Prepare effectively for your AACE International PSP Planning & Scheduling Professional (PSP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 3
Total 163 questions

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

A.

Budget at completion (BAC)

B.

Budgeted cost of work performed (BCWP)

C.

Estimate to complete (ETC)

D.

Estimate at completion (EAC)

The addition of which of the following relationships would cause a logic loop?

A.

O H - D

B.

O C - J

C.

O F-I

D.

O l-C

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

A.

ADM is limited to finish-to-start logic relationships, while PDM is not.

B.

PDM is a bar chart with network logic, while ADM is a pure logic network.

C.

ADM is manual CPM calculations, while PDM is computerized.

D.

ADM uses arrows, while PDM uses boxes.

Which of the following is NOT input data to the construction planning process?

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

When resource leveling craft labor for a critical path schedule, the scheduler

A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

What does the narrow band at "Y" represent?

A.

Resource limitation period.

B.

A rework period.

C.

Activity inactivity.

D.

You cannot tell with the information supplied.

Which of the following phases does NOT describe the commonly accepted construction life cycle?

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don't follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

A.

4001, 5001, and 6001

B.

2003 and 7001

C.

4001 and 5001

D.

2004, 4001. and 5001

What activities are concurrent to Activity 2001 in the "normal" schedule?

A.

7001.

B.

1001.

C.

1000.

D.

2003.

What is the actual duration as of the status date or data date of Activity B?

A.

7.

B.

3.

C.

0.

D.

4.

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

What project cost elements would NOT normally be reflected in the Activity 1000?

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects

The BEST reason to use multiple calendars is to:

A.

more accurately show how the project will be built

B.

allow each specialty contractor to have a unique schedule of work/non-work periods

C.

track owner activities according to their specific calendar in order to develop a good

working relationship

D.

evaluate float for the benefit of the contractor

What portion of Activity B is on the critical path?

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

A.

3.9% (1 : 25.708)

B.

2.3% (1 : 43.501).

C.

9.1% (1 : 11.000).

D.

8.6% (1 : 11.591)

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.