Prepare effectively for your iSQI CTFL-001 ISTQB Certified Tester Foundation Level certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 3
Total 338 questions

The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment? 1 credit

A.

ISO 9126

B.

IEEE 829

C.

BS 7925/2

D.

DO-178B

Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits

A.

If the scope of test performance improvement covers all test levels, TMMi is preferred since TPI focusses mainly on black-box testing.

B.

If the organization is already applying CMMI, TMMi may be preferred since it has the same structure and uses the same terminology. TMMi addresses management commitment very strongly and is therefore more suitable to support a top-down improvement process.

C.

TPI is much more a bottom-up model that is suitable for addressing test topics for a specific (test) project.

D.

TMMi can only be used with the traditional V model,whereas TPI can be used with all types of software life cycles.

Model characteristics:

Which THREE of the below mentioned characteristics relate to TMMi? 1 credit

A.

5 maturity levels

B.

Focussed on higher level testing

C.

20 key areas

D.

Highly related to CMMI

E.

Continuous model

F.

Staged model

G.

Focussed on component and integration testing

A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits

A.

Synchronized with the overall long-term organizational strategy

B.

Defined according to the maturity model used

C.

Most visible to stakeholders

D.

Low costs actions first

Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit

A.

Test environment more complex

B.

Define expectation for tasks and deliverables

C.

Clear channels of communications

D.

Possibly different cultures

E.

Testing of non-functional requirements

F.

Audit trail from requirements to test cases

G.

Applying test automation

Which of the following is a valid drawback of independent testing? 1 credit

A.

Developer and independent testing will overlap and waste resources.

B.

Developers loose the sense of responsibility and independent testers may become a bottleneck.

C.

Independent testers need extra education and always cost more.

D.

Independent testers will become a bottleneck and introduce problems in incident management.

Which of the following is a benefit of independent testing? 1 credit

A.

Code cannot be released into production until independent testing is complete.

B.

Testing is isolated from development.

C.

Independent testers find different defects and are unbiased.

D.

Developers do not have to take as much responsibility for quality.

Based on the information given in the scenario, identify how the team could be improved most effectively? 2 credits

A.

By providing training in the payroll domain

B.

By providing a workshop on test design techniques

C.

By providing specific training on the systems being tested

D.

By providing training on reviewing requirements

A number of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.

i. External test specialists perform non-functional testing.

ii. Testing is outsourced.

iii. Testing is carried out by the developer.

iv. A separate test team carries out the testing.

v. Testing is performed by the business.

vi. Testing is performed by a different developer.

Which of the following orders the above in a correct order of independence? 1 credit

A.

i, ii, iv, vi

B.

ii, i, v, vi

C.

ii, v, i, iii

D.

i, iv, v, vi

As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use? 2 credits

A.

Decision Table Testing

B.

Boundary Value Analysis

C.

Error Guessing

D.

Exploratory Testing

Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit

A.

Brainstorming

B.

Inspections

C.

Expert interviews

D.

Independent assessments

Which of the following is a project risk mitigation step you might take as test manager? 1 credit

A.

Testing for performance problems

B.

Hiring a contractor after a test analyst leaves the company

C.

Arranging a back-up test environment in case the existing one fails during testing

D.

Performing a project retrospective meeting using the test results after each increment

Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits

A.

The concerns over the user interface may lead to changes to the interface which cannot be implemented by development in time for the second test iteration.

B.

The concerns over the user interface raises the likelihood of a risk in that area and increases the amount of test effort needed for the user interface, thereby limiting the test effort available for other parts of the test management tool.

C.

The delivery of the application without the interface changes may upset the user community.

D.

The method used for test estimation is not accurate enough and hence the money spent on testing exceeded its budget.

Which test management control option is most appropriate to adopt under these circumstances? 2 credits

A.

Introduce mandatory evening and weekend working to retrieve the 3 week slippage.

B.

Reconsider the exit criteria and review the test plan in the context of the current situation.

C.

Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.

D.

Arrange a meeting with the user community representatives to discuss the user interface.

Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits

A.

The skills and experience of developers to correct the failures.

B.

The standards used for the requirements specification.

C.

The metrics recorded from testing the capture-replay tool.

D.

The number of testers in the company and their grade.

Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits

A.

No priority or severity assigned

B.

Incident numbering is manual rather than automated

C.

No mentioning of reproduceability

D.

No classification on type of incident

In general which part of the testing activity is most difficult to estimate? 1 credit

A.

Test planning

B.

Test execution

C.

Test management

D.

Test design

Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)

A.

Test planning, test case preparation and test execution for each of the four iterations

B.

Work should be explicitly allocated to test completion, test management, installation and to training on using the system

C.

Activities to deploy the system in the user environment

D.

Regression testing in the second, third and fourth iterations

E.

Development activities for unit and integration testing

F.

Reviews on requirements documentation

G.

Defining test environment requirements for system testing

In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons. 1 credit

A.

The quality of the development estimate may be poor.

B.

In general bottom-up estimation is always better than top-down estimation.

C.

The percentage based technique only applies to the V life cycle model.

D.

Using the same percentage every time does not address the level of risk of the application to be tested.

E.

The maturity of the organization, e.g. the quality of the test basis, quality of development testing, configuration management, availability of test tools, also influence the effort needed for testing.

F.

It builds on large set of historical data

G.

The result is almost always a too low estimate for the required test effort

Which aspect in the test estimate is the main risk in this project? 1 credit

A.

Quality of the specification

B.

Availability of end-users

C.

The costs of hardware and tools

D.

Unknown input quality due to third party development