Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PK0-005 CompTIA Project+ Certification (2026) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your CompTIA PK0-005 CompTIA Project+ Certification (2026) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 4 / 7
Total 460 questions

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?

A.

Create a new project management plan.

B.

Collect all project meeting minutes.

C.

Perform project scope management.

D.

Review the project charter.

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

A project manager is developing a project management plan. The resource assignments are complete. Which of the following steps should have been completed before completing the resource assignments?

A.

Determine the budget considerations.

B.

Develop a kickoff presentation.

C.

Review the existing artifacts.

D.

Define the units of work.

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

A.

SLA

B.

TOR

C.

SOW

D.

NDA

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

A.

The scope of the project deliverable is clearly defined

B.

There is a non-disclosure agreement in place

C.

There are multiple requirements for the product

D.

The PM wants to simplify the logistics of the required product

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

A.

Assign action items to attendees.

B.

Distribute an agenda.

C.

Email the minutes from the previous meeting.

D.

Schedule a convenient time.

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

The project manager sends individual messages to team members about what must be accomplished. However, the team communicates confusion about the tasks assigned. Which of the following communication methods would be best to use?

A.

Informal internal

B.

Asynchronous verbal

C.

Synchronous external

D.

Formal written

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).

A.

Documentation

B.

Team collaboration

C.

Gap analysis

D.

Training sessions

E.

Touch points

F.

Progress monitoring

Which of the following statements best describes zero-based budgeting?

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

During the project initiation phase, a project manager needs to assign individual roles and responsibilities to various team members. Which of the following would best enable them to do so?

A.

ERP

B.

RAM

C.

JAR

D.

CCB

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A.

Change the precedence of the tasks to " finish-to-start " .

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Page: 4 / 7
Total 460 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved