Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CA0-001 PMI Certified Associate in Project Management (CAPM) Certification Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI CA0-001 Certified Associate in Project Management (CAPM) Certification certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 6
Total 525 questions

Which of the following is not a part of the project cost baseline but is included in the project budget?

A.

Management Contingency Reserve

B.

Management Overheads

C.

Project Management Planing

D.

Activity Cost Contingency Reserve

Which of the following is an output of a Verify Scope process?

A.

Formal acceptance

B.

WBStemplate

C.

SOW acceptance

D.

Rework

A project plan is:

A.

A formal, approved document used to guide both project execution and project control.

B.

A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.

C.

A narrative description of products or services to be supplie

D.

A document describing the organizational breakdown structure of the company.

Which of the following is an output of Define Scope?

A.

PBS

B.

Project Scope statement

C.

WBS Template

D.

Constraints

An example of a project is:

A.

Billing customers

B.

Managing an organization

C.

Constructing a building

D.

Providing technical support

Which of the following activity is not performed as part of the direct and manage project execution process?

A.

Monitor implementation of approved changes

B.

Validate deliverables

C.

Staff, train, and manage the project team

D.

Manage cisks and implement risk responses

The scope management provides:

A.

A basis for future decisions about the project.

B.

A baseline to accomplish verification measures.

C.

A baseline to evaluate potential scope changes.

D.

All of the above.

The project management plan:

A.

Identifies all the steps and processes that will be used after a project is initiated

B.

Steps needed to complete a project task

C.

Prepared at the beginning and fixed throughout the execution of the project

D.

Includes project charter

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

__________ involves using project characteristics in a mathematical model

A.

Analogous estimating

B.

Life-cycle costing

C.

Parametric modelling

D.

Bottom up estimating

You are the project manager and you have created a contract for your customer. The contract must have ________.

A.

Offer and consideration

B.

Start date and acceptance of start date

C.

Signatures and the stamp of a notary public

D.

Signatures of all stakeholders

What involves determining what quantities are to be used to perform project activities.

A.

Resource planning

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

What are the outputs of Initiation process?

A.

Project charter and PM assigned

B.

Constraints

C.

Assumptions

D.

Al1 of the above

The planning processes are:

A.

Define Scope, Resource planning, Estimate Costs, Schedule development. Define Activities

B.

Inputs, Control, Status reports, Risk management

C.

Planning, Resource planning, Quality assurance, Risk control

D.

Define Scope, Team development, Control Schedule, Budget control, Contract administration

Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.

A.

Improve the accuracy of cost, time and resource estimates

B.

Define a baseline for performance measurement and control

C.

Facilitate clear responsibility assignments

D.

Al1 of the above

You are the project manager of a project. Your project just went into integration mode. This means that your project __________.

A.

Has been accepted by the sponsor and the client

B.

Will be closed due to lack of resources

C.

Resources are being assigned to other areas of the business

D.

None of the above

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year?

A.

$600

B.

$1200

C.

$3000

D.

$100

In which type of organization, a project manager is in complete control of the project?

A.

Projectized organization

B.

Balanced Matrix organization

C.

Strong Matrix

D.

Weak Matrix organization

At which stage, stakeholders have the maximum influence on a project?

A.

Initial stage

B.

Closing stage

C.

Execution stage

D.

None of the above

In an optimal organization structure, the project manager is:

A.

Functional

B.

Weak matrix

C.

Piojectized

D.

Dedicated project team

Market conditions are a part of ________.

A.

Enterprise environmental factors

B.

Project management concerns

C.

Organizational process assets

D.

Cost factor

A major assumption of all network scheduling methods is that the activity duration must be _____.

A.

Statistically dependent

B.

Variance distributed

C.

Statistically independent

D.

Deterministic

In which type of organization, a project manager is in complete control of the project?

A.

Projectized organization

B.

Balanced Matrix organization

C.

Strong Matrix

D.

Weak Matrix organization

Which of the following plans is not done during the writing of a project plan?

A.

Executive Communication

B.

Risk Management

C.

Quality Management

D.

Scope Statement

Conformance to specifications document is one description of _________.

A.

Quality

B.

Scope

C.

Integration

D.

Procurement

Purchasing insurance is an example of __________.

A.

Transfer

B.

Acceptances

C.

Mitigation

D.

Contingency

What are common types of cost-reimbursable contracts?

A.

CPF

B.

CPFF

C.

CPIF

D.

Al1 of the above

When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?

A.

Parametric estimating

B.

Bottom-up estimating

C.

Top-down estimating

D.

Analogous estimating

A Reserve Analysis is a technique for:

A.

Estimate Activity Durations

B.

Estimate Activity Resources

C.

Sequence Activities

D.

Define Activities

A Project Scope Management includes :

A.

Initiation

B.

Project Plan Execution

C.

Overall Change Control

D.

Report Performance

Page: 5 / 6
Total 525 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved