Prepare effectively for your SAP C_TS422_2022 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 2
Total 80 questions

What is the work center hierarchy in capacity planning?

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Which time elements can be reduced by a reduction strategy?

Note: There are 3 correct answers to this question.

A.

Goods receipt processing time

B.

Move time

C.

Wait time

D.

Float after production

E.

Queue time

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release