Prepare effectively for your USGBC LEED-AP-BD+C LEED AP Building Design + Construction (LEED AP BD+C) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 4 / 6
Total 337 questions

How is the distance between the project site and the manufacturing location determined for Materials and Resources Credit. Building Disclosure and Optimization - Sourcing of Raw Materials. Option 2. Leadership Extraction Practices?

A.

Roadway distance

B.

Straight line distance

C.

Rail freight distance

D.

Air freight distance

A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be desirable considering the location of the project?

A.

Energy and Atmosphere Credit, Optimize Energy Performance, Exemplary Performance

B.

Indoor Environmental Quality Credit, Quality Views, Exemplary Performance

C.

Indoor Environmental Quality Credit, Acoustic Performance, Exemplary Performance

D.

Energy and Atmosphere Credit, Enhanced Commissioning, Exemplary Performance

A project attempting to meet the preferred parking requirements for Location and Transportation Credit, Green Vehicles may provide what incentive to meet the requirements and highlight the project sustainable vehicle strategy?

A.

Three years of free parking for green vehicles

B.

Preferred parking decals for 5% of occupants utilizing carpool vehicles

C.

A permanent discounted parking rate of at least 20% for all green vehicles

D.

An annual maintenance voucher for at least 5% of occupants driving green vehicles

A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope. The new building project needs to complete a new Phase I ESA if

A.

the Phase II ESA uncovers suspected contamination

B.

contamination was identified by the certified facility

C.

the certified facility's Phase I ESA is older than 180 days

D.

the local equivalent standard is more stringent than ASTM E1527-05

A project team reviews office chairs with a Type III environmental product declaration (EPD) for the five different categories of environmental impact reduction. Which of the following must the chairs demonstrate for product optimization?

A.

A reduction in at least two categories

B.

A reduction below the industry average in at least three categories

C.

A 5% reduction in all categories

D.

A 10% reduction in GHG emissions and a 10% reduction in at least two other categories

When a project team sustainably develops a project site, the design should

A.

increase water runoff

B.

maximize construction pollution

C.

remediate sites already in decline

D.

replace natural water flow patterns

Which of the following strategies would be considered an acceptable minor improvement within the wetland buffer for Location and Transportation Credit, Sensitive Land Protection?

A.

Build a two-story fitness facility

B.

Change the grade to install a security fence

C.

Provide a vehicular access drive that is less than 16 ft. (5 m) in width

D.

Remove trees that are less than 6 inches (15.24 cm) diameter at breast height

The intent of the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention is to £

A.

control erosion, noxious odors and landfill waste

B.

control erosion, landfill waste and excessive noise

C.

control erosion, waterway sedimentation and airborne dust

D.

control erosion, waterway sedimentation and noxious odors

What LEED Building Design and Construction rating system mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit?

A.

Healthcare

B.

Schools

C.

Data centers

D.

Hospitality

Showers are addressed under which prerequisites and/or credits within LEED Building Design and Construction?

A.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Indoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

B.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Water Efficiency Credit, Water Metering

C.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Prerequisite, Outdoor Water Use Reduction; and Location and Transportation Credit, Bicycle Facilities

D.

Water Efficiency Prerequisite, Indoor Water Use Reduction; Water Efficiency Credit, Cooling Tower Water Use; and Water Efficiency Credit, Water Metering

A facility manager cleaning highly reflective paving material is

A.

unnecessarily wasting water

B.

reducing the heat island effect

C.

increasing the heat island effect

D.

lowering the Solar Reflectance Index (SRI)

Which of the following credit categories identifies environmental issues that are most relevant for a project's chapter area or country?

A.

Location and Transportation

B.

Energy and Atmosphere

C.

Sustainable Sites

D.

Regional Priority

Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite,

Storage and Collection of Recyclables?

A.

Take appropriate measures for the safe collection, storage and disposal of batteries

B.

Make a waste stream projection for the entire year based on the six hours of the waste stream study

C.

Make a waste stream projection for the entire week, based on the six hours of the waste stream study

D.

Extend the waste stream study to cover a representative time period of a minimum of 24 hours to identify the top five recyclable waste streams

Commissioning (Cx) and verification are requirements to qualify for LEED certification. What are the basic systems that need to be commissioned?

A.

Electrical, Mechanical, Plumbing, and Renewable Energy

B.

Electrical, Structural, Mechanical, and Lighting

C.

Electrical, Structural, Audio Visual, and Envelope

D.

Electrical, Plumbing, Telecommunications, and Fire Suppression

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

A.

Revise the documentation and resubmit the form

B.

Abandon meeting this prerequisite

C.

Submit an appeal to Green Business Certification Inc.

D.

Ask the General Contractor to be more aggressive with recycling goals

According to Location and Transportation Credit, Sensitive Land Protection, Option 2: Floodplains requirement, projects that do not have legally adopted flood hazard maps should locate on a site that is:

A.

Entirely outside any floodplain subject to a 1% or greater chance of flooding in any given year

B.

Within a floodplain subject to a 3% or greater chance of flooding every other year

C.

Outside any floodplain subject to a 2% or greater chance of flooding in any given 5-year period

D.

Entirely outside any floodplain subject to a 3% or greater chance of flooding in any given 10-year period

A topographic assessment of a project site located 150 ft. (45 m) from a water body was conducted. The results of the slope analysis show that the site is generally sloping 6% to 8% to the northwest over most of the site, with some steep slopes located at the eastern edge of the property, which may impact the runoff volume. Which one of the following LEED credits or prerequisites will be affected by these results?

A.

Sustainable Sites Credit, Rainwater Management

B.

Sustainable Sites Prerequisite, Environmental Site Assessment

C.

Location and Transportation Credit, Sensitive Land Protection

D.

Location and Transportation Credit, High-Priority Site

The Exemplary Performance threshold for Sustainable Sites Credit, Rainwater Management requires:

A.

Utilizing a rain garden to manage the 98th percentile rainfall event

B.

Managing 100% of rainfall that falls within the project boundary

C.

Achievement of both Option 1. Percentile of Rainfall Events and Option 2. Natural Land Cover Conditions

D.

Utilizing a combination of both structural and non-structural measures to manage the 98th percentile rainfall event

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?

A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

What is the sequence of the process for LEED certification?

A.

Submit documentation through LEED Online, Choose Rating System, Review, Register, Certify

B.

Submit documentation through LEED Online, Choose Rating System, Register, Review, Certify

C.

Choose Rating System, Register, Submit documentation through LEED Online, Review, Certify

D.

Choose Rating System, Register, Submit documentation through LEED Online, Certify, Review