ISEB-PM1 BCS Foundation Certificate in IS Project Management Free Practice Exam Questions (2025 Updated)
Prepare effectively for your BCS ISEB-PM1 BCS Foundation Certificate in IS Project Management certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
All of the following are tools and techniques of the Contract Administration process except for which one?
A project involves arranging for the closing of the company office where the team works and relocating everyone to a new city. The BEST thing the project manager can do is:
Which of the following are inputs to Activity Definition?
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.
What is the cost variance?
What provides information regarding the ways people, teams, and organizational units behave?
Company A is launching a new communications satellite system. Resource B was assigned combined projects of design, construction, integration, and launch of the satellite.
Resource B's role is that of a:
Which of the following statements is in agreement with McGregor's concepts concerning Theory X and Theory Y managers?
Inspection is a tool and technique for which of the following processes?
Which one of the following is true regarding the change control board?
At the end of the project, what will be the value of SV?
The widget production project is well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgets inspected, 47 percent fell within the acceptable weight range. This is an example of:
A project manager is assigned to a project which phase of the project?
The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:
Stakeholder analysis identifies what information and relates it to the purpose of the project?
The most rapid Estimate Costs technique is ___________.
What is the minimum a project schedule must include?
The initial development of a Project Scope Management plan uses which technique?
The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:
What does a SPI value greater than 1.0 indicate?
In which of the following contract types does the buyer have the most cost risk?
While reviewing project performance, the project manager determines that the schedule variance is -500.
What is the BEST thing to do?
Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?
Risk event is the description of what may happen to the _____ of the project.
Objectives can be described as all of the following except for which one? Choose the least correct answer.
What is the function of a Project Management Office (PMO)?
What cost control technique is used to compare actual project performance to planned or expected performance?
Which is one of the determining factors used to calculate CPI?
Which of the following provides a comprehensive and consistent method of controlling the project and ensuring its success?
In which of the following team development stages does the team meet and learn about the project and their formal roles and responsibilities?
Reserve Analysis a technique not used in: