Prepare effectively for your USGBC LEED-AP-BD+C LEED AP Building Design + Construction (LEED AP BD+C) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 6
Total 337 questions

Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?

A.

Energy and Atmosphere Credit. Demand Response

B.

Energy and Atmosphere Credit. Advanced Energy Metering

C.

Energy and Atmosphere Prerequisite. Minimum Energy Performance

D.

Energy and Atmosphere Prerequisite. Building Level Energy Metering

During a design charrette, community neighbors raise a concern about potential glare resulting from a project's highly reflective roof. Which option should the LEED AP recommend to best address these concerns?

A.

Install a vegetative roofing system

B.

Change the design to reduce the amount of roofing area

C.

Change the roofing material to a dark material to eliminate the issue

D.

Increase the parapet height

For a new project with a $10 million construction cost, the weight of the total recycled content is 0.9 tons (816.5 kilograms) each for post-consumer and pre-consumer recycled content. The value of the total recycled content is one million each for post-consumer and pre-consumer recycled content. What is the percentage of recycled content that contributes toward Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2, Leadership Extraction Practices?

A.

33%

B.

20%

C.

40%

D.

18%

What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?

A.

LEED v4, LEED for Neighborhood Development Conditional Approval

B.

LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood Development Certified Project

C.

LEED for Neighborhood Development Pilot, Stage 1 LEED for Neighborhood Development Pre-reviewed Plan

D.

LEED 2009, Stage 1 Conditional Approval of LEED for Neighborhood Development Plan

Which of the following variables must be included in the calculations for Indoor Environmental Quality Credit, Quality Views?

A.

Ceiling heights

B.

Building furniture

C.

Movable partitions

D.

Permanent interior obstructions

Which of the following Sustainable Sites credits are eligible to be used as a campus approach?

A.

Light Pollution Reduction, Places of Respite, Open Space

B.

Heat Island Reduction, Places of Respite, Site Master Plan

C.

Direct Exterior Access, Heat Island Reduction, Rainwater Management

D.

Heat Island Reduction, Light Pollution Reduction, Rainwater Management

At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project's

A.

environmental zone

B.

longitude and latitude

C.

ASHRAE 90.1 - 2010 climate zone

D.

Environmental Protection Agency Phase I Assessment

An existing vacant office building will be completely renovated and new mechanical, electrical and plumbing systems will be installed. 20% of the building's gross floor area will be complete at the time of certification. There will be a data center and some retail stores on the ground floor of the building at a future date. Which rating system is applicable for the building?

A.

LEED BD+C: Retail

B.

LEED BD+C: Data Centers

C.

LEED BD+C: Core & Shell Development

D.

LEED BD+C: New Construction & Major Renovation

The required minimum scope of analysis for a product-specific declaration that contributes toward Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations, Option 1. Environmental Product Declaration is

A.

gate-to-gate

B.

cradle-to-gate

C.

cradle-to-grave

D.

cradle-to-cradle

Which of the following plumbing fixtures apply to the calculations in Water Efficiency Prerequisite, Indoor Water Use Reduction?

A.

Toilets, urinals, pre-rinse spray valves

B.

Toilets, private lavatory faucets, dishwashers

C.

Urinals, public lavatory faucets, kitchen sink faucets

D.

Urinals, showerheads, commercial kitchen filling operations faucets

A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?

A.

Utility cost savings over the lifetime of the system must offset the higher initial cost

B.

Higher initial cost must exceed the cost of the utility over the lifetime of the system

C.

Higher initial cost must exceed the savings on the utility cost over the lifetime of the system

D.

Utility cost savings over the lifetime of the system must be lower than the higher initial cost of the system

U.S. Green Building Council (USGBC)'s vision for using LEED internationally includes

A.

allowing more stringent credit requirements for countries outside of the U.S. so that all projects can achieve LEED

B.

creating multiple LEED rating systems for different countries

C.

modifying U.S. reference standards, such as ASHRAE 90.1, to be more appropriate for regions outside the U.S.

D.

providing opportunities for alternative compliance paths that meet the unique needs of a particular region

What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?

A.

Schools

B.

Data centers

C.

Hospitality

D.

Warehouses and distribution centers

What aspects of each space should the LEED consultant consider to identify the regularly occupied spaces on a project to ensure that floor area values are utilized consistently across credits?

A.

Rate of outdoor air provided per person

B.

Fire ratings of installed wall and ceiling assemblies

C.

Average number of occupants standing or seated

D.

Typical duration of occupancy in each space per day

A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content. Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?

A.

$75

B.

$150

C.

$750

D.

$1,500

What type of project would benefit from showing compliance with Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

A.

One in which the budget and timeline would benefit from simplified decision making and analysis during the project design

B.

One in which the project team wants to explore the energy performance and load reduction effects of several envelope and lighting designs and mechanical systems

C.

One in which the project team wants to achieve efficiency trade-offs between systems, offsetting the lower efficiency of one system by the improved efficiency of another

One in which the owner wants an estimate of the carbon reductions or lower operating costs (energy savings, demand charge savings) from energy strategies, beyond a simple calculation for individual energy conservation measures

A building owner installs a building automation system (BAS) to allow programmable load control. Which of the

following credits can be pursued because of the installation?

A.

Energy and Atmosphere Credit, Demand Response

B Energy and Atmosphere Credit, Ongoing Commissioning

B.

Energy and Atmosphere Credit, Enhanced Commissioning

C.

Energy and Atmosphere Credit, Enhanced Refrigerant Management

For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to

A.

five bicycle trails

B.

at least eight diverse uses

C.

a restaurant, a grocery shop, a post office and two bus lines

D.

a rapid transit stop that is within 3 mi. (5 km) biking distance of the project boundary

The design team has specified products to achieve Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices for the project. At the end of the construction, it was discovered that the transporter who shipped a portion of the wood did not have chain-of-custody (CoC) certification. The design team should do which of the following?

A.

Submit a Credit Interpretation Ruling (CIR) to get clarification from USGBC

B.

Recalculate the percent of certified wood and consider the affected wood as non-certified

C.

Recalculate the percent of certified wood and delete the affected wood from the calculation

D.

Remove and replace the affected wood from the project site

For minimum acoustic performance, peak-hour is defined as M

A.

lowest noise level over a specified sample time

B.

highest noise level over various periods of time

C.

an energy-average of the noise level over a specified sample time

D.

an energy-average of noise level divided by total sample time and area of the space