Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 7
Total 1320 questions

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

Which element does a project charter contain?

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Perform Quantitative Risk Analysis focuses on:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives.

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

A.

Program

B.

Functional

C.

Project

D.

Portfolio

A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.

How can the manager document the business value for the Portfolio Steering Committee?

A.

Conduct a feasibility study to determine the business impact of the new product.

B.

Prepare a benefits management plan to capture target benefits and strategic alignment.

C.

Execute a market study for similar products and demonstrate a market need.

D.

Create a presentation outlining the business benefits of the new product.

What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?

A.

Plan Schedule Management

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Durations

Which statement correctly describes the value of a business case?

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

A regression line is used to estimate:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Who is responsible for initiating a project?

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Stakeholder satisfaction should be managed as a key project:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)

A.

Project audit

B.

Deliverable acceptance

C.

Risk register tracking

D.

Stakeholder mapping

E.

Issue log update

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Outputs of the Control Communications process include:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Which input to the Plan Risk Management process provides information on high-level risks?

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Which document can help a project manager to leverage historical project information?

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Match each tool or technique with its corresponding Project Cost Management process.

The key benefit of the Monitoring and Controlling Process Group is the ability to:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

What is an output of the plan resource management process

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Under which circumstances should multiple projects be grouped in a program?

A.

When they are needed to accomplish a set of goals and objectives for an organization

B.

When they have the same project manager and the same organizational unit

C.

When they have the same scope, budget, and schedule

D.

When they are from the same unit of the organization

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

A.

Expand the scope of the project.

B.

Schedule the tasks in sequence.

C.

Increase quality review cycles.

D.

Schedule the tasks in parallel.

Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?

A.

Influence and challenge

B.

Innovation and administration

C.

Leadership and management

D.

Engagement and guidance

In a typical project, project managers spend most of their time:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

What is the process of ensuring that project resources are assigned and available?

A.

Control Procurements

B.

Acquire Resources

C.

Control Resources

D.

Plan Procurement Management

A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity. How can the project manager assist the team to resolve the issue?

A.

Request the new resource be relocated with the rest of the team and document a change request forthe project.

B.

Ask the team to identify possible options to resolve the issue with minimal impact to the new resource.

C.

Log this issue in the issue log and escalate it to the management team, asking them to replace the new team member.

D.

Consult the communications management plan to review available options, such as special virtual meetings, with the new resource.

Which is an example of analogous estimating?

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

An example of a group decision-making technique is:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

A.

Control chart

B.

Flowchart

C.

Checksheet

D.

Pareto diagram

What is the number of stakeholders, if the project has 28 potential communication channels?

A.

7

B.

8

C.

14

D.

16

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.

Which are examples of processes that may be used once or at predefined points in the project life cycle?

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.

BAC

B.

EAC

C.

ETC

D.

WBS

A project manager called for a team meeting...................method did the team use

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

A.

Rolling wave planning

B.

Expert Judgement

C.

Decomposition

D.

Data analysis

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

How is program success measured?

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner

B.

By the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Who determines which dependencies are mandatory during the Sequence Activities process?

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

The process of prioritizing risks for further analysis or action is known as:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Risk categorization is a tool or technique used in which process?

A.

Plan Risk Responses

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Page: 2 / 7
Total 1320 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved