PSP AACE International Planning & Scheduling Professional (PSP) Exam Free Practice Exam Questions (2025 Updated)
Prepare effectively for your AACE International PSP Planning & Scheduling Professional (PSP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?
What method offers the best chance of the schedule being used effectively to implement the project in the field?
Each of the following accurately describes total float in a schedule EXCEPT:
The data date or status date of a schedule represents the:
What was the original planned duration for Activity A through Activity G?
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
How could the structural steel drawing delay have been prevented?
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
Activity C is a
The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
Determine the correct formula and date for the late start for the Activity 11001:
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
Estimate to complete (ETC) is __________________.
An early start constraint dictates
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
What is a key first step in developing a critical path method schedule?