Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 7
Total 1320 questions

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Which tool or technique is used in Manage Stakeholder Expectations?

A.

Stakeholder management strategy

B.

Communication methods

C.

Issue log

D.

Change requests

Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Which of the following is an example of the simplest fixed-price contract?

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

In which of the risk management processes is the processes is the project charter used as an input?

A.

Palm Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

The process of defining how the project scope will be validated and controlled is known as:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

An output of the Create WBS process is:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?

A.

Plan Cost Management

B.

Estimate Activity Resources

C.

Estimate Costs

D.

Determine Budget

Which of the following is provided by the critical path method?

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

A.

Negative

B.

Zero

C.

Positive

D.

Free

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Which type of risk diagram is useful for showing time ordering of events?

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.

Which of the following elements is the team using?

A.

Definition of ready (DoR)

B.

Burndown chart

C.

Backlog refinement

D.

Definition of done (DoD)

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

A.

Plan Quality Management

B.

Control Quality

C.

Risk Management

D.

Plan Scope Management

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

A.

Identify the crashed project schedule to find the shortest duration to complete the project.

B.

Identify the longest activity path in the schedule with the shortest possible duration.

C.

Identify the tasks with float duration, which do not impact the duration of the project.

D.

Identify the path through the schedule with leveled resources and the shortest duration.

Completion of the product scope is measured against the product:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

A.

Team velocity in past iterations

B.

Related epics of each story

C.

Product owner ' s priorities

D.

Detailed acceptance criteria

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

A.

The organization

B.

The project

C.

The industry

D.

The product

What is the best tool to calculate the critical path on a project?

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

A.

Storyboarding

B.

Wireframes

C.

Data simulation

D.

Report prototyping

The precedence diagramming method (PDM) is also known as:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Which project performance domain is the work breakdown structure (WBS) developed?

A.

Development approach and life cycle

B.

Delivery performance

C.

Project work

D.

Planning

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Labor, materials, equipment, and supplies are examples of:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team

Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

A.

Build vs. buy

B.

Expert judgment

C.

Alternatives identification

D.

Product analysis

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Which statement describes the Monitor Communications process?

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?

A.

Risk management plan

B.

Communications management plan

C.

Change management plan

D.

Stakeholder engagement plan

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (TandM).

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

A.

Organizational standard processes

B.

Marketplace conditions

C.

Historical information

D.

Templates

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

A.

-8000

B.

-2000

C.

2000

D.

8000

In which project risk management process is the data analysis technique not used?

A.

Plan Risk Management

B.

Implement Risk Response

C.

Monitor Risks

D.

Perform Quantitative Risk Analysis

Agile release planning provides a high-level summary timeline of the release schedule based on.

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Which tool should a project manager use to calculate cost variance for a project?

A.

Contingency analysis

B.

Review lessons learned from similar projects

C.

Expert judgment

D.

Actual cost

Which tool or technique is used in the Estimate Costs process?

A.

Acquisition

B.

Earned value management

C.

Vendor bid analysis

D.

Forecasting

An input of the Plan Procurement Management process is:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

A.

Portfolios

B.

Standards

C.

Concepts

D.

Programs

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

A.

-700

B.

-200

C.

200

D.

500

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

A.

5

B.

2

C.

3

D.

4

Which tools and techniques should a project manager use to monitor risks?

A.

Expert judgment, data analysis, and interpersonal and real skills

B.

Data analysis, audits, and decision making

C.

Expert judgement, audits, and decision making

D.

Meetings, data gathering, and expert judgment

Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?

A.

Conduct Procurements B Plan Procurement Management

B.

Plan Risk Responses

C.

Plan Risk Management

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)

A.

Many expected simple scope change requests

B.

Few expected simple scope change requests

C.

Routine and repetitive activities

D.

Collocated project teams

E.

Use of established templates

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A.

Slack

B.

Float

C.

Lag

D.

Lead

In which Project Cost Management process is work performance data included?

A.

Plan Cost Management

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.

B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge

C.

An iteractive scheduling and on-demand, pull-based scheduling will be required.

D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted

Page: 1 / 7
Total 1320 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved