Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 7
Total 1320 questions

During what project management process does the project team begin identifying risks?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager. What should the project manager do to address this issue?

A.

Encourage the team to follow the project plan that was developed with team input.

B.

Apply emotional intelligence (EI) skills, such as active listening, to understand the team ' s issues.

C.

Instruct the team members to self-organize and resolve any outstanding issues.

D.

Ask the team members to record their concerns in the lessons learned log for future action.

Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?

A.

All business rules and data requirements for each process are documented.

B.

All relevant business rules for each process are documented.

C.

The resulting documentation adheres to established organizational standards.

D.

The data requirements for each process are documented.

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

A.

Collaboration

B.

Negotiation

C.

Decision making

D.

Influencing

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00

When developing a schedule which tools and techniques should a project manager use?

A.

Schedule Networfc Analysis and Critical Path Method

B.

Activity list and expert Judgement

C.

Milestone Iist and Risk Register

D.

Basis ot estimates and Rolling Wave Planning

At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

A.

Run a spike to ensure all information available is correct and then decide which stories to implement.

B.

Develop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).

C.

Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.

D.

Bring up all risks for implementing the user stories and discuss possible solutions.

Which Project Time Management process includes bottom-up estimating as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

A project manager is identifying the risks of a project. Which technique should the project manager use?

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

Which is an example of Administer Procurements?

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Which are the most important competencies required for a project manager?

A.

Leadership, bilingualism, experience, and technical Knowledge

B.

PMP certification, experience, technical Knowledge, and post-graduate education

C.

Leadership, strategic and business management, project management knowledge, and technical knowledge

D.

Communication skills, project management knowledge, PMP certification, and availability to travel

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?

A.

Resource management plan and lessons learned register

B.

Resource management plan and cost baseline

C.

Resource management plan and procurement management plan

D.

Resource management plan and preassignment

Which process involves determining, documenting, and managing stakeholders ' needs and requirements to meet project objectives?

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

What is the difference between verified and accepted deliverables?

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Scope, schedule, and cost parameters are integrated in the:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.

Which is the correct hierarchy in a project environment, from most to least Inclusive?

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

The process for performing variance analysis may vary, depending on:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

What should a project manager use to determine how much money is needed to complete a project?

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Change requests are an output from which Project Integration Management process?

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Which of the following is an input to Control Scope?

A.

Project schedule

B.

Organizational process assets updates

C.

Project document updates

D.

Work performance information

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Match the method for categorizing stakeholders with its corresponding description

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

A.

Risk register

B.

Sprint board

C.

Sprint planning

D.

User story

To which process is work performance information an input?

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Which is an aspect of the requirements management plan?

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Which three processes are generally included in risk management? (Choose three)

A.

Monitor Risk Costs

B.

Identify Risks

C.

Plan Risk Responses

D.

Perform Qualitative Risk Analysis

E.

Estimate Risk Activity Resources

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?

A.

Analyzing the change

B.

Approving the change

C.

Reviewing the change

D.

Discussing the change

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

A tool and technique used in the Develop Project Charter process is:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

The project manager needs to review the templates in use. The templates are part of the:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

A new project manager is assigned to a high-visibility project. The project manager starts with the requirements analysis process. Who should the project manager onboard to assist with the requirements traceability matrix or analysis?

A.

Systems analyst

B.

Business analyst

C.

Project sponsor

D.

Technical consultant

An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee ' s duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?

A.

Strategic

B.

Finance

C.

Project

D.

Operations

Which of the following strategic considerations often results in project authorization?

A.

Customer requests and/or issue resolution

B.

Stakeholder expectations and/or strategic opportunity (business need)

C.

Technological advancement and/or senior executive request

D.

Market demand and/or legal requirements

One of the key benefits of the Plan Human Resource Management process is that it:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

After recommending to Tan (client) to leave the feature out, what should the project manager do?

A.

Document the end user feedback and follow the change control process in order to define small-scale prototypes to test ideas and try new approaches during future iterations.

B.

Have the end user write a user story with a brief description of an outcome of the feature.

C.

Check with the project team that the resources needed to add this feature are made available by restructuring the timeline and reducing initial quantities.

D.

Enable a stakeholder change in order to facilitate the project to provide the required deliverable as well as the intended outcome.

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Projects are undertaken by an organization to support the:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

A tool and technique used during the Define Scope process is:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

What specific quality considerations should be examined while completing Quality Management plan?

A.

Risk registerB Stakeholder engagement

B.

Continuous improvement

C.

Standards and regulatory compliance

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Which tool or technique is used in the Plan Scope Management process?

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

What is a tool to improve team performance?

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Which is the correct formula for calculating expected activity cost for three-point estimating?

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

A.

The risk management plan and the assumption log

B.

Costs estimates and cost forecast

C.

The risk management plan and the basis of estimates

D.

The assumption log and the project charter

In the basic communication model, which term refers to the method that is used to convey the message?

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

Page: 3 / 7
Total 1320 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved