Prepare effectively for your USGBC LEED-AP-BD+C LEED AP Building Design + Construction (LEED AP BD+C) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?
During a design charrette, community neighbors raise a concern about potential glare resulting from a project's highly reflective roof. Which option should the LEED AP recommend to best address these concerns?
For a new project with a $10 million construction cost, the weight of the total recycled content is 0.9 tons (816.5 kilograms) each for post-consumer and pre-consumer recycled content. The value of the total recycled content is one million each for post-consumer and pre-consumer recycled content. What is the percentage of recycled content that contributes toward Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2, Leadership Extraction Practices?
What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?
Which of the following variables must be included in the calculations for Indoor Environmental Quality Credit, Quality Views?
Which of the following Sustainable Sites credits are eligible to be used as a campus approach?
At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project's
An existing vacant office building will be completely renovated and new mechanical, electrical and plumbing systems will be installed. 20% of the building's gross floor area will be complete at the time of certification. There will be a data center and some retail stores on the ground floor of the building at a future date. Which rating system is applicable for the building?
The required minimum scope of analysis for a product-specific declaration that contributes toward Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations, Option 1. Environmental Product Declaration is
Which of the following plumbing fixtures apply to the calculations in Water Efficiency Prerequisite, Indoor Water Use Reduction?
A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?
U.S. Green Building Council (USGBC)'s vision for using LEED internationally includes
What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?
What aspects of each space should the LEED consultant consider to identify the regularly occupied spaces on a project to ensure that floor area values are utilized consistently across credits?
A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content. Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?
What type of project would benefit from showing compliance with Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?
A building owner installs a building automation system (BAS) to allow programmable load control. Which of the
following credits can be pursued because of the installation?
For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to
The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?
For minimum acoustic performance, peak-hour is defined as M