CA0-001 PMI Certified Associate in Project Management (CAPM) Certification Free Practice Exam Questions (2025 Updated)
Prepare effectively for your PMI CA0-001 Certified Associate in Project Management (CAPM) Certification certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
What cost control technique is used to compare actual project performance to planned or expected performance?
Which of the following is a technique for resolving conflict?
At the end of the project, what will be the value of SV?
Which of the following is a conflict resolving technique that emphasizes areas of agreement rather than areas of difference?
A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month. Which tool or technique is used in this case?
During what process is the quality policy determined?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entire process, the goal is 10 and the standard deviation is 1.
For this data set, it is correct to say that the process:
What scope definition technique is used to generate different approaches to execute and perform the work of the project?
Regardless of style, what information is shown in a process flowchart?
Providing forecasts to update current cost and schedule information is a part of which process?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
Given the following values, what is the calculated expected activity cost (CE) when using PERT?
CO = $7,000
CM = $10,500
CP = $11,000
Company A is delivering a product in three parts. The contract allows for the parts to be delivered either one after the other or at the same time.
Which type of project phasing will allow for the most flexibility in delivering the full product when product requirements are subject to rapid change?
Who must accept the end product for a project to be considered closed?
Which of the following is a tool or technique of the Collect Requirements process?
Who decides buyer and seller roles in a teaming agreement?
A business case is an input to which of the following processes?
Which of the following is an input to direct and manage project execution?
Expected Monetary Value (EMV) analysis is commonly used in:
What is the first step in preparing the risk register?
Which of the following equations is used to calculate schedule variance?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?
What is a technique used in the performance reporting process?
What does a SPI value greater than 1.0 indicate?
What is a specific advantage of analogous estimating in comparison with other cost estimate techniques?
Which of the following is an input to the Direct and Manage Project Execution Process?
Which of the following is a tool or technique for distribute information?