RCDDv14.1 BICSI Registered Communications Distribution Designer – RCDDv14.1 Free Practice Exam Questions (2025 Updated)
Prepare effectively for your BICSI RCDDv14.1 BICSI Registered Communications Distribution Designer – RCDDv14.1 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects.
Where should the program manager incorporate this input?
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end What should be completed first to close all appropriate contracts?
A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results'?
Key performance indicators
B. Benefits management plan
C. Communications management plan
D. Ishikawa diagram
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)
Which service is NOT typical of Grade 1?
Alter a company's senior executive management meeting the CEO issues a mandate to automate a new-client on-boarding process that would effectively eliminate the current manual paper-based process. The assigned program sponsor selects a program manager
Both the program sponsor and the program manager must ensure that the program charier contains which of the following?
An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However the business team does not report to the IT program manager and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?
A design build firm has been retained by a client to construct an outpatient clinic. The client has hired an ICT distribution designer to review the DB firm's work product ensuring that the certified (mat documents are complete. In what capacity would the designer MOST LIKELY be serving?
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
What step can be a phase of the Bidding and Negotiating process?
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement
What should the program manager do first?
A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified
Key stakeholders for the program should include which of the following?
The program manager of a multinational program must reconcile data including subject matter experts* labor hour estimates and other direct resource hour estimates. In addition the program manager must prepare the cash flow analysis
Which of the following should be considered to get a baseline budget?
i program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced
he program manager will use the qualified seller list to do which of the following?
Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?
A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives.
What should the program manager do next?
A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?
The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It). What is to be the MINIMUM size of the TR?
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools
Which of the following must be addressed?
You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%. What size commercial DD (distribution device) is required to accommodate the increase?