Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PSP AACE International Planning & Scheduling Professional (PSP) Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your AACE International PSP Planning & Scheduling Professional (PSP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 4
Total 216 questions

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?

A.

A bar chart cannot accurately reflect the impact of changes in durations or logic to the baseline

B.

A bar chart is always an oversimplified view of the project schedule

C.

A tor chart does not show all the activities required to construct the project

D.

A bar chart does not show whether the project with be completed within the allowable time

How many work days does it take to move the product from testing to sale?

A.

60.

B.

70.

C.

100.

D.

90.

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

A.

Proceed with company processes even if they conflict with the client

B.

The client contract specifications always have priority

C.

Review any differences and negotiate workable specifications

D.

Suggest that the client issue a change order, accepting the contractor's processes

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects

Schedule forecasts are periodically conducted to project the project schedule performance at completion Which of the following situations would probably result in an incorrect forecast?

A.

The cost variance

B.

The profit or loss for the project

C.

The variance at completion

D.

The schedule variance

Background

Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.

It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.

You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.

With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.

In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.

1. Pull the project team together and ensure everyone understands which activities are on the critical path. Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.

2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.

3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.

4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.

Assignment

Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:

a. the current problem and potential impact(s);

b. each course of action, stating advantages and disadvantages as appropriate;

c. your recommendations, properly supported.

Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).

While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.

Take time to read the problem and consider what you want Evan to say. Good luck!

Determine the driving activity for Activity 10001.

A.

Activity 11001.

B.

Activity 10002.

C.

Activity 9005.

D.

There is no driving activity for Activity 10001 in the backward pass.

How many entities/subcontractors should a scheduled activity cover?

A.

More than one it the activity is in a single calendar period

B.

More than one it the subcontractors agree

C.

Only one

D.

More than one if the concurrent work cannot be split between subcontractors

What activities are concurrent to Activity 2001 in the "normal" schedule?

A.

7001.

B.

1001.

C.

1000.

D.

2003.

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Which of the following phases does NOT describe the commonly accepted construction life cycle?

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Which of the following is not an internal stakeholder?

A.

Owner

B.

installer

C.

Subcontractor

D.

Prime Contractor

What is the relationship depicted between Activity G and Activity H?

A.

You cannot tell with the supplied information.

B.

Start-to-start.

C.

Finish-to-start.

D.

Finish-to-finish.

What problems can a soils engineer deal with on a project?

A.

Survey error.

B.

Hidden subsurface conditions.

C.

Archeological findings.

D.

Toxic soils.

Determine the correct formula and date for the late start for Activity 9001.

A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 -> 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 -> 11-20-02.

You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?

A.

Group schedule activities together based on their start dates

B.

Display detailed information regarding the sequencing of activities in the schedule

C.

Organize reports to group related work activities

D.

Display resources me contractor plans to use on each activity

Which of the following is the most important scheduling consideration for the BILCO contractual scope?

A.

Logical phasing lies

B.

Update frequency

C.

Conforming CPM schedule to SDOT standards

D.

Cost loading

What changes to logic would eliminate Activity B from the critical path?

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

Page: 3 / 4
Total 216 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved