Prepare effectively for your PRINCE2 Prince2-Foundation PRINCE2 7 Foundation written Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
What is a purpose of the communication management approach?
What statement describes how the project manager should ensure effective communication within a project?
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
How does PRINCE2 ensure that the specific management needs of an organization are met?
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?
In which step of the Issue management’ technique should Superseded versions be archives?
According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?
How is Uncertainty Identified, assessed and controlled?
Which feature of a stage plan suggests that a project is in danger of scope creep?
Which statement BEST describes how approved plans enable control?
Which is a description of a purpose of the 'managing product delivery’ process?
According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?
What is a purpose of the ‘quality’ practice?
As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of 'business case management' technique should the project manager assess this?
How does product-based planning help to determine the project approach?
In which process are the key decisions to control the project made?
Which TWO are objectives of the 'closing a project’ process?
1. To confirm to the project board that each stage’s products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
When is a work breakdown structure MOST useful?