Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 7
Total 1320 questions

Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?

A.

Leadership management

B.

Technical project management

C.

Strategic management

D.

Business management

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Which of the following is a narrative description of products, services, or results to be delivered by a project?

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)

A.

Project management plan

B.

Product roadmap

C.

Requirements traceability matrix

D.

Business goals and objectives

E.

Risk register

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

The procurement process that documents agreements and related documentation for future reference is known as:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

The Identify Stakeholders process is found in which Process Group?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

A.

Control charts

B.

Pareto diagrams

C.

Ishikavva diagrams

D.

Checksheets

Which of the following processes are part of the Project Integration Management Knowledge Area?

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

A.

create the project management plan.

B.

identify the project objectives.

C.

review and update stakeholder engagement.

D.

create the schedule baseline.

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

A.

100

B.

120

C.

1,000

D.

1,200

For what project management process is work performance information an output?

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

Which method should the project manager adopt?

A.

SAFe®

B.

Kanban

C.

Feature-driven development (FDD)

D.

Scrum

What important qualities should project managers possess for strategic and business management?

A.

Skills and behaviors related to specific domains of project management

B.

Knowledge and competencies needed to guide and motivate a team

C.

Skills and behaviors needed to help an organization achieve its goals

D.

Expertise in the industry and organization that deliver better outcomes

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Which organizational process asset can make an impact on the outcome of a project?

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

Which process is engaged when a project team member makes a change to project budget with project manager ' s approval

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

A.

Daily scrum

B.

Increments

C.

Sprint retrospective

D.

Sprint backlog

E.

Product backlog

What communications management process enables an effective information flow among project stakeholders ' ?

A.

Monitor Stakeholder Engagement

B.

Manage Communications

C.

Monitor Communications

D.

Manage Stakeholder Engagement

When can we say that a project is completed?

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?

A.

Feature-driven development (FDD) as it will deliver product segments and the milestones are controlled by the development manager.

B.

Kanban as it will provide flexibility to the team for working at their own pace in the time frame requested.

C.

Scrum as it uses sprints and retrospectives, maximizing time delivery and the value of the product.

D.

Extreme Programming (XP) as it will help deliver more quickly since developers will work in pairs.

For a stakeholder with low interest and high power, the project manager should:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

What communication methods would a project manager use for overall effective project communication?

A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Which of the following is an output of the Define Activities process?

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Which of the following is an example of tacit knowledge

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

The zero duration of milestones in project planning occurs because milestones:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Project Stakeholder Management focuses on:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.

Portfolio

B.

Project

C.

Program

D.

Operations

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Variance and trend analysis is a tool and technique used in which process?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

What CPI > 1 and SPI < 1 mean?

A.

Under budget ahead of schedule

B.

Over budget, behind schedule

C.

Under budget, behind schedule

D.

Over budget, ahead of schedule

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

In which type of organizational structure are staff members grouped by specialty?

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Perform Quantitative Analysis focuses on:

A.

compiling a lsit of known risks and preparing responses to them

B.

assessing the probability of occurrence and impact for every risk in the risk register

C.

evaluating the contingency and management reserves required for the project

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

After missing a weekly communication meeting hosted by the project manager, a stakeholder looks at the latest report in the common repository.

What is the communication type used in this scenario?

A.

Pull

B.

Verbal

C.

Written

D.

Push

Inputs to the Plan Schedule Management process include:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Which tools and techniques should a project manager use when estimating costs?

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Which of the following is an input to Direct and Manage Project Execution?

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Which action is included in the Control Costs process?

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

A weighting system is a tool for which area of Conduct Procurements?

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller ' s

D.

Planning purchase and acquisition

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

A.

2

B.

3

C.

4

D.

6

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

A.

The receiver decodes the message

B.

The receiver responds to the message with feedback.

C.

The receiver transmits the message

D.

The receiver acknowledges their receipt of the message

Which Process Group contains those processes performed to define a new project?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

What is an example of an emerging trend in procurement management?

A.

Online technology enable projects to postpone ordering long lead items until the items are needed

B.

Online technologies allow a project ' s progress to be viewed by all stakeholders to build better relations

C.

Online procurement tools provide buyers with multiple sources to advertise to sellers.

D.

Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.

What does an S-curve from a Monte Carlo analysis show?

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

Page: 5 / 7
Total 1320 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved