies the 'manage by exception' principle while taking into account the PRINCE2 Agile behaviours?

A.

It applies the principle well because the project manager will now decide how to proceed with the issue.

B.

It applies the principle well because the project manager's decision helps the Website Team self-organize within the constraints of the work package.

C.

It applies the principle poorly because the Website Team should be empowered to deal with issues relating to the work package.

D.

It applies the principle poorly because everyone in the Website Team should be aware that the work package is outside of tolerance.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information

The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.

The event village will comprise a number of work packages:

1. Event village design

2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities

3. Stalls which will be sold to local businesses to raise funds for the event:

Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.

There are 30 vendor stalls selling products related to the event.

The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.

4. A car park for 200 cars.

5. Temporary facilities including changing rooms, toilets and shower facilities.

6. Dismantling of the event village and clean up.

The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.

Using the Project Scenario and Event Village Additional information, answer the following question:

The typical approach to planning taken by the Event Village team is for the plans to be developed by the project manager and the Event Village team manager, and then presented to the team.

Which setting on the Agilometer is the MOST appropriate to reflect this approach?

A.

Medium/High for 'level of collaboration' because the team manager has been involved throughout the planning process.

B.

Medium/High for 'ability to work iteratively and deliver incrementally' because of the use of the feedback loop involving the team.

C.

Low/Medium for 'acceptance of agile' because the teams understanding of an agile way of working could be improved.

D.

Low/Medium for 'ease of communication' because this form of communication is too formal.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

Website showing the event details, competition rules, etc.

2. Team Registration functionality:

team name, player's names and ages;

contact information;

payment;

lunch pack requirements (includes any special dietary needs);

car parking requirements.

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

An online knowledge base about healthy lifestyles that includes a discussion forum.

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

There are several work packages being delivered during Stage 4. The Website Team Scrum Master is concerned that project-level issues may be overlooked and this might impact the Website Team during the current timebox.

Which agile way of working can be used as part of the 'controlling a stage' process to ensure that these issues are identified?

A.

Scrum of Scrums.

B.

Retrospectives.

C.

MoSCoW.

D.

User stories.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.

2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

advertisements:

a radio interview;

production of a hand-out/flyer;

banners and signs to put up around the town and at the event;

the provision of a website and social media content;

promotional posters to be displayed by local businesses.

Using the Project Scenario and Marketing Additional information, answer the following question:

Which approach BEST outlines how to apply the 'continued business justification' principle during the initiation stage?

A.

Plan to publish a simple advertisement within a few days of timebox one to get feedback.

B.

Request that the Head of the LGA confirms that the funding is available.

C.

Plan a 'Design the Best Poster' competition in schools to encourage fitness awareness in children.

D.

Define a brief for the marketing campaign with costings for the use of each marketing approach.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

Website showing the event details, competition rules, etc.

2. Team Registration functionality:

team name, player's names and ages;

contact information;

payment;

lunch pack requirements (includes any special dietary needs);

car parking requirements.

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

An online knowledge base about healthy lifestyles that includes a discussion forum.

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

The Scrum Master has been advised by the supplier subject matter expert that the five day task of building the social media website is now almost complete - there is just one more day's work to do.

How should this be shown on the burn-down chart?

A.

The work remaining should be the difference between work completed and work left to be done.

B.

The task should be shown as 80% complete as there is only one day's worth of effort left.

C.

The task should be marked as almost complete as there is less than one day's worth of effort left.

D.

The task should NOT be updated until the task has been completed.

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information

The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.

The event village will comprise a number of work packages:

1. Event village design

2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities

3. Stalls which will be sold to local businesses to raise funds for the event:

Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.

There are 30 vendor stalls selling products related to the event.

The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.

4. A car park for 200 cars.

5. Temporary facilities including changing rooms, toilets and shower facilities.

6. Dismantling of the event village and clean up.

The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.

Using the Project Scenario and Event Village Additional information, answer the following question:

It has been agreed that supervised access to the vendor stalls will only be allowed between 16:00 and 20:00 on the day before the event to allow set-up.

Which is the BEST means of communicating these arrangements to all of the vendors?

A.

Using visualizations in the form of diagrams and pictures.

B.

By e-mailing everyone and asking for confirmation of receipt.

C.

By telephone to discuss the arrangements with each stall holder.

D.

Face to face in a workshop to enable discussion.