Prepare effectively for your ATLASSIAN ACP-610 Managing Jira Projects for Data Center and Server Certification certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 2
Total 75 questions

Currently, the Done column of the Finance board shows all issues ever completed, regardless of age. Now, the team wants to do a periodic clean-up of the Done column.

• They want to do the clean-up whenever it is needed on an ad-hoc basis.

• They want to be able to report on all the issues that were removed during each clean-up.

Which solution meets their need?

A.

remove issues as needed using the Release link

B.

exclude issues in Done status from the board filter

C.

exclude issues in Done status via a sub-filter

D.

exclude issues where Resolution != EMPTY from the board filter

Which statement is definitely true about sub-tasks being used on a Scrurn board?

A.

Sub-task estimations are rolled up and displayed as the Original Estimate on the parent card.

B.

Sub-tasks can only be created by board administrators

C.

Sub-tasks can be displayed as cards in the Active sprints view.

D.

Sub-tasks can be displayed as cards in the Backlog view.

E.

Sub-tasks will automatically get resolved when the parent is moved to the Done column.

The head of customer service wants to identity potential bottlenecks in the support workflow of her teams in the last three months. Which report provides this information?

A.

Created vs. Resolved Issues Report

B.

Time Since Issues Report

C.

Cumulative Flow Diagram

D.

Resolution Time Report

E.

Average Age Report

The extract of a permission scheme for a project is shown below.

Clare is joining your team and needs to:

• analyze incoming requests with her initials tagged to a label

• re-assign requests to subject matter experts

Which project role does Clare need?

A.

Assigners

B.

Viewers

C.

Administrators

D.

Assignables

E.

Workers

F.

Editors

You manage a Scrum project with two development teams.

Issues are associated with each team using a custom field called Jean.

Parallel sprints have been disabled.

Which setup will provide each team with an individual Burndown Chart?

A.

a single Scrum board with quick filters

B.

a single Scrum board using the Team field as the Estimation Statistic

C.

two Scrum boards using the Team field as the Estimation Statistic

D.

two Scrum boards using the Team field in their board filters

You are responsible for three software products with individual release cycles.

Each product is managed in a different project.

Which report can provide an instant progress overview of all fix versions across all projects?

A.

Release Burndown

B.

Pie Chart Report

C.

Version Workload Report

D.

Version Report

E.

Single Level Group By Report

Paul and Tessa are in the Auditors role of every project.

You need to write a JQL query that shows Issues reported by either of them that are still unassigned.

Select the correct JQL query.

A.

Reporter IN (Paul, Tessa) AND Assignee IS EMPTY

B.

Reporter IN (Auditors) AND assignee - EMPTY

C.

Reporter IN membersOfCAuditors") AND assignee = NULL

D.

Reporter IS Paul OR Reporter IS Tessa AND Assignee IS NULL

E.

(Reporter - Paul OR Reporter – Tessa) AND Assignee - Unassigned

Some issues in your project have labels and others do not.

Some tasks in your project are identified by a distinct label: daily_business. You need to prevent these issues from being displayed on the team's Scrum board

Which solution meets this requirement?

A.

• Create a quick filter

• Add: NOT labels="daily_business_

B.

• Update the board sub-filter

• Add; AND NOT labels = daily business

C.

• Update the board filter

• Add: AND labels NOT IN (daily.business, EMPTY:

D.

• Update the board filter

• Add: AND (labels != daily, business OR labels IS EMF

Which statementis definitely true about priorities in Jira?

A.

Project administrators can re-order existing priorities in their projects.

B.

Project administrators can create new priorities in their projects.

C.

The same set of priorities is always available in each project.

D.

Jira administrators can create and update global priorities.

Which statementis true about Jira attachments?

A.

Users can search for issues that contain attachments

B.

Users need Work On Issues permission to remove attachments.

C.

Users need Edit Issues permission to add attachments.

D.

Project administrators can disable attachments through project settings.

Analyze the Epic Report shown.

Identify why the epic completion date is hard to predict.

A.

Most stories aren't estimated until the end of the epic

B.

The configured Working Days for the board are unrealistic.

C.

The team is using issue count for their estimation statistic.

D.

The team adds new stories throughout the epic.

Your team has been completing work on a fully estimated epic in each of the last four sprints.

Your product owner wants you to predict how many additional sprints will be needed to complete it.

Which single report can provide the information?

A.

Epic Burndown

B.

Sprint Report

C.

Release Burndown

D.

Epic Report

Savresh can create issues and assign them to anyone in the Testers group. However, they cannot re-assign issues to Savresh. What are two possible reasons for this? (Choose two.)

A.

Savresh needs to be a component lead.

B.

Testers need Edit Issues permission.

C.

Savresh needs to be a project lead.

D.

Testers need Assignable User permission.

E.

Testers need Assign Issues permission.

F.

Savresh needs Assignable User permission.

You need to display data on a dashboard that shows the correlation between the following:

• the number of days that issues have been open

• the number of comments on the issues

• the number of participants on the issues

Identify the single gadget that meets these requirements.

A.

Heat Map

B.

Bubble Chart

C.

Activity Stream

D.

Issue Statistics

E.

Voted Issues

You need a field that:

• allows different options in different projects

• allows options to be disabled where necessary

• allows only a single value

• allows a default value to be configured

Which field meets these requirements?

A.

Select List (single choice)

B.

Checkboxes

C.

Component/s

D.

Labels

Sam and Jo are product managers responsible for two separate products. Each product has its own Jira project and a corresponding Scrum board.

Management requests an integration between the products. Sam and Jo decide to create all the integration-related issues in Sams project and label them integration".

Jo updated his Scrum board's saved filter to include the relevant integration issues from Sam's project.

Which statement is definitely true?

A.

All integration issues always appear on top of Jo's backlog.

B.

Changes to the rank of integration issues on Jo's board are reflected on Sam's board.

C.

Jo is unable to rank integration issues created by Sam.

D.

Sam is unable to transition integration issues that were ranked by Jo.

E.

Integration issues can only be ranked on Sam's board.

The team requests that you update the name of your project. What impact will this have on Jira?

A.

The URL for issues will change.

B.

The project key will change.

C.

Issue filters may need to be updated.

D.

Issue search will not find issues from that project until Jira is re indexed.

Gen prioritizes and triages support requests as soon as they come in. She now wants to use drag-and-drop to:

• quicklyassign and transition them to in Progress

• instantly associate them with Epics

Which board view will meet these requirements?

A.

Scrum backlog

B.

Kanban board

C.

Kanban backlog

D.

Active sprints

A Scrum board contains issues from a single project. An extract of the project's permission scheme is shown.

Who can definitely see the Scrurn board and rank issues?

A.

any member of Developers role with Jira Software application access

B.

any logged in user

C.

member of both Developers role and Product Owner role

D.

any member of Developers role

You want to report on your team's performance to the stakeholders. View one of the reports for your team:

Based only on the report shown, which statement about your teams performance is definitely true?

A.

Your team is not estimating their work accurately.

B.

Your team sometimes commits more work than it can complete in an iteration.

C.

Your team is committing unestimated work to an iteration.

D.

Scope change is affecting the team's ability to complete work on time.

E.

Your team is using sprint duration inconsistently

Page: 1 / 2
Total 75 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved