Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 4 / 7
Total 1337 questions

Which of the following tasks is related to perform the qualitative risk analysis process?

A.

Identify the project risks and assign a probability of occurrance

B.

Perform a sensitivity analysis to determine which risk has the most potential for impacting the project

C.

Analyze the effect of identified project risks as numerical data

D.

Prioritize each project risk and assign the probability of occurrence and impact for each one

Which of the following is an input to the Direct and Manage Project Execution process?

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Which of the following is a tool and technique for Estimate Activity Durations?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Select three processes that are associated with Project Schedule Management.

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

Which of these is true of project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Change request status updates are an output of which process?

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Which of the following is an example of an organizational system that is arranged based on the job being performed?

A.

Simple

B.

Multi-divisional

C.

Functional

D.

Project-oriented

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

A.

management

B.

response

C.

tolerance

D.

appetite

What tool or technique is used in the Collect Requirements process?

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Tools and techniques used in Direct and Manage Project Work include:

A.

Process analysis and expert judgment

B.

Analytical techniques and a project management information system

C.

Performance reviews and meetings

D.

Expert judgment and meetings

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Why is tailoring required in a project?

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

A.

Run a spike to ensure all information available is correct and then decide which stories to implement.

B.

Develop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).

C.

Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.

D.

Bring up all risks for implementing the user stories and discuss possible solutions.

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Change requests are an output from which Project Integration Management process?

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

In the Define Activities process, the schedule management plan is used to:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

The Verify Scope process is primarily concerned with:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?

A.

Set up a meeting with the sponsor.

B.

Set up a go/no-go meeting.

C.

Wait for the next sprint.

D.

Deliver the product.

What is one of the main purposes of the project charter?

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definilion of stakeholder roles and responsibilities

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

In which type of organizational structure are staff members grouped by specialty?

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

What is the difference between the critical path and the critical chain?

A.

Scope changes

B.

Resource limitations

C.

Risk analysis

D.

Quality audits

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A.

Result

B.

Product

C.

Service

D.

Improvement

What should a project manager use to determine how much money is needed to complete a project?

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Which is a list of organizational systems that may have an impact on a project?

A.

Internal policies, company procedures, and organizational resources

B.

Company culture, purchasing system, and project management information system

C.

Organizational structure, governance framework, and management elements

D.

Organizational process assets, enterprise environmental factors, and corporate knowledge

A project management office manages a number of aspects including the:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?

A.

Time and material (TandM)

B.

Cost plus fixed fee (CPFF)

C.

Fixed price

D.

Cost plus award fee (CPAF)

Which process determines the correctness of deliverables?

A.

Verify Deliverables

B.

Validate Deliverables

C.

Review Deliverables

D.

Analyze Deliverables

Which of the following is an information gathering technique in Identify Risks?

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Portfolio Management is management of:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?

A.

Product and sprint backlog

B.

Key performance indicators (KPIs) and baseline

C.

Increments and bottlenecks

D.

Burndown and burnup charts

Which of the following tasks focuses on decomposing work packages?

A.

Adjust duration estimates

B.

Define activities

C.

Complete rolling wave planning

D.

Develop milestone list

Which tools or techniques are used during the Close Project or Phase process?

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Testing falls into which of the following categories of cost of quality?

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

The project team of a predictive project is following the requirements traceability matrix to ensure the deliverables align with customer expectations. If the project had been an adaptive project, the project team would use a different artifact to ensure the deliverables align with customer expectations. What should the project team use in an adaptive project?

A.

Business case

B.

Product backlog

C.

Milestone list

D.

Product management plan

Which is an enterprise environmental factor?

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

What three strategies are used to respond to threats?

A.

Escalate, accept, and mitigate

B.

Accept share, and avoid

C.

Escalate, transfer, and exploit

D.

Mitigate, accept, and prioritize

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?

A.

Take control of all decisions and product planning.

B.

Build a team that can respond to changes within a collaborative, decision-making environment.

C.

Promote a team with a narrow specialization within a hierarchical environment.

D.

Delegate project decisions to the product owner and sponsor.

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

In the Develop Project Team process, which of the following is identified as a critical factor for a project ' s success?

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Two resources are performing a peer review of an artifact. What should be the outcome of the peer review?

A.

All business rules and data requirements for each process are documented.

B.

All relevant business rules for each process are documented.

C.

The resulting documentation adheres to established organizational standards.

D.

The data requirements for each process are documented.

What is the number of stakeholders, if the project has 28 potential communication channels?

A.

7

B.

8

C.

14

D.

16

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Which of the following techniques is used during Control Scope?

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

A.

2.0

B.

45

C.

0.5

D.

15

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

A.

Project plan

B.

Business case

C.

Budget requirement

D.

Project charter

Which of the following tools and techniques is used in the Verify Scope process?

A.

Inspection

B.

Variance analysis

C.

Expert judgment

D.

Decomposition

What is the first step in the Stakeholder Management process?

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

What is an objective of the Develop Project Team process?

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Page: 4 / 7
Total 1337 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved