CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2025 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.
In a project using agile methodology, who may perform the quality control activities?
A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.
Which entities will the project manager attempt to influence?
Match the influence with its corresponding category of influence.
Which are the main objectives of Project Risk Management?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Which process is engaged when a proiect learn inember makes a change to project budget with the project manager's approval?
Which of the following are outputs of the Define Scope process in Project Scope Management?
Which of the following is a category of organizational process assets?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
Which of the following tasks focuses on decomposing work packages?
What is a tailoring consideration for the application of Project Risk Management processes?
The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
Which of the following is an example of an internal factor that influences the outcome of the project?
What does expert judgment provide as an input to the resource management plan?
A project manager called for a team meeting...................method did the team use
A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?
Which of the following are outputs from the process of creating a work breakdown structure (WBS)?
In an agile and adaptive project, which scope management entity invokes stakeholder engagement?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take into account for risk management in this environment?
Make-or-buy analysis is a tool and technique of which process?
Tailoring considerations for project scope management may include:
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
Match each dimension of the communications management plan to its corresponding focus.
Which knowledge area includes the processes to identify, define, and unify the various project management processes?
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
Which contract type is least desirable to a vendor?
What is the project manager's responsibility in Project Integration Management?
What can increase the complexity of the Manage Stakeholder Engagement process?
Which set of competencies should a project manager have?
Which is a list of organizational systems that may have an impact on a project?
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
To which knowledge area does the Collect Requirements process belong?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?
Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?
When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
Which task will a project manager undertake while conducting Project Resource Management?
A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
What communication methods would a project manager use for overall effective project communication?
Which are inputs for the Plan Quality Management process?
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?
A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
Which of these is true of project integration management?
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
A graphic display of project team members and their reporting relationships is known as a:
Technical capability, past performance, and intellectual property rights are examples of:
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
Which item is a cost of conformance?
Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Stakeholder communication requirements should be included as a component of:
Which output is the approved version of the time-phased project budget?
In project management, a temporary project can be:
The following is a network diagram for a project.
The free float for Activity H is how many days?
The process of obtaining seller responses, selecting a seller, and awarding a contract is called: