Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PSP AACE International Planning & Scheduling Professional (PSP) Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your AACE International PSP Planning & Scheduling Professional (PSP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 4
Total 216 questions

Which of the following is NOT true?

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?

A.

The activity with the highest sensitivity.

B.

The activity with the longest duration.

C.

The activity with the lowest total float value.

D.

The activity with the highest resource loading.

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

A.

263 CY

B.

368 CM

C.

201 CY

D.

306 CY

Project delays are best analyzed

A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

A.

$271,000

B.

$299,000

C.

$139,000

D.

$289,000

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

A.

30 lifts

B.

133 lifts

C.

42 lifts

D.

60 lifts

If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

A.

12.

B.

14.

C.

13.

D.

Cannot be determined.

What defines a KPI?

A.

Phase milestones

B.

Initiation of a weather risk window

C.

Key discrete project final or interim goals

D.

Interim milestones related to weather phasing

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

A.

Budget at completion (BAC)

B.

Budgeted cost of work performed (BCWP)

C.

Estimate to complete (ETC)

D.

Estimate at completion (EAC)

The BEST reason to use multiple calendars is to:

A.

more accurately show how the project will be built

B.

allow each specialty contractor to have a unique schedule of work/non-work periods

C.

track owner activities according to their specific calendar in order to develop a good

working relationship

D.

evaluate float for the benefit of the contractor

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

A.

2 cranes

B.

1 crane

C.

4 cranes

D.

3 cranes

Identify the minimum project duration.

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Project Life Cycle Phases do NOT include the following item:

A.

procurement

B.

budgeting

C.

design

D.

start-up

Baseline schedule can be submitted only__________.

A.

at the beginning or the construction

B.

once the project gets impacted try change

C.

once the design for the construction gets approved

D.

once the safety quality and insurance requirements are met

What are Phases based on and derived from?

A.

Resources

B.

Constructability

C.

Score of Work

D.

Budget

Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?

A.

$195 per day

B.

S1.772 per day

C.

General conditions do not need to be reduced to break even

D.

$1.223 per day

Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

A.

After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B.

After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C.

After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

: 20

Constraints control events or activities that __________________.

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Page: 2 / 4
Total 216 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved