Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 1 / 7
Total 1337 questions

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

What organizational process asset (OPA) can impact a project?

A.

Marketplace conditions

B.

Preapproved supplier lists

C.

Physical environmental elements

D.

Legal restrictions

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?

A.

Traceability matrixB Lessons learned

B.

Change control proceduresD Resource availability

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

A.

Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.

B.

Make surveys among the stakeholders and meet with the team once a month.

C.

Create a social network and post news there.

D.

Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Which statement describes the Monitor Communications process?

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

Due to today ' s competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?

A.

Planning and risk management skills

B.

Communication and time management skills

C.

Business intelligence and leadership skills

D.

Strategic and business management skills

Which process involves developing an approximation of the monetary resources needed to complete project activities?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Which task will a project manager undertake while conducting Project Resource Management?

A.

Identity the different aspects of me team to manage and control physical resources efficiently.

B.

Procure equipment, materials, facilities, and infrastructure for the project.

C.

Train the team members in project skill sets.

D.

Define the roles and responsibilities of each team member.

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Taking out insurance in relation to risk management is called what?

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Success is measured by benefits realization for a:

A.

strategic plan

B.

project

C.

portfolio

D.

program

The integrative nature of project management requires which Process Group to interact with the other Process Groups?

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Project Management

What are the Project Procurement Management processes?

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

The process for performing variance analysis may vary, depending on:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?

A.

Add the risk to the project risk register, as the lack of solutions could impact how the product is built.

B.

Add the issue to the project issue log, as it will impact the project performance.

C.

Facilitate a brainstorming session for the team to discuss ideas to solve the problem.

D.

Meet with the project sponsor to understand their vision on how to address the problem.

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

A.

Close Project or Phase

B.

Conduct Procurements

C.

Control Procurements

D.

Close Procurements

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.

$800

B.

$1000

C.

$1250

D.

$1800

The Define Scope process is in which of the following Process Groups?

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Enterprise environmental factors are an input to which process?

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

A.

Initiate change control.

B.

Address risk mitigation.

C.

Escalate this to the project sponsor.

D.

Initiate project closure.

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

A.

Develop the feature as a parallel work package.

B.

Shorten the current work period and begin the new work.

C.

Ask a dedicated team member to complete it immediately.

D.

Prioritize it in the requirements list for the next work period.

What are the objectives of Initiation processes?

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.

B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.

C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.

D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Which of the following is a category of organizational process assets?

A.

Government standards

B.

Organizational culture

C.

Employee capabilities

D.

Organizational knowledge bases

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

A.

Product

B.

Cost-benefit

C.

Stakeholder

D.

Research

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

When does Monitor and Control Risks occur?

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Which schedule network analysis technique modifies the project schedule to account for limited resources?

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

A.

lead

B.

lag

C.

mandatory dependency

D.

internal dependency

What is main purpose of Project Quantity Management?

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Which term describes an assessment of correctness?

A.

Accuracy

B.

Precision

C.

Grade

D.

Quality

Which process is engaged when a project team member makes a change to project budget with project manager ' s approval

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Which of the following is the primary output of the Identify Risks process?

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

What should be the frequency for meetings when transitioning from Scrum to Kanban?

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

For which kind of quantitative risk analysis chart can a tornado diagram represent values?

A.

Sensitivity analysis

B.

Monte Carlo analysis

C.

Expected monetary value analysis

D.

Decision tree analysis

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

A.

Iterative

B.

On-demand

C.

Interactive

D.

Quality

Which Control Quality tool is also known as an arrow diagram?

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

How can a project manager evaluate project team development?

A.

Produce team performance assessments.

B.

Hold weekly meetings to engage every member

C.

Complete a personal skill assessment on each team member

D.

Provide recognition awards to team members

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Which of the following are components of the project management plan?

A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan

B.

Scope management plan, issue log, risk register and project schedule network diagram

C.

Scope management plan, schedule baseline, milestone list, and assumption log

D.

Scope management plan, cost estimates, duration estimates, and resource calenders

What describes the relationship between projects, programs, and portfolios?

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.

Which are the most important competencies required for a project manager?

A.

Leadership, bilingualism, experience, and technical Knowledge

B.

PMP certification, experience, technical Knowledge, and post-graduate education

C.

Leadership, strategic and business management, project management knowledge, and technical knowledge

D.

Communication skills, project management knowledge, PMP certification, and availability to travel

A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.

How should the project manager report the status of the project?

A.

The project is at risk as the cost variance (CV) is negative.

B.

The project is within budget and within schedule.

C.

The project is within budget but is delayed.

D.

The project is tracking well as the cost variance (CV) is negative.

Work performance information and cost forecasts are outputs of which Project Cost Management process?

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

The initial development of a Project Scope Management plan uses which technique?

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Which tools and techniques should a project manager use when estimating costs?

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

What purpose does the hierarchical focus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the focus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Page: 1 / 7
Total 1337 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved