Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 3 / 7
Total 1337 questions

What is the process of determining the stakeholders impacted by a business problem or opportunity?

A.

Stakeholder requirements

B.

Stakeholder identification

C.

Stakeholder analysis

D.

Stakeholder characteristics

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

Exhibit A is an example of which of the following types of Sequence Activities?

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Assigned risk ratings are based upon:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders ' tolerances.

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process ' ?

A.

Assumption log

B.

Milestone list

C.

Business case

D.

Risk register

What is an output of the plan resource management process

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

A.

50-75%

B.

25-50%

C.

75-100%

D.

0-25%

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

In agile projects while performing scope management. What is the definition of requirements

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

The Monitoring and Controlling Process Group includes processes that:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

What is the purpose of the project management process groups?

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Plan Communications Management develops an approach and plan for project communications based on stakeholders ' needs and requirements and:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

How many Project Management Process Groups are there?

A.

3

B.

4

C.

5

D.

6

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

A.

Control chart

B.

Flowchart

C.

Checksheet

D.

Pareto diagram

Plan Schedule Management is a process in which Knowledge Area?

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

In project management, which document is used to start the initial risk identification?

A.

Assumption log

B.

Risk management plan

C.

Risk register

D.

Issue log

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

In an organization with a projectized organizational structure, who controls the project budget?

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to evaluate the solution in the larger context to ensure it does not behave in unacceptable ways when deployed to production.

Which evaluation technique should be used here?

A.

Performance testing

B.

Integration testing

C.

Day-in-the-life testing

D.

Exploratory testing

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

An adaptive team ' s velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.

How should the project manager calculate the anticipated velocity for future sprints?

A.

Use the velocity of the last sprint, as it is the most recent one to share.

B.

Add a 30% buffer to the velocity to calculate future velocity.

C.

Calculate the average of the past five sprints to predict future velocity.

D.

Change the adaptive tool that the team is using to calculate velocity.

Which is a tool or technique used in Define Scope?

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Which characteristics do effective project managers possess?

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Which is an example of analogous estimating?

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

The number of potential communication channels for a project with 5 stakeholders is:

A.

10.

B.

12.

C.

20.

D.

24.

The purpose of inspection in Perform Quality Control is to keep errors:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Construction of a building has stopped due to a supplier ' s failure to deliver concrete. The project schedule is behind by three months.

What should the project manager do to overcome this problem and put the project back on track?

A.

Follow the risk response plan and allocate resources, if needed, to overcome the issue.

B.

Consult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.

C.

Extend the time of product delivery and use management reserve to cover any losses.

D.

Accept any penalties that might occur and continue working as initially planned.

The activity tailoring is necessary because:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects

B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide

C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects

D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

A.

Daily scrum

B.

Increments

C.

Sprint retrospective

D.

Sprint backlog

E.

Product backlog

Which Project Time Management process includes bottom-up estimating as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

What does expert judgment provide as an input to the resource management plan?

A.

Geographic distribution of facilities and resources

B.

Physical resource management policies and procedures

C.

Estimated lead times based on lessons learned

D.

Templates for the resource management plan

Which key benefit can a project manager obtain by identifying stakeholders?

A.

Identify the appropriate focus for engagement of each stakeholder.

B.

Assess the risk exposure for each stakeholder.

C.

Map stakeholder power and influence grid.

D.

Identify the appropriate channels of communication with all stakeholders.

Monte Carlo is which type of risk analysis technique?

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Which technique is used in Perform Quantitative Risk Analysis?

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

In a project using agile methodology, who may perform the quality control activities?

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Which format can a network diagram take?

A.

Flow chart

B.

Control chart

C.

Affinity diagram

D.

Cause-and-effect diagram

What type of meeting is held to discuss prioritized product backlog items?

A.

Status

B.

Daily standup

C.

Iteration planning

D.

Release planning

Expected monetary value (EMV) is computed by which equation?

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Which is the correct formula for calculating expected activity cost for three-point estimating?

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

A project manager builds consensus and overcomes obstacles by employing which communication technique?

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

A tool and technique used in the Develop Project Charter process is:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Which activity may occur at project or phase closure?

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking

A project team identifies defects that will require a modification to a tool ' s functionality. What process should the project manager follow to obtain stakeholder buy-in?

A.

Control Schedule

B.

Perform Qualitative Risk Analysis

C.

Perform Integrated Change Control

D.

Control Scope

An input of the Control Schedule process is the:

A.

resource calendar.

B.

activity list.

C.

risk management plan.

D.

organizational process assets.

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

The following is a network diagram for a project.

The total float for the project is how many days?

A.

3

B.

5

C.

7

D.

9

Which three processes are generally included in risk management? (Choose three)

A.

Monitor Risk Costs

B.

Identify Risks

C.

Plan Risk Responses

D.

Perform Qualitative Risk Analysis

E.

Estimate Risk Activity Resources

An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.

What effective tools should the project teams use to collaborate?

A.

Adopt an iterative development approach and conduct virtual meetings.

B.

Arrange frequent colocated meetings and let the teams work together.

C.

Focus on developing products by only using teams that are colocated.

D.

Benchmark and adopt best practices that are being used by the competition.

What is the total float of the critical path?

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Which of the following is contained within the communications management plan?

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

An example of a group decision-ma king technique is:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Which of the following are processes associated with Project Cost Management?

A.

Develop Costs. Estimate Costs, Determine Budget. Control Costs

B.

Develop Budget, Determine Budget, Determine Risks, Control Costs

C.

Plan Cost Management, Estimate Costs. Determine Budget. Control Costs

D.

Plan Budget Management. Determine Budget, Create Cost Accounts. Control Costs

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

A.

Low-fidelity prototyping

B.

High-fidelity prototyping

C.

Data prototyping

D.

Report prototyping

Page: 3 / 7
Total 1337 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved