Prepare effectively for your SAP C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Revenues & Payment
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?
Project Structure
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do
not want to produce..
Which setup do you recommend?
Cost and Budget
What function are available for period end-closing in the project System?
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?