Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PK0-005 CompTIA Project+ Certification (2026) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your CompTIA PK0-005 CompTIA Project+ Certification (2026) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 7
Total 447 questions

Which of the following best represents the project impact to a company's brand value?

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.The project meets the expected milestones and finishes on time and within budget.

Given the following network diagram:

Which of the following is the critical path?

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

A.

Issue log

B.

Dashboard

C.

WBS

D.

Milestone chart

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Which of the following would a scrum team discuss during a daily stand-up meeting?

A.

The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take

B.

Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors

C.

Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination

D.

Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Which of the following aspects are true of waterfall as compared to agile? (Select two).

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?

A.

In-person meetings

B.

Email

C.

Telephone

D.

Videoconference

Which of the following is a characteristic that defines a project?

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Which of the following statements best describes a content management system?

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Which of the following can a project manager infer from the following velocity chart?

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

A.

SLA

B.

TOR

C.

SOW

D.

NDA

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Page: 3 / 7
Total 447 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved