Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: s2p65

Easiest Solution 2 Pass Your Certification Exams

Prince2-Practitioner PRINCE2 Practitioner Exam Free Practice Exam Questions (2025 Updated)

Prepare effectively for your PRINCE2 Prince2-Practitioner PRINCE2 Practitioner Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 5
Total 282 questions

When updating the project plan as part of Managing a stage boundary, what else might be updated?

A.

Exception Plan

B.

Project Management team

C.

Business Case

D.

Project Initiation Documentation

Which of the following management products ARE updated as part of Managing a stage boundary?

1. Business Case

2. Benefits Review Plan

3. Configuration Item Records

4. Project Brief

A.

1, 2, 3

B.

1, 3, 4

C.

1, 2, 4

D.

2, 3, 4

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

A.

Scope, People & Resources, Benefit

B.

Scope, Risk, Product

C.

Risk, Benefit, Product

D.

Scope, Risk, Benefit

Which of the following activities is NOT an action of preparing for planned closure?

A.

Update the project plan with actual

B.

Update the Project Management Team

C.

Request a product status account

D.

Confirm project has delivered what is defined in Project Product Description

Which of the following activities could trigger the production of an exception plan?

A.

Review Stage status

B.

Giving ad hoc direction

C.

Escalating a project issue

D.

Report stage end

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Which of the following statements is FALSE regarding the Continued Business Justification?

A.

The justification for the project must remain the same throughout the project.

B.

The justification for the project should remain vabd.

C.

The justification for the project may change.

D.

If the project is no longer justified it should be stopped.

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service

provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Who is responsible for ensuring that the value-for-money solution is constantly reassessed?

A.

Business Assurance

B.

Senior User

C.

Corporate or Programme Management

D.

Reject Support

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology

Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the

Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and

operating models, plus an outline Business Case for the required project. The external consultants

also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating

models) and the service level agreement between MFH and the future service

provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run

trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the

recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Reasons heading?

A.

The lack of up-to-date technology in MFH means a re-engineering of existing services will not necessarily deliver the performance improvements required.

B.

Providing re-engineered services in-house will remove the need to transfer staff to a service provider.

C.

The Ministry of Food Hygiene (MFH) needs to deal with the increasing pressure to cut costs and better manage supplier's performance.

D.

Relocating staff to the selected service provider's premises will mean that no property transfer is required.

E.

The inadequate controls, outdated standards and outdated technology must be addressed.

Scenario

Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:

There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including:

    20% discount for all repeat customers - not cost-effective and very short term

    A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year

    A series of television and press advertisements was too expensive

    A direct mail shot to all customers - benefit would be short term

    Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

Which 2 statements should be recorded under the Expected dis-benefits heading?

A.

A high quality, glossy product will involve additional costs.

B.

Individuals in the engineering team who are not selected to appear in the calendar photographs will become de-motivated.

C.

The calendar may not result in the expected 10% increase in orders.

D.

Because the Calendar project is a priority for the MNO Manufacturing Company, the delivery of other projects within the Marketing department will be delayed.

E.

The calendar may not result in the 10 further orders from the list of prospective customers in 12 months.

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology

Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run

trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Expected benefits heading?

A.

The 10-year outsourcing contract, at current prices, will be worth £80m.

B.

Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.

C.

The total expected savings over 10 years, at current prices, is £20m.

D.

The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.

E.

The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.

Which of the following statements is TRUE with regard to expected benefits?

A.

They cannot be assigned

B.

They don't need to follow corporate objectives

C.

They should be measurable

D.

Tolerances cannot be set against expected benefits

Scenario

Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:

There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including:

    20% discount for all repeat customers - not cost-effective and very short term

    A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year

    A series of television and press advertisements was too expensive

    A direct mail shot to all customers - benefit would be short term

    Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

Which 2 statements should be recorded under the Costs heading?

A.

The MNO marketing budget this year is £120k.

B.

The project will be funded from the business marketing budget

C.

10 further orders with an average profit of £2k will deliver a benefit of £20k in the first year.

D.

The new company logo is estimated to cost £4k.

E.

Project costs are estimated to be a total of £26.5k.

The project is part of a program to increase the number of ABC courses that respond to legislation. The program manager has instructed the project manager to deliver the 'e-learning course' incrementally. The project manager has asked the program manager how often the highlight reports are required, and what format the reports should be presented in.

Is this an appropriate approach to controlling progress, and why?

A.

Yes, because the approach should support the delivery approach selected by the program.

B.

Yes, because the project event-driven controls need to align to program controls.

C.

No, because the program team should review project progress using peer reviews.

D.

No, because the progress controls should be documented in the project initiation documentation.

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.''

In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''.

Is this appropriate, and why?

A.

Yes, because delivering incrementally will reduce the impact of the threat.

B.

Yes, because a risk response needs to be implemented for this major threat.

C.

No, because risks responses should be identified as part of the 'plan' step.

D.

No, because a risk action should be allocated to implement a response.

The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2.

Is this an appropriate action, and why?

A.

Yes, because the project manager should recommend corrective actions required.

B.

Yes, because moving the work enables stage 2 to be delivered within tolerance.

C.

No, because the team manager should inform the project manager by raising an issue.

D.

No, because the stage deviation should be referred to the project board for a decision.

During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.

What should project assurance do next?

A.

Update the team plan to show that the work package is complete.

B.

Check the work package and follow the procedure to deliver completed products.

C.

Verify that all the products to be delivered by the work package are approved.

D.

Update the stage plan to show the work package as completed.

ABC has experience of delivering training projects that respond to new legislation. Previous projects have had to change the acceptance criteria, due to further updates being made to legislation during the project.

What action should be taken to address this, and why?

A.

Agree and prioritize the acceptance criteria during the initiation stage, because these criteria will be used to determine if the project can be closed.

B.

Agree and prioritize the acceptance criteria during the initiation stage, because they can be amended through change control, if needed.

C.

Set the quality tolerances for the acceptance criteria in the product descriptions, because this would allow for additional changes in legislation.

D.

Set the quality tolerances for the acceptance criteria in the product descriptions, because quality tolerances define the acceptable range.

The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and finds that the expected delivery date is unrealistic. As a result, the project manager agrees an extra two weeks to complete the work package, within the current stage tolerance. The work package is then accepted by the team manager.

Is this an appropriate application of the 'manage product delivery' process, and why?

A.

Yes, because the team manager should set the time required to complete a work package.

B.

Yes, because the team manager should agree the limits within which the work is to be completed.

C.

No, because the work package, defined by the project manager, should not be changed.

D.

No, because the use of the stage time tolerance should be authorized by the project board.

Page: 1 / 5
Total 282 questions
Copyright © 2014-2025 Solution2Pass. All Rights Reserved