C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems Free Practice Exam Questions (2025 Updated)

Prepare effectively for your SAP C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 2
Total 110 questions

Revenues & Payment

A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

A.

Settle the WBS element to the highest billing element before you do the result analysis.

B.

Split the project intdifferent project according to each company code.

C.

Change the project structure so that it correspond better to the company's organization structure.

D.

Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

Project Structure

Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.

What standard report do you recommend?

A.

Structure overviews for budget.

B.

Cost element report on budget updates.

C.

Line item report for budget

D.

Hierarchical report on budget updates.

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

A.

Material master

B.

Network activity

C.

WBS element

D.

BOM item

What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question

A.

Project simulations allow posting of actual data

B.

Project simulations can be created without using an operational project as a template

C.

Project simulations can be used to plan structures and costs

D.

Project simulations can create purchase requisitions

E.

Multiple project simulations can be used simultaneously

Cost and budget

A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do

not want to produce..

Which setup do you recommend?

A.

Assign a sales order to a project with appropriate hierarchy levels.

B.

Assign a network to a sales order

C.

Assign Several production orders to a sales order

D.

Assign One production order to a sales order

Cost and Budget

What function are available for period end-closing in the project System?

A.

Result analysis

B.

Progress analysis

C.

Milestone trend analysis

D.

Settl ement

E.

Confirmation

You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

A.

Unit costing for WBS

B.

Easy Cost Planning (ECP) for WBS

C.

Detailed planning for WBS

D.

Planning of overall values

Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

A.

The materials must allow sales order or project stock

B.

The exact lot size procedure must be used

C.

The procurement type of the material must be internal

D.

An MRP group must be assigned

You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

A.

The manual hierarchical revenue planning will be displayed only if expert mode is activated

B.

The manual hierarchical revenue planning has no reference to cost elements

C.

Cost element reports can display costs but not revenues

D.

Cost element reports display integrated planning only

The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

A.

Calculation of actual values

B.

Goods receipt for purchase order

C.

Creation of purchase orders

D.

Activity allocation

A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

A.

Only capacity requirements

B.

Forward

C.

Current date

D.

Backward

You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

A.

The person responsible for the work center

B.

The person responsible for the superior WBS element

C.

The MRP controller for the network

D.

The person responsible for the network activity

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

A.

Scheduling and capacity category

B.

Scheduling and distribution key

C.

Control key of an activity

D.

Capacity planner group in the network header

Page: 2 / 2
Total 110 questions