CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2025 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Risk responses reflect an organization's perceived balance between:
A tool and technique used during the Collect Requirements process is:
An input of the Create WBS process is:
During project selection, which factor is most important?
Which of the following is an output of the Conduct Procurements process?
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
Who determines which dependencies are mandatory during the Sequence Activities process?
The diagram below is an example of a:
An input to the Collect Requirements process is the:
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Plan-do-check-act is also known as:
An input to the Estimate Activity Resources process is:
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
The completion of the project scope is measured against the:
Projects are separated into phases or subprojects; these phases include:
The three processes of Project Cost Management are:
What happens to a stakeholder's project influence over time?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
The initial development of a Project Scope Management plan uses which technique?
The total of the planned value (PV) is also known as:
Which of the following includes how requirements activities will be planned, tracked, and reported?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
Activity cost estimates are quantitative assessments of the probable costs required to:
Which of the following is a strategy to deal with positive risks or opportunities?
Which of the following is an output of Close Procurements?
What is project management?
Which characteristics do effective project managers possess?
One of the objectives of a quality audit is to:
At the end of the project, what will be the value of SV?
Which of the following is a project constraint?
Which of the following is an input to Direct and Manage Project Execution?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
Which quality control technique illustrates the 80/20 principle?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Which of the following can be used as an input for Define Scope?
The process for performing variance analysis may vary, depending on:
Administer Procurements is part of which Process Group?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which risk response strategy is common for both positive and negative risks?
Which technique is utilized in the Control Schedule process?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Which input will be used when tasked with developing the human resource plan?
Exhibit A is an example of which of the following types of Sequence Activities?
Which of the following is a tool or technique used in the Determine Budget process?
Resource calendars are included in the:
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
The process of identifying specific actions to be performed to produce project deliverables is:
Which of the following is an input to the Develop Project Charter process?
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Expected monetary value (EMV) is computed by which equation?
Inputs to the Plan Risk Management process include the:
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
How does a requirements traceability matrix help to determine whether a product is ready for delivery?
Select three processes that are associated with Project Schedule Management.
What does leadership involve?
What is the recommended approach for handling risk in a high-variability environment?
The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?