Prepare effectively for your CompTIA PK0-005 CompTIA Project+ Certification (2026) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 7 / 7
Total 460 questions

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?

A.

Real-time, multi-authoring tool

B.

Wiki knowledge base and search engine

C.

Workflow and e-signature platform

D.

File-sharing platform and storage system

During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?

A.

Milestone chart

B.

Velocity chart

C.

Task board

D.

Burndown chart

Which of the following situations would require a project manager to revise the communication plan during a project ' s execution?

A.

A change is approved that impacts the project schedule and budget

B.

The test results are not as expected

C.

The team is unclear which meetings they should attend

D.

A stakeholder requests some changes to the scope

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following action should the project manager take next?

A.

Document the change request in the change log.

B.

Communicate the change request to stakeholders.

C.

Determine the decision makers for the change request.

D.

Validate the change request.

Which of the following does a commercial, off-the-shelf system usually require?

A.

Cloud infrastructure

B.

Privacy assessment

C.

Minimal customization

D.

Dedicated IP address

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

A.

Approving deliverables

B.

Enforcing vendor rules of engagement

C.

Reporting overall process

D.

Scheduling team touch points

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Which of the following requires the MOST availability from the business team?

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall