CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which of the following tasks is related to perform the qualitative risk analysis process?
Which of the following is an input to the Direct and Manage Project Execution process?
Which of the following is a tool and technique for Estimate Activity Durations?
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
Select three processes that are associated with Project Schedule Management.
Which of these is true of project integration management?
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
Change request status updates are an output of which process?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
Which of the following is an example of an organizational system that is arranged based on the job being performed?
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
What tool or technique is used in the Collect Requirements process?
Tools and techniques used in Direct and Manage Project Work include:
Which of the following is an input to the Perform Qualitative Risk Analysis process?
Which procurement management process includes obtaining seller response, seller selection, and contract awarding?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
Why is tailoring required in a project?
At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?
A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Change requests are an output from which Project Integration Management process?
In the Define Activities process, the schedule management plan is used to:
A project manager should consider the impact of project..............manager following
A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?
The Verify Scope process is primarily concerned with:
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
What is one of the main purposes of the project charter?
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
In which type of organizational structure are staff members grouped by specialty?
What is the difference between the critical path and the critical chain?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
What should a project manager use to determine how much money is needed to complete a project?
Which is a list of organizational systems that may have an impact on a project?
A project management office manages a number of aspects including the:
A project manager needs to request outside support......manager need to create
A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?
Which process determines the correctness of deliverables?
Which of the following is an information gathering technique in Identify Risks?
Portfolio Management is management of:
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
Which of the following tasks focuses on decomposing work packages?
Which tools or techniques are used during the Close Project or Phase process?
Testing falls into which of the following categories of cost of quality?
The project team of a predictive project is following the requirements traceability matrix to ensure the deliverables align with customer expectations. If the project had been an adaptive project, the project team would use a different artifact to ensure the deliverables align with customer expectations. What should the project team use in an adaptive project?
Which is an enterprise environmental factor?
What three strategies are used to respond to threats?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?
In the Develop Project Team process, which of the following is identified as a critical factor for a project ' s success?
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?
What is the number of stakeholders, if the project has 28 potential communication channels?
Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?
Which of the following techniques is used during Control Scope?
Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?
Which of the following tools and techniques is used in the Verify Scope process?
What is the first step in the Stakeholder Management process?
What is an objective of the Develop Project Team process?




