Prepare effectively for your BICSI RCDDv14.1 BICSI Registered Communications Distribution Designer – RCDDv14.1 certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
In a PTP network using optical fiber, the ________ is responsible for media conversions from the optical fiber to the balanced twisted pair network within the residence.
You are designing a system requiring the transmission of data. Your system must perform higher than ________ kHz in order to do so.
A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?
ICT project installation issues that require coordination with mechanical, electrical and/or other "trades" can be BEST accomplished by
For optical fiber cabling, which of the following test instruments is used to locate and identify any anomalies?
Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
In a program's definition phase a program manager in country A is assigned to expand a restaurant chain into country B. communications management plan zThe program manager creates the program team by identifying the required protect management resources
Which of the following represents an initial step needed to evaluate available resources that are aligned with me program's needs''
Which of the following options BEST describes Request for Quote (RFQ)?
A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component protect requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.
What is a critical component of the Program Schedule Management Process?
External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor
What should the program manager do?
What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)
How many classes of telecommunications administration are there?
Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another
How should the program manager decide which template is appropriate?
The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter What increase in usable floor space should another 103 mm (four trade size) sleeve be added?
How does a portfolio’s collection of work differ from that of a program's collection of work?