Prepare effectively for your PRINCE2 Prince2-Foundation PRINCE2 7 Foundation written Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 4 / 7
Total 471 questions

To meet the minimum requirements for applying the progress theme, what must be considered?

A.

How lessons will be learned

B.

How time-driven reports will be produced

C.

Which management products will be baselined

D.

Who is responsible for reporting on progress

Which is a purpose of the Risk Register?

A.

Describe the risk management techniques and standards to be applied to the project

B.

Act as a central record of information relating to the identified risks for the project

C.

Act as a repository for informal issues

D.

List the responsibilities for achieving an effective risk management procedure

Which should be provided by a project mandate?

A.

Terms of reference

B.

Detailed Business Case

C.

Stage tolerances

D.

Initiation Stage Plan

Which is a minimum requirement for applying the organization theme?

A.

To document the project management team structure

B.

To define the experience required for each project role

C.

To include external stakeholders on the project board

D.

To train project team members in the use of PRINCE2

Which process provides information for the project board to review a completed stage and confirm continued business justification?

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Within which integrated element does PRINCE2 set minimum requirements?

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Which is an objective of the 'initiating a project' process?

A.

To ensure that baselines are established and controlled

B.

To ensure that the business case is kept under review

C.

To ensure that the planned products are delivered within tolerances

D.

To ensure that user acceptance of the products is confirmed

Which is an objective of the 'starting up a project' process?

A.

To approve the initiation stage

B.

To select the project mandate

C.

To define the project quality management approach

D.

To appoint the project management team

Which theme estimates the cost of delivering the project?

A.

Business case

B.

Change

C.

Plans

D.

PROGEESS

Which is a minimum requirement when applying the 'risk' theme?

A.

To identity and ring-fence an explicit risk budget within the project's budget

B.

To describe the probability impact grid in the risk management approach

C.

To appoint project assurance to maintain the risk register during initiation

D.

To assess if risks might have a material impact on business justification

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Which is a purpose of the quality theme?

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Which is an objective of the ‘directing a project’ process?

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

What is documented in the project plan to support the 'manage by exception' principle?

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Which is a purpose of a quality register?

A.

To record cross-references to issues relating to the quality of the products

B.

To record the date a completed work package was received

C.

To provide the status of quality activities carried out for completed products

D.

To capture quality concerns about completed products

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Identify the missing word in the following sentence relating to one of the principles:

A PRINCE2 project should have [?] defined for each project objective.

A.

themes

B.

principles

C.

processes

D.

tolerances