Prepare effectively for your CompTIA PK0-005 CompTIA Project+ Certification (2025) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 6
Total 362 questions

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

A.

Risk assessment

B.

Preliminary scope statement

C.

Work breakdown structure

D.

Milestone chart

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

A.

Milestone

B.

Gantt

C.

Burndown

D.

PERT

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

A.

Baseline

B.

RBS

C.

WBS

D.

Milestones

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

A.

Awareness of the local environment

B.

Awareness of the brand value

C.

Awareness of the resource constraints

D.

Awareness of the company's mission

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

A.

Grant the client access to the project repository.

B.

Create a chat to communicate in real time.

C.

Schedule a weekly status meeting.

D.

Send a weekly status report by email.

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Which of the following best represents an intellectual property breach?

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.