Prepare effectively for your CompTIA PK0-005 CompTIA Project+ Certification (2025) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 4 / 6
Total 362 questions

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

A.

Project dashboard

B.

Gap analysis

C.

Risk register

D.

Communication plan

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

A.

Issue, issue

B.

Issue, risk

C.

Risk, issue

D.

Risk, risk

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

A.

RFP

B.

WBS

C.

SLA

D.

SOW

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?

A.

Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting's agenda.

B.

Ask the team member to leave the meeting and create a new meeting to discuss these topics.

C.

Adjust the current meeting's agenda to accommodate the team member's topics.

D.

Allow the team member to bring up the topics, which could lead to important discussions and insights.

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

A.

Change log

B.

Project Gantt

C.

Issue log

D.

Requirements traceability matrix