Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 5
Total 284 questions

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

A.

Follow up on the schedule and assess the best course of action if any delays are detected.

B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

A.

Develop an efficient network protection solution quickly to mitigate the risk.

B.

Escalate the case to the risk manager and wait for their instructions.

C.

Conduct an analysis to determine the root cause of the failed response.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

A.

Risk analysis

B.

Risk identification

C.

Risk treatment

D.

Risk evaluation

The major investor in a road construction project is constantly asking project team members for information about the project ' s execution. This has resulted in the project team working 20% of their day preparing project reports for the stakeholders.

What should the risk manager do to enhance the project team ' s approach to risk reports?

A.

Talk to the project team and ensure they avoid direct communication with this stakeholder.

B.

Engage with the team to enhance the project risk reports sent to the stakeholders.

C.

Highlight to the stakeholders the agreed predetermined frequency of risk reports.

D.

Work with the project sponsor to ensure stakeholders avoid directly influencing the project team.

What should the risk owner use as an effective information-gathering technique during the planning session?

A.

Monte Carlo analysis

B.

Update risk register

C.

Brainstorming

D.

Cost and time estimating

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

A.

Use the Delphi technique involving experts who have identified opportunities in the past

B.

Interview more stakeholders who have a positive mindset

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.

What should the project manager do to avoid this risk?

A.

Record this risk and the clients preference in the risk register.

B.

Ask the sales person to lead the communication with the client

C.

Call the client and advise that online communication is easier and faster.

D.

Meet the client and plan tor critical milestone meetings.

A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.

What should the risk manager advise the team to do first?

A.

Mitigate the risk by asking the team member to gather more information.

B.

Add the risk to the issue log and revisit it when there is more information.

C.

Arrange a meeting with the stakeholder to discuss the risk and information.

D.

Add the risk to the risk register and gather information about its probability and impact. 

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project ' s profitability will increase by 80%.

What type of request is the risk manager describing?

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment 

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.

Which steps should the risk manager consider when updating relevant project documents?

A.

Update the issue log with relevant information as the immediate concern for key stakeholders.

B.

Assume the delay will not affect the timeline and continue with the current scheduled activities.

C.

Update the project documents after the work has been completed and formally accepted.

D.

Assess the delay with the technical team, update the schedule and risk register, and inform stakeholders.

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk ' s status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register. 

Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

A.

Enhance the process of identification of different Individual project risks.

B.

Allows monitoring the impact against the overall project risk exposure.

C.

Establishes risk sources and ownership for trigger monitoring.

D.

Creates a single repository for all project risk documents.

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks. 

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

D.

Cost-benefit analysis

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

A.

Engaged the sponsor and informed them of the decision to remove the planned feature.

B.

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.

C.

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.

D.

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 

A project team is presenting a delivery plan to a client. Some of the client ' s experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.  

Page: 2 / 5
Total 284 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved