Adobe AD0-E903 Practice Test Questions Answers

Exam Code: AD0-E903 (Updated 70 Q&As with Explanation)
Exam Name: Adobe Workfront Project Manager Professional
Last Update: 04-Jul-2025
Demo:  Download Demo

PDF + Testing Engine
Testing Engine
PDF
$50.75   $144.99
$38.5   $109.99
$35   $99.99

Questions Include:

  • Single Choice: 66 Q&A's
  • Multiple Choice: 4 Q&A's

  • Reliable Solution To Pass AD0-E903 Adobe Workfront Certification Test

    Our easy to learn AD0-E903 Adobe Workfront Project Manager Professional questions and answers will prove the best help for every candidate of Adobe AD0-E903 exam and will award a 100% guaranteed success!

    Why AD0-E903 Candidates Put Solution2Pass First?

    Solution2Pass is ranked amongst the top AD0-E903 study material providers for almost all popular Adobe Workfront certification tests. Our prime concern is our clients’ satisfaction and our growing clientele is the best evidence on our commitment. You never feel frustrated preparing with Solution2Pass’s Adobe Workfront Project Manager Professional guide and AD0-E903 dumps. Choose what best fits with needs. We assure you of an exceptional AD0-E903 Adobe Workfront Project Manager Professional study experience that you ever desired.

    A Guaranteed Adobe AD0-E903 Practice Test Exam PDF

    Keeping in view the time constraints of the IT professionals, our experts have devised a set of immensely useful Adobe AD0-E903 braindumps that are packed with the vitally important information. These Adobe AD0-E903 dumps are formatted in easy AD0-E903 questions and answers in simple English so that all candidates are equally benefited with them. They won’t take much time to grasp all the Adobe AD0-E903 questions and you will learn all the important portions of the AD0-E903 Adobe Workfront Project Manager Professional syllabus.

    Most Reliable Adobe AD0-E903 Passing Test Questions Answers

    A free content may be an attraction for most of you but usually such offers are just to attract people to clicking pages instead of getting something worthwhile. You need not surfing for online courses free or otherwise to equip yourself to pass AD0-E903 exam and waste your time and money. We offer you the most reliable Adobe AD0-E903 content in an affordable price with 100% Adobe AD0-E903 passing guarantee. You can take back your money if our product does not help you in gaining an outstanding AD0-E903 Adobe Workfront Project Manager Professional exam success. Moreover, the registered clients can enjoy special discount code for buying our products.

    Adobe AD0-E903 Adobe Workfront Practice Exam Questions and Answers

    For getting a command on the real Adobe AD0-E903 exam format, you can try our AD0-E903 exam testing engine and solve as many AD0-E903 practice questions and answers as you can. These Adobe AD0-E903 practice exams will enhance your examination ability and will impart you confidence to answer all queries in the Adobe AD0-E903 Adobe Workfront Project Manager Professional actual test. They are also helpful in revising your learning and consolidate it as well. Our Adobe Workfront Project Manager Professional tests are more useful than the VCE files offered by various vendors. The reason is that most of such files are difficult to understand by the non-native candidates. Secondly, they are far more expensive than the content offered by us. Read the reviews of our worthy clients and know how wonderful our Adobe Workfront Project Manager Professional dumps, AD0-E903 study guide and AD0-E903 Adobe Workfront Project Manager Professional practice exams proved helpful for them in passing AD0-E903 exam.

    All Adobe Workfront Related Certification Exams

    Total Questions: 51
    Updated: 04-Jul-2025
    Total Questions: 0
    Updated: 04-Jul-2025
    Available Soon
    Total Questions: 0
    Updated: 07-Jul-2025
    Available Soon

    AD0-E903 Questions and Answers

    Question # 1

    A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

    A.

    Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

    B.

    Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

    C.

    Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

    Question # 2

    An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?

    A.

    Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. From the Reporting Settings dropdown, add a prompt for Portfolio Name.

    B.

    Visit the Reports area and create a new Project report. Group the results by Portfolio Name. Add a column for Actual Cost and summarize this column by SUM.

    C.

    Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. Group the results by Portfolio Name.

    Question # 3

    Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

    A.

    Status

    B.

    Condition

    C.

    Progress Status

    Question # 4

    Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

    What may have caused the planned start date of Task 2 to remain the same?

    A.

    The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

    B.

    The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

    C.

    The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

    D.

    The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

    Question # 5

    Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

    A.

    Critical Path

    B.

    Baselines

    C.

    Milestones