CCM FIDIC Certified Contract Manager Free Practice Exam Questions (2026 Updated)
Prepare effectively for your FIDIC CCM Certified Contract Manager certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))
(Under the FIDIC Red and Yellow Books (edition 1999), which two of the following answers are correct regarding the application for Interim Payment Certificates? Choose all correct answers.)
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
You are the Contract Manager of the Employer for a Data Centre Project using the FIDIC Yellow Book (edition 2017). As a Contract Manager during the procurement stage, you are to explain the difference between Dispute Avoidance and Adjudication Board (DAAB) and other alternative dispute resolutions for this type of project. Which one of the following statements of its explanation is NOT correct?
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?
Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor ' s Proposal. Which two of the following statements are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).
(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?
Choose all of the correct answers (multiple possibilities).)
Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?
Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?
(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)
Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)
Choose all of the correct answers (multiple possibilities).
(Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)