CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?
Which tool or technique is used in Manage Stakeholder Expectations?
Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
Which of the following is an example of the simplest fixed-price contract?
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
In which of the risk management processes is the processes is the project charter used as an input?
The process of defining how the project scope will be validated and controlled is known as:
A technique used to determine the cause and degree of difference between baseline and actual performance is:
An output of the Create WBS process is:
The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?
Which of the following is provided by the critical path method?
A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
Which input provides suppliers with a clear set of goals, requirements, and outcomes?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Which type of risk diagram is useful for showing time ordering of events?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?
Completion of the product scope is measured against the product:
An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?
Typical outcomes of a project include:
In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?
What is the best tool to calculate the critical path on a project?
What prototyping technique shows a sequence or navigations through a series of images or illustrations?
The precedence diagramming method (PDM) is also known as:
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
Which project performance domain is the work breakdown structure (WBS) developed?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
Labor, materials, equipment, and supplies are examples of:
During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
An issue log is an input to which Project Human Resource Management process?
Which statement describes the Monitor Communications process?
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
In which project risk management process is the data analysis technique not used?
Agile release planning provides a high-level summary timeline of the release schedule based on.
Which tool should a project manager use to calculate cost variance for a project?
Which tool or technique is used in the Estimate Costs process?
An input of the Plan Procurement Management process is:
A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
Which tools and techniques should a project manager use to monitor risks?
Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?
Which baselines make up the performance measurement baseline?
A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
In which Project Cost Management process is work performance data included?
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?