Prepare effectively for your PRINCE2 PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 1
Total 56 questions

At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.

Which practice is being applied?

A.

Business case

B.

Plans

C.

Progress

D.

Quality

During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.

The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the ‘evaluate a work package’ activity, and why?

A.

Yes, because evaluation confirms that completed quality activities are recorded and that the current status is understood by the relevant parties

B.

Yes, because the team manager should review the work-package information, report progress for the agreed period, and notify the project manager when a tolerance is forecast to be exceeded

C.

No, because only the project manager may evaluate the status of a work package and decide what it should report

D.

No, because a forecast work-package tolerance breach should be reported directly to the project board in an exception report

ORGANIZATION

Use the ‘Additional Information’ in the Scenario Booklet to answer this question.

Here are three roles relating to the LouisShopping Project.

Which individual (A–E) would be MOST appropriate for each role according to the ‘organization’ practice?

Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.

A.

Regeneration Manager

B.

Regeneration Officer

C.

Chief Technology Officer

D.

Heritage Manager

E.

Portfolio Director

Roles:

Project support

User assurance

Senior supplier

PROCESSES

During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.

During which activity should this clarification of the mandate and business expectations take place?

A.

Appoint the project management team

B.

Appoint the project executive and manager

C.

Select the project approach

D.

Plan the initiation stage

Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance. While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.

Is this an appropriate application of ‘prepare the next stage plan’, and why?

A.

Yes, because the next stage plan should reflect authorized changes, with affected product information and the project initiation documentation updated where necessary

B.

Yes, because every authorized change must be implemented through an exception plan before the related work may enter the following stage

C.

No, because authorized changes should remain outside the next stage plan until the project has been re-authorized by the business layer

D.

No, because project assurance should prepare the next stage plan and update the affected product information independently of the project manager

A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.

Is this an appropriate application of the issues practice, and why?

A.

Yes, because the legislation may affect the resources available to deliver the project

B.

Yes, because external events must be managed outside the project’s agreed controls

C.

No, because legislation should be recorded after its full effect on delivery is known

D.

No, because external events are managed by the business rather than by the project team

During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.

Is this an appropriate application of the ‘capture issues and risks’ activity, and why?

A.

Yes, because recording the concern in the project log is sufficient before allowing delivery to continue

B.

Yes, because the project manager may dismiss an informally raised concern without further investigation

C.

No, because the project manager should assess an informally raised concern before deciding what action to take

D.

No, because the team manager should report the concern only in the next scheduled checkpoint report

During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown’s ‘green town’ status.

During which ‘initiating a project’ activity should this workshop take place?

A.

Agree the tailoring requirements

B.

Agree the management approaches

C.

Prepare the project plan

D.

Prepare the full business case

During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.

During which closing activity should this be done?

A.

Prepare planned closure

B.

Confirm project acceptance

C.

Evaluate the project

D.

Request project closure

During initiation, new information from BuildyBrick shows that additional protection of historic buildings will extend the planned duration.

Which role should the project manager consult to check that the revised plan still meets the needs of the project board and business?

A.

Business layer

B.

Team manager

C.

Project assurance

D.

Project executive

During stage 3, the project manager forecasts that the stage-level recycling tolerance will be exceeded. The project manager records the matter in the issue register and sends only an issue report to the project board.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because an issue report is sufficient whenever a sustainability target is forecast to be missed

B.

Yes, because the forecast shortfall should be treated only as an off-specification in the issue report

C.

No, because the forecast breach should be escalated to the portfolio office rather than the project board

D.

No, because it is an exception which should be escalated in an exception report

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

A.

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.

Which practice is being applied in ‘managing a stage boundary’?

A.

Plans

B.

Organization

C.

Quality

D.

Progress

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed