Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 4
Total 264 questions

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

A.

Update the risk register accordingly and review it in regular project meetings.

B.

Accept the risk because residual risks are often low.

C.

Ask a subject matter expert (SME) to assess the residual risk and take action.

D.

Assign a risk owner and set it as high priority and high impact.

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?

A.

Update the definition of done (DoD) to improve risk management.

B.

Review the acceptance criteria for upcoming stories.

C.

Prioritize risk mitigation stories for the next sprint.

D.

Check stories in the product backlog to identify risks.

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

A product roadmap should contain which of these primary components?

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

A.

Agree with the external supplier on the timeline.

B.

Register the risk with a medium impact.

C.

Align with stakeholders on the risk threshold.

D.

Engage another supplier with shorter delivery times.

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

C.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Meet with the project manager to revisit the project schedule.

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

A.

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

B.

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

C.

Prepare a list of the key resources that will be used to compile a risk management plan.

D.

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?

A.

Conduct a strengths weakness, opportunities, and threats (SWOT) analysis.

B.

Create a contingency plan

C.

Start a vendor assessment

D.

Submit a change request

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

A.

Plan Risk Management

B.

Perform Qualitative Risk Analysis

C.

Perform Quantitative Risk Analysis

D.

Monitor and Control Risk

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

A.

Document the risk in the risk register for analysis.

B.

Document the detailed risk consequences,

C.

Immediately start the contracting process.

D.

Proceed with the quantitative risk analysis. 

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

A.

Exclude risk averse stakeholders from future risk discussions

B.

Explain risk handling and mitigation strategies

C.

Increase the impact of all risks in the risk breakdown structure (RBS)

D.

Develop a generous probabilistic cash flow model

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

A.

Sensitivity analysis

B.

What-if scenario analysis

C.

Regression analysis

D.

Decision tree analysis

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

A.

Immediately hire as soon as the project begins to fall behind schedule.

B.

Hire as soon as the project metrics trigger a risk response.

C.

Only hire when it is economically feasible to do so.

D.

Only hire if risk response is escalated and approved by the stakeholders. 

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.

What additional information should the risk manager prioritize in the risk register updates?

A.

Actual outcomes and performance of risk management strategies

B.

Actual outcomes of the project's risks and risk responses

C.

Actual costs and schedule delays of risk events

D.

Actual cost impact of risk events

Page: 2 / 4
Total 264 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved