Prepare effectively for your APICS CPIM-ECO Execution and Control of Operations certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 2
Total 105 questions

Which of the following project characteristics would suggest using the PERT technique, rather than the critical path method?

A.

Estimates of individual task times are probabilistic.

B.

Project tasks are backward scheduled.

C.

Due dates are needed to identify critical tasks.

D.

Project management can determine the critical path.

The actual output of a work center for a given time period can be determined by evaluating the:

A.

number of standard hours in the queue.

B.

number of standard hours per units produced.

C.

number of machine hours.

D.

amount of rated capacity less rework.

Which of the following activities takes place during prototype production and testing?

A.

Customer acceptance is emphasized.

B.

The complete product is produced in low-volume pilot runs.

C.

Delivery schedules for components and subassemblies are established.

D.

The qualification of suppliers begins.

A company is gathering data as to why the machine is consistently shutting down. What methodology should a company pursue first?

A.

5S

B.

Plan-do-check-act

C.

Kaizen event

D.

Statistical process control

Which of the following terms describes a management technique used to evaluate planned changes to production processes?

A.

Analysis of variance

B.

Theory of constraints

C.

Design of experiments

D.

Design for manufacturability

Important and measureable characteristics of a product or process whose performance targets are set by the customer is:

A.

voice of the customer.

B.

customer-as-participant.

C.

critical-to-quality.

D.

concurrent engineering.

During a soldering operation some components were getting damaged due to high temperatures. A fix to eliminate the defect was put into place, which resulted in a(n):

A.

SPC study.

B.

6 sigma process.

C.

poka-yoke.

D.

100% inspection.

With vendor managed inventory, a supplier must obtain which of the following data from the customer to ensure high service levels?

A.

Average quantity per shipment

B.

Average inventory level

C.

Inventory consumption

D.

On-time delivery percentage

A company produces a part with a nominal diameter of 2.0 inches and a tolerance of ± 0.006 with a standard deviation of 0.001 inches. A sample has the average diameter of 1.996 inches with a standard deviation of 0.001 inches. What is the CPK and process capability?

A.

0.667, capable

B.

0.667, not capable

C.

0.333, capable

D.

0.333, not capable

Which of the following concepts is a reason to create a visual factory?

A.

They are more successful because visual systems are more robust.

B.

They are inexpensive to implement.

C.

They are more successful because they display well for customer visits.

D.

They are successful because they are self-explaining and self-improving.

What management approach is based on the participation of all members of an organization in improving processes, and culture in which they work?

A.

Total Quality Control

B.

Total Quality Engineering

C.

Total Quality Management

D.

Total Waste Management