Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 5
Total 284 questions

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.

How should the risk manager manage the risk level?

A.

Communicate risk levels only to the supportive stakeholders.

B.

Advise the sponsor to meet with the stakeholders to discuss the risk levels.

C.

Collaborate with the project manager to communicate risk levels to stakeholders.

D.

Coach the project manager on communicating risk levels to stakeholders.

An eco-friendly sustainable textile-dyeing project has begun, with a focus on identifying and managing environmental risks. The risk manager, collaborating with the project manager, is tasked with reviewing and updating the project’s risk management plan. To inform this process, the risk manager needs relevant insights specifically related to environmental risk factors.

What should the risk manager do?

A.

Review process documents from Six Sigma to identify areas of process inefficiency.

B.

Refer to standards for information security management systems to ensure compliance.

C.

Consult environmental enthusiasts for informal feedback on potential risks.

D.

Use prompt lists to systematically identify and analyze environmental risk factors.

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option ' s success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

A.

Ask the sponsor to define the risk strategy to align with client needs.

B.

Develop a framework and engage the team in creating a risk plan.

C.

Train the team on basic techniques and defer the risk strategy for later.

D.

Concentrate on high-priority risks to meet the sponsor ' s expectations.

Page: 5 / 5
Total 284 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved