Prepare effectively for your Adobe AD0-E911 Adobe Workfront Project Manager Certified Professional certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 2
Total 95 questions

Given this information regarding a Task:

    Planned Start Date: May 14

    Actual Start Date: May 14

    Planned Completion Date: May 20

    Projected Completion Date: May 22

    Percent Complete: 50%

    Duration: 5 Days

    Planned Hours: 8 Hours

    Status: In Progress If today ' s date were May 19, what would be the Task ' s progress status?

A.

Behind

B.

On Time

C.

At Risk

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

A.

Projected Date

B.

Planned Date

C.

Estimated Date

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

A task won’t close when trying to select “Complete.”

Which two reasons block someone from being able to close a task? (Choose two.)

A.

A predecessor task is “In Progress.”

B.

The subtasks are not “Complete.”

C.

The task is a predecessor to another task.

D.

The task is assigned to a job role and not an individual user.

E.

The project is “Active.”

A project manager is updating a project in Workfront that is behind schedule.

Which action could be taken so that all tasks are completed by the requested completion date?

A.

Give all tasks a Task Constraint of “Must Start On”

B.

Reduce the durations of the tasks.

C.

Adjust all of the Planned Start Dates to the same day.

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

A.

Assigned To

B.

Assignments

C.

Assigned

Which date type should an assignee update to change the completion date of a task?

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date