Prepare effectively for your BCI CBCI Certificate of the Business Continuity Institute (CBCI) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 3
Total 176 questions

In relation to maintaining a Business Continuity (BC) culture, the first few minutes of every Business Continuity (BC) workshop and presentation can be used by the BC professional to:

A.

Allocate additional new BC responsibilities to participants

B.

Reconnect participants to the organization and raise awareness of the benefits of protecting the organization from harmful disruptions

C.

Demonstrate to participants how successful top management has been in addressing risks

D.

Enable the BC professional to re-design procedures and solutions

Horizon scanning, cost-benefit analysis, and consulting with information from risk assessments are examples of activities undertaken when:

A.

Establishing the Business Continuity Management System (BCMS)

B.

Defining the initial scope of the BCMS

C.

Developing the Business Continuity (BC) policy

D.

Assessing the viability of BC strategies and solutions

During the process of strategy determination as part of solutions design, the Business Continuity (BC) professional should consider and select solutions to deliver agreed strategies in partnership with the:

A.

Finance director

B.

Department representative

C.

Relevant product, activity or resource owner

D.

Incident response team leader

Which method of measuring culture requires periodic checks to determine the percentage of the organization's personnel currently covered by existing Business Continuity culture initiatives?

A.

Unstructured observation

B.

Culture index

C.

Behavioural consistency

D.

Business Continuity awareness

When establishing a Business Continuity Management System (BCMS), engagement with stakeholders is important. Which of the following is NOT a reason for engaging with internal stakeholders?

A.

Existing policies and procedures may be relevant to the BCMS so early identification will reduce the risk for duplication of work

B.

Early collaboration with colleagues will engage them in the process and secure support for the ongoing development and implementation of the BCMS

C.

Engagement of stakeholders will reduce the potential for conflict at later stages of the programme

D.

Involving stakeholders will reduce the workload and responsibilities of the Business Continuity Professional as administrative activities can be delegated to other staff

Which of the following statements about the methods used to collect information following an exercise is correct?

A.

Only senior level exercise participants should provide opinions during the debrief

B.

One-on-one interviews with all exercise participants should be conducted within one month following the exercise

C.

A hot debrief should be conducted within one month after the conclusion of an exercise

D.

Surveys are especially effective if an exercise and its participants are spread out over multiple locations

Within the context of risk assessment, the identification of solutions is influenced by a variety of business relevant considerations, including:

A.

Delivering performance targets

B.

Timely production of quality assurance audit trails

C.

Compliance with regulatory requirements

D.

Ensuring that communication protocols are observed

Which of the following is an indicator of an improved Business Continuity (BC) culture?

A.

Top management no longer needs to engage in Business Continuity (BC) activities as personnel have embraced BC and others have taken the lead.

B.

Trained internal personnel are in place and are committed to maintaining Business Continuity (BC).

C.

External experts have been appointed to design and implement solutions without the need to involve the personnel engaged in the activities.

D.

Business continuity plans are developed when time is available and are stored securely in case they are needed in the future.

Strategies to resume business operations following a disruption are based on the outcomes of the:

A.

Negotiations with stakeholders regarding their minimum requirements in a disruption

B.

Governance structures established for the Business Continuity Management System (BCMS)

C.

Analysis of Maximum Tolerable Period of Disruption (MTPD) and Recovery Time Objectives (RTO)

D.

Collaborations generated by the organization's Business Continuity culture

The Recovery Time Objective (RTO), competency of team members, and complexity of the processes to be recovered are factors that will play a role in determining the level of detail contained in:

A.

Operational plans

B.

Strategic plans

C.

Crisis communication plans

D.

Emergency response plans

In relation to Business Continuity (BC) solutions, which of the following would be included in the procedure for communications with people outside of the organization during a disruption?

A.

Clarification that all personnel have the responsibility of keeping social media information up to date and should treat this as a priority activity

B.

Identification of the team, group or individual with the responsibility, authority and technical knowledge to deliver communications via each available method

C.

Instruction that external communications should not take place until after the incident is over

D.

Permission for communications personnel to make decisions on how the organization is represented in a crisis without prior agreement with top management

Which of the following would be the most effective and motivating way to share information that is intended to influence personnel to embrace Business Continuity?

A.

Use language that is clear and easily accessible to all when producing documents, presentations or training materials

B.

Provide detailed explanations on all of the organization and set regular tests to ensure that personnel are taking sufficient interest

C.

Ensure that attendance at meetings is recorded and reflected in the staff performance appraisals

D.

Send all information via email or the intranet on the assumption that this will be everyone’s preferred, and most convenient, form of communication

Which of the following solutions in the context of building and work environment resources would support a strategy of relocating operations to another work area belonging to the organization should an incident occur?

A.

Re-purpose work areas and facilities to enable working arrangements for organization personnel during a disruption

B.

Contract former employees and contractors to undertake work at the replacement during a disruption

C.

Create a separate supply chain to support the alternative site in the case of an incident occurring

D.

Advise personnel that they will have to work around the existing workstations and equipment in the alternative site as it will be an emergency situation

Reading the organization's mission statement, annual reports, corporate social media accounts, or newsletters can contribute to building a better understanding of the organization’s:

A.

Business Continuity Management System (BCMS)

B.

Emergency Response Strategy

C.

Culture

D.

Crisis Communication plan

Which of the following is a technique for collecting Business Impact Analysis (BIA) information?

A.

Workplace observation

B.

Workplace health and safety reviews

C.

Monthly budget reviews

D.

Questionnaires and surveys

Which of the following is a possible outcome of a gap analysis to establish whether new strategies and solutions are required?

A.

Validation exercises to confirm the findings of the gap analysis that can be presented to top management as part of the decision-making process

B.

Agreement from top management that a Business Impact Analysis (BIA) should be completed to determine the new procedures required

C.

A determination that Business Continuity capabilities exceed requirements and resources could be redistributed

D.

A schedule for sharing the outcomes with all personnel to invite their comments and encourage them to embrace Business Continuity

Which of the following actions will lead to the protection of priority activities with respect to their Recovery Time Objectives (RTOs) and will limit the impacts of disruptions to prioritised activities?

A.

Conducting a risk assessment

B.

Conducting an Activity Business Impact Analysis (BIA)

C.

Creating a set of approved strategies and solutions to mitigate unacceptable risks and single points of failure

D.

Grouping unacceptable risks and single points of failure by owner and having discussions with each activity and resource owner

In relation to validation, what is meant by review?

A.

The process for assessing the suitability, adequacy, and effectiveness of the Business Continuity Management System (BCMS) and identifying opportunities for improvement

B.

The process to ensure that personnel have embraced business continuity and are complying with requirements

C.

The ability of an organization to develop business continuity solutions and to train personnel to implement them effectively

D.

The process to identify an event that could lead to disruption

The professional practice that aims to measure the competence of individuals, team cohesiveness and the effectiveness of Business Continuity (BC) capability is:

A.

Solutions Design

B.

Analysis

C.

Validation

D.

Enabling Solutions

When implementing solutions so that they can be deployed to respond to disruption, the Business Continuity professional should:

A.

Review and revise the specifications for each solution developed in the design phase prior to launching them

B.

Work with the teams who will utilize the solutions to develop any new systems or tools required to enable implementation

C.

Allocate implementation to the relevant teams and instruct them to manage the implementation as they see fit and to their own timelines

D.

Empower the implementation team to make changes to specifications without referring back to top management