CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?
During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the project manager noticed that the team members do not follow SMART objectives.
What are SMART objectives?
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.
What should the business analyst do?
Which statement describes the various purposes of project scheduling?
Which of the following is example of communication tools and techniques?
During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?
In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process'?
Match each Project Cost Management process with its appropriate keyword
Which of the following projects is a quality candidate for adaptive approaches?
On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.
What is the advantage of using this tool?
What characteristic of servant leadership supports resource management in an agile environment?
Which is the appropriate tool to identify the possible correlation two elements in aprocess?
Which process uses expert judgment to manage project resources?
A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.
What should the project manager do?
When paying a consultation fee to a technical expert, what type of contract is often used'?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take to account for risk management n this environment’
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?
A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.
How should the project manager report the status of the project?
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
A project manager should consider the impact of project..............manager following
A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?
An organization's project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?
What important qualities should project managers possess for strategic and business management?
A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.
Which evaluation technique should be used here?
A project manager is newly assigned to a project. Which document can help the project manager understand the project scope?
Which is a major component of an agreement?
A project team has missed a milestone.
Which response strategy should be implemented?
Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?
Which process determines the correctness of deliverables?
An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.
What effective tools should the project teams use to collaborate?
Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?
A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?
After missing a weekly communication meeting hosted by the project manager, a stakeholder looks at the latest report in the common repository.
What is the communication type used in this scenario?
A product owner wants to ensure that the project's requirements, including product requirements, are met and validated. To do this project manager wants.
Match each process to its definition.
An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee's duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?
Which of the following does a portfolio combine?
Which are the most important competencies required for a project manager?
In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
Which of the following is used as input to prepare a cost management plan?
What purpose does the hierarchical focus of stakeholder communications serve?
What should be the frequency for meetings when transitioning from Scrum to Kanban?
What key component of the project charter defines the conditions for dosing a project phase?
What is the Project Schedule Management practice used to deliver incremental value to the customer'?
The process of identifying specific actions to be performed to produce project deliverables is:
Which statement correctly describes the value of a business case?
An input to the Estimate Activity Resources process is:
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
Administer Procurements is part of which Process Group?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
At the end of the project, what will be the value of SV?
Who is responsible for initiating a project?
Which activity may occur at project or phase closure?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which of the following is an input to Direct and Manage Project Execution?
Expected monetary value (EMV) is computed by which equation?
Projects are separated into phases or subprojects; these phases include:
An input to the Collect Requirements process is the:
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
What is project management?
A few black text boxes Description automatically generated with medium confidence
A group of words on a white background Description automatically generated