Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 2 / 7
Total 1337 questions

Which organizational process asset can make an impact on the outcome of a project?

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

A.

Engage customer earlier

B.

Conduct quality audits

C.

Validate Scope

D.

Validate quality requirements

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

A.

Develop Schedule

B.

Create VVBS

C.

Estimate Activity Resources

D.

Define Scope

In complex projects/ initiating processes should be completed:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

A project manager should communicate to stakeholders about resolved project issues by updating the:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

What organizational asset can influence the Plan Risk Management process?

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

Which conflict resolution technique produces the most lasting results?

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

The product scope description is used to:

A.

Gain stakeholders ' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Which tools and techniques will a project manager use to develop a project charter?

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Which of the following is an output from Control Scope?

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Which component of the project management plan should be updated if a change occurs?

A.

Project charter

B.

Project baseline

C.

Assumption log

D.

Schedule forecast

Projects are separated into phases or subprojects; these phases include:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Which can be used to convert a verified deliverable to an accepted deliverable?

A.

Decomposition

B.

Reporting

C.

Voting

D.

Brainstorming

A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.

To reduce the risk with this approach, which step should the business analyst take?

A.

Add the risk to the risk register so other stakeholders are aware of the approach.

B.

Distribute the documented requirements to relevant stakeholders in all time zones for review and comment.

C.

Ask the stakeholders in the elicitation sessions to speak on behalf of stakeholders in other time zones.

D.

Request the project sponsor to approve this requirements elicitation approach for this project.

During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?

A.

Submit a change request for additional budget to secure a project resource.

B.

Consult with the functional manager for a replacement resource.

C.

Distribute work to other team members to reduce impact to the project schedule.

D.

Consult the risk register for an appropriate risk response.

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

The links between the processes in the Process Groups are often:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

The following is a network diagram for a project.

The free float for Activity H is how many days?

A.

4

B.

5

C.

10

D.

11

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

A.

The organization

B.

The project

C.

The industry

D.

The product

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

A.

Three-point estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Data analysis

Which process uses expert judgment to manage project resources?

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Manage Team

D.

Both A and B

Which technique is utilized in the Control Schedule process?

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Which document includes the project scope, major deliverables, assumptions, and constraints?

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.

100

B.

120

C.

1,000

D.

1,200

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

A.

USS-30,000

B.

US$120,000

C.

US$370,000

D.

US$400,000

Which of the following are outputs of the Define Scope process in Project Scope Management?

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project scope statement and project documents updates

D.

Scope baseline and project documents updates

Inputs to the Plan Schedule Management process include:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity ' s prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?

A.

Perform Integrated Change Control.

B.

Conduct a risk assessment with the team.

C.

Update the schedule to include compliance.

D.

Manage Stakeholder Engagement.

As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming.

What should the project manager have done to avoid this situation?

A.

Coupled inexperienced team members with individuals having extensive knowledge in the required field

B.

Had open and transparent planning that engages internal and external stakeholders

C.

Held regular meetings more often with team members to check on their progress and obstacles

D.

Diversified more of the project team to capture a broad range of experiences

A member of the agile project team has questions about a task which will start in the next sprint. The team member needs clarification from the product owner regarding some inconsistencies. When should the team discuss these inconsistencies?

A.

During the next sprint planning

B.

During the next sprint meeting

C.

During the next sprint review session

D.

During the next sprint retrospective

For what project management process is work performance information an output?

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Which of the following lists represents the outputs of the Monitor Communications process?

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?

A.

Escalate

B.

Mitigate

C.

Avoid

D.

Transfer

Perform Quantitative Risk Analysis focuses on:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives.

The key benefit of the Monitoring and Controlling Process Group is the ability to:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Stakeholder identification and engagement should begin during what phase of the project?

A.

After the project management plan is completed

B.

After the stakeholder engagement plan is completed

C.

As soon as the project charter has been approved

D.

After the communications management plan is completed

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.

BAC

B.

EAC

C.

ETC

D.

WBS

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

A.

Expand the scope of the project.

B.

Schedule the tasks in sequence.

C.

Increase quality review cycles.

D.

Schedule the tasks in parallel.

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (TandM)

D.

Cost Plus Incentive Fee Contract (CPIF)

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating

Which of the following activities are included as part of a project manager ' s responsibilities?

A.

Direct, control, and focus on structure.

B.

Problem solve , achieve the bottom line, and focus on success.

C.

Control, maintain project status, and develop.

D.

Inspire, engage, and build relationships with people.

Page: 2 / 7
Total 1337 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved