Prepare effectively for your AACE International PSP Planning & Scheduling Professional (PSP) Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 4
Total 216 questions

Each of the following accurately describes total float in a schedule EXCEPT:

A.

The amount of time an activity can be delayed without delaying the overall project completion time.

B.

Can be positive or negative.

C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Control Level Schedule activities are NOT one of the following:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

What portion of Activity B is on the critical path?

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

A KPI is an acronym for:

A.

Key Planning Index

B.

Known Planning Impediments

C.

Keep Parameter Integrity

D.

Key Performance Indicator

The Work Breakdown Structure (WBS) is established to reflect the:

A.

lowest level of the project estimate

B.

lowest level reporting back to the program WBS

C.

lowest level of effort scope

D.

lowest level where the work is managed

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

A.

Industry publications.

B.

Critical path schedules prepared by you for similar completed projects.

C.

The Petrochemical Industry New Plant Task Duration Handbook.

D.

The cost estimate for the plant prepared by your firm's estimating department.

The EBS is established by:

A.

The contractor s planning and scheduling office

B.

The government entity with the authority to approve/stop the work

C.

The entity with the authority to fund and direct the enterprise

D.

The contractors and subcontractors

EBS is an acronym for:

A.

Elongated Budget Synopsis

B.

European Basic Schedule

C.

Enterprise Breakdown Structure

D.

Eventual Base Structure

When are KPIs defined?

A.

At project initiation

B.

At NTP

C.

At the start of the Construction Phase

D.

After the Bidding Phase

A good change management plan___________.

A.

is provided to stakeholders after it is created

B.

is detailed during the planning phase

C.

tracks minor decisions

D.

involves only the project controls team

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

When resource leveling craft labor for a critical path schedule, the scheduler

A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

Should activities be coded with the EBS value?

A.

Yes. the project coding should roll up to EBS values

B.

No. only a few EBS values exist at the activity level

C.

No. the EBS Is much higher than activity coding

D.

Yes. the EBS is the most important project coding level

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Which of the following project planning situations is the most frequent contributor to cost overruns?

A.

lack of detailed planning for operational start-up

B.

Insufficient planning for change management

C.

Inappropriate definition of work breakdown structure

D.

Inadequate definition of scope at the estimate (budget) stage

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

255 days

C.

267 days

D.

477 days

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort