Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 5
Total 278 questions

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks ' severity, and update the risk register.

During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.

What should the risk manager do to educate stakeholders?

A.

Conduct risk workshops tailored to all stakeholders.

B.

Invite all stakeholders to daily coordination meetings.

C.

Distribute risk-policy documents to all stakeholders.

D.

Provide project management training to all stakeholders.

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members ' concerns about risk identification?

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes. 

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

A.

Include the risk in the register and communicate with the stakeholders.

B.

Communicate with the client to provide the previous shutdown plan.

C.

Review and update the project schedule.

D.

Interview the other project manager to learn more details.

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

A.

Enhance the process of identification of different Individual project risks.

B.

Allows monitoring the impact against the overall project risk exposure.

C.

Establishes risk sources and ownership for trigger monitoring.

D.

Creates a single repository for all project risk documents.

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

A.

Detailed work breakdown structure (WBS)

B.

Lessons learned from previous projects

C.

Baselines approved by the project team

D.

Actual data from the current project

The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.

What should the risk manager do first to demonstrate this to the stakeholders?

A.

Gather other project risk historical information.

B.

Gather and reconcile project risk report data.

C.

Work with the sponsor to convince the risks are under control.

D.

Work with the team to ensure the project is in good health. 

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project ' s profitability will increase by 80%.

What type of request is the risk manager describing?

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment 

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

A project manager wants to introduce a new technology to improve a project ' s performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.

What should the project manager do in this situation?

A.

Escalate this initiative to project decision makers and sponsors.

B.

Accept the fact that there is a risk associated with this new technology.

C.

Take advantage of this opportunity of Improving the project performance.

D.

Outsource the implementation of the new technology as soon as possible.

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company ' s business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

A risk manager faces resistance as they try to implement the project ' s risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers

this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about

to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?

A.

Perform a risk impact analysis.

B.

Perform a risk reserve analysis.

C.

Perform a procurement analysis.

D.

Perform a stakeholder impact and influence analysis.

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project ' s budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

A.

Stakeholder management and communication tools

B.

Team performance reports and analysis tools

C.

Schedule management tools (i.e., Gantt Charts)

D.

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations) 

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.

What should the risk manager do first?

A.

Develop a residual risk management plan to manage the residual risks.

B.

Analyze, document, and communicate the residual risks to stakeholders.

C.

Record the residual risks in the watch list for future reference.

D.

Implement the contingency plan when the residual risks occur.

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

A.

Work breakdown structure (W & S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Page: 3 / 5
Total 278 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved