Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

Prince2-Foundation PRINCE2 7 Foundation written Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PRINCE2 Prince2-Foundation PRINCE2 7 Foundation written Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 7
Total 471 questions

Which is an objective of the Starting up a Project process?

A.

Identify who will be responsible for creating the Project Plan

B.

Agree how the project will be monitored and controlled after initiation

C.

Authorize the Project Manager to proceed with the initiation stage

D.

Agree how issues and changes will be identified, assessed and controlled

How is the tailoring approach defined for a project?

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

What should be considered when defining the number of management stages in a project?

A.

When the team managers are available

B.

When key decisions need to be made

C.

When highlight reports will be submitted

D.

When project support will be available

Which role represents the stakeholders who will operate the project's products after the project is complete?

A.

Executive

B.

Senior user

C.

Senior supplier

D.

Project manager

Which is a purpose of the 'initiating a project' process?

A.

To decide if it is worthwhile to initiate a project

B.

To decide on the project approach

C.

To establish solid foundations for a project

D.

To identify the number of work packages required

Which statement about time-driven controls is CORRECT?

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

A.

and the project board are responsible

B.

and the team manager(s) are accountable

C.

has responsibility

D.

decides who is responsible

Why is the 'initiating a project' process used?

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Which is a purpose of the 'directing a project' process?

A.

To exercise overall control over the project

B.

To take corrective action to control risks and issues

C.

To do the minimum in order to decide whether the project is feasible

D.

To update the project plan before the next stage

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A.

Enable the Project Board to decide whether or not to authorize the project

B.

Justify the continuing viability of the project

C.

Enable the Project Board to decide whether or not to authorize project closure

D.

Justify the initiation of a project

What problem may occur if projects are not aligned with corporate business strategy?

A.

The control of projects may be poor

B.

The outputs may be of poor quality

C.

The objectives of different projects may overlap

D.

The project management approaches used may differ

How does the project board use the 'manage by stages' principle to control the project?

A.

By approving the project management team

B.

By reviewing project viability at defined intervals

C.

By ensuring that the benefits are managed and controlled

D.

By reviewing previous project closure documentation

Which statement describes the 'Implement' step within the recommended risk management procedure?

A.

Take planned action to respond to a risk

B.

Implement the responsibilities for risks defined in the Risk Management Strategy

C.

Assess the proximity of a risk

D.

Identify the level of risks that can be tolerated by the project

Which is a minimum requirement for applying the risk theme?

A.

Threats must be assessed for their impact on the viability of the project

B.

A single role that is responsible for all risks must be defined

C.

The PRINCE2 risk management procedure must be followed

D.

Team managers must maintain their own risk registers

According to the 'continued business justification' principle, what must project benefits be aligned to?

A.

Regular deliveries throughout the project

B.

The business objectives

C.

The direction of the project board

D.

The technology available

Which approach must be followed as a minimum requirement for applying the plans theme?

A.

Activity-based planning

B.

Product-based planning

C.

Agile

D.

Risk management

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

A.

change budget

B.

project budget

C.

project's cost tolerance

D.

project's risk tolerance

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

A.

Continued business justification

B.

Defined roles and responsibilities

C.

Manage by exception

D.

Manage by stages

Which is a purpose of a project brief?

A.

To act as a base document which enables the project board to assess progress

B.

To provide a sound basis for project initiation

C.

To define how the achievement of the project's benefits can be measured

D.

To provide a description of the means and frequency of communication

Page: 3 / 7
Total 471 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved