AgilePM-Practitioner APMG-International Agile Project Management (AgilePM) Practitioner Exam Free Practice Exam Questions (2025 Updated)
Prepare effectively for your APMG-International AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Total 134 questions
Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?
Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not
happen again.
Which Agile principle MOST influences this course of action?
A three-month timeframe has been specified to catch the seasonal sales window.
Which Agile principle MOST influences this course of action?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the
project in the Prioritised Requirements List?
The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-
rounds of the new bedroom and en-suite bathroom facilities throughout the project.
Is this an appropriate application of Agile Project Management for this project?
During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what
needed to be done before these would be acceptable.
Is this an appropriate application of Agile Project Management for this project?
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.
The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions.
Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.
The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director's leadership team in the UniCo building. At the last Operations' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.
Is this an appropriate approach to reward the brain in the need for 'status', and
why?
The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.
Which preference does this behavior BEST display?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?
Answer the following questions about applying the principles for building
engagement to the Change Programme, defined by Hodges.
Which 2 actions demonstrate inclusivity?
Which approach is the MOST likely to ensure that the participants apply themselves productively to the co-design tasks in a workshop?
Which tool is likely to be the MOST useful in a co-design workshop for summarizing staff or customer reactions to a situation?
Total 134 questions