Prepare effectively for your Exin CDCS EXIN EPI Certified Data Centre Specialist certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 2
Total 120 questions

You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.

A.

12 Amperes

B.

30 Amperes

C.

60 Amperes

D.

80 Amperes

The air intake of the mission-critical server at the top of the rack is measuring 25 °C/77 °F.

Is this acceptable?

A.

Yes, this is allowed according to the standards and guidelines

B.

As long as it does not exceed the average server room temperature of 38 °C/100 °F

C.

Depends on the ANSI/TIA-942 Rating the data center needs to comply with

D.

No, the temperature needs to be 20 °C/68 °F

In which stage of the data center life cycle does testing and commissioning take place?

A.

Design stage

B.

Implement stage

C.

Operate/optimize stage

D.

Retire stage

Where should perforated tiles be installed?

A.

At the back of racks

B.

Every 5th rack

C.

One tile per rack in front

D.

As close to AC as possible

Which standard defines the requirements for network administration?

A.

ISO/IEC 30129

B.

ANSI/TIA-568

C.

ASHRAE

D.

ANSI/TIA-606

Which formula is correct?

A.

Phase-to-Neutral Voltage = Phase-to-Phase voltage * 1.732

B.

Phase-to-Neutral Voltage = Phase-to-Phase voltage /1.732

C.

Phase-to-Neutral Voltage = Phase-to-Neutral voltage * 1.732

D.

Phase-to-Neutral Voltage = (Phase-to-Phase voltage * 1.732) / Phase-to-Neutral Voltage

What is the focus of the Open Compute Project (OCP)?

A.

Saving energy, materials, and costs

B.

Standardizing equipment only for hyperscale data centers

C.

Developing an open-source operating system

D.

Making cloud computing more accessible

When installing a raised floor, can we use a spirit level bar to level the floor?

A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

What should be considered when installing overhead data cabling?

A.

To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.

B.

Copper data cabling should not be placed in metal cable trays.

C.

Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

D.

All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.

Which efficiency indicator accounts for all cooling costs (installation, operation, disposal)?

A.

HER

B.

COP

C.

PUE

D.

LCC

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

An air-conditioner unit needs to be selected. Two types are available:

Unit-A has a Sensible Heat Ratio (SHR) of 0.7.

Unit-B has a Sensible Heat Ratio (SHR) of 0.9.

From an efficiency point of view, which one should be selected?

A.

It does not matter, as the Sensible Heat Ratio has nothing to do with efficiency.

B.

Not relevant, as Sensible Heat Ratio is only specified for air-conditioner equipment to indicate the ratio between intake temperature and exhaust temperature.

C.

Unit A

D.

Unit B

What mainly affects the cooling capacity of a raised floor tile?

A.

Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle

B.

Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile

C.

Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

D.

Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile

What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?

A.

Two feeds coming from two different substations, one power company is not acceptable

B.

Two feeds coming from two different substations, one power company is acceptable

C.

Two feeds entering the data center building from one substation

D.

One feed from one substation split over two separated distribution boards in separate rooms

A computer room is fitted with a hypoxic-based fire suppression system. On what principle does it work?

A.

It removes the heat from the fire

B.

It lowers the oxygen levels in the room

C.

It removes the fuel from the fire

D.

It uses water as an extinguisher

When designing a data center network, your company wants to minimize the number of network cables to install. What type of physical cabling layout would be the best choice?

A.

Top of Rack (ToR) design

B.

End of Row (EoR) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout