Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

PSP AACE International Planning & Scheduling Professional (PSP) Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your AACE International PSP Planning & Scheduling Professional (PSP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 3
Total 163 questions

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

A.

30 lifts

B.

133 lifts

C.

42 lifts

D.

60 lifts

What method offers the best chance of the schedule being used effectively to implement the project in the field?

A.

Issue detailed schedule updates as frequently as possible.

B.

Obtain consent and agreement to the schedule from the key project personnel.

C.

Include detailed and stringent set of scheduling specifications in the contract.

D.

Allow large time contingencies on milestones and completion deadlines.

Each of the following accurately describes total float in a schedule EXCEPT:

A.

The amount of time an activity can be delayed without delaying the overall project completion time.

B.

Can be positive or negative.

C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

The data date or status date of a schedule represents the:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based

What was the original planned duration for Activity A through Activity G?

A.

26.

B.

28.

C.

24.

D.

25.

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

A.

06-11-02.

B.

06-04-02.

C.

06-18-02.

D.

06-05-02.

How could the structural steel drawing delay have been prevented?

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

Activity C is a

A.

Contentious activity.

B.

Continuous activity.

C.

1-day activity.

D.

Milestone.

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

Determine the correct formula and date for the late start for the Activity 11001:

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

A.

Delay product release by 5 days.

B.

Expedite packaging by 5 days.

C.

Expedite printing by 5 days.

D.

Delay manufacturing by 5 days.

Estimate to complete (ETC) is __________________.

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work

An early start constraint dictates

A.

An activity's remaining duration.

B.

The planned start of a successor activity

C.

The planned start of an activity.

D.

The actual start of an activity.

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

What is a key first step in developing a critical path method schedule?

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

Page: 2 / 3
Total 163 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved