Prepare effectively for your GIAC GCPM GIAC Certified Project Manager Certification Practice Test certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
You are the project manager for PassGuide Inc. Your project has a budget at completion of $950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone.
What is the project's cost performance index?
Which of the following components of communication is described in the statement below?
"It describes the pitch, tone, and inflections of a message that affect what the message means."
You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?
Charlie has just completed the project according to the terms of the contract. She and the customer are completing a walk through of the project deliverables, and the customer is asking for changes to the deliverables before she'll accept the product. What project management Mprocess should manage the documented change request that may come from scope verification?
Which of the following are outputs of the Plan Quality process?
Each correct answer represents a complete solution. Choose all that apply.
Which of the following is described in the statement below?
"It is a form of discussion held in person or by electronic means. Its goal is to come to a written agreement regarding a business matter."
You work as a project manager for PassGuide Inc. You want to calculate the minimum completion time for a project along with the possible start and finish times for the project activities. Which of the following techniques will you use to accomplish the task?
You have just completed scope verification for your project. This process creates three deliverables for the organization. Which one of the following is not an output of the scope verification process?
You work as a project manager for PassGuide Inc. You want to share the organization strategic ideas, tasks, dependencies, and associations with team members. Which of the following will help you to achieve the above task?
You work as a project manager for PassGuide Inc. Which of the following processes will you use to aggregate the probable costs of individual activities or work packages to set up an authorized cost baseline?
Which of the following are inputs of the Perform Integrated Change control process?
Each correct answer represents a complete solution. Choose all that apply.
A company is hiring project manager for its new project. Which of the following skills of a professional should it weigh most?
Which of the following is a document that covers the work that will be done, how the work will be compensated, and any penalties for noncompliance?
Which of the following process groups involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan?
Jeff works as a project manager for PassGuide Inc. He has to adjust the amount of time between two activities. He wants to delay the start of the second activity by 14 hours. Which of the following scheduling components will Jeff add to the second activity?
In which process group does the project manager and the performing organization choose the vendors the project will use?
You work as a project manager for PassGuide Inc. You and your team are working on the probability and impact matrix. You have to determine the importance of risk and prioritize it accordingly.
Which of the following will help you achieve the above task?
In which of the following processes is it ensured that the human resources are available and the required team is obtained for completing the project assignments?
The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process?
Each correct answer represents a part of the solution. Choose all that apply.