CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which organizational process asset can make an impact on the outcome of a project?
A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
In complex projects/ initiating processes should be completed:
What is the function of a Project Management Office (PMO)?
A project manager should communicate to stakeholders about resolved project issues by updating the:
What organizational asset can influence the Plan Risk Management process?
Which conflict resolution technique produces the most lasting results?
The product scope description is used to:
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
Which tools and techniques will a project manager use to develop a project charter?
Which of the following is an output from Control Scope?
Which component of the project management plan should be updated if a change occurs?
Projects are separated into phases or subprojects; these phases include:
A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?
A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
Which can be used to convert a verified deliverable to an accepted deliverable?
A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.
To reduce the risk with this approach, which step should the business analyst take?
During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
The links between the processes in the Process Groups are often:
Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
The following is a network diagram for a project.
The free float for Activity H is how many days?
In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?
When would resource leveling be applied to a schedule model?
Which Process Group and Knowledge Area include the Sequence Activities process?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
Which process uses expert judgment to manage project resources?
Which technique is utilized in the Control Schedule process?
Which document includes the project scope, major deliverables, assumptions, and constraints?
What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
Which of the following are outputs of the Define Scope process in Project Scope Management?
Inputs to the Plan Schedule Management process include:
A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.
How should the project manager proceed?

As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming.
What should the project manager have done to avoid this situation?
A member of the agile project team has questions about a task which will start in the next sprint. The team member needs clarification from the product owner regarding some inconsistencies. When should the team discuss these inconsistencies?
For what project management process is work performance information an output?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which of the following lists represents the outputs of the Monitor Communications process?
A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.
Which approach should the project manager take?
Perform Quantitative Risk Analysis focuses on:
The key benefit of the Monitoring and Controlling Process Group is the ability to:
The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.
Which of the 5Cs of written communications does the project manager need to address?
Stakeholder identification and engagement should begin during what phase of the project?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
Which of the following activities are included as part of a project manager ' s responsibilities?



