Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2025, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 7
Total 1305 questions

Perform Quality Control is accomplished by:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Which of the following techniques is used during Control Scope?

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Which of the following is an output of the Define Activities process?

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Organizations perceive risks as:

A.

events that will inevitably impact project and organizational objectives.

B.

the effect of uncertainty on their project and organizational objectives.

C.

events which could have a negative impact on project and organizational objectives.

D.

the negative impact of undesired events on their project and organizational objectives.

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

The formal and informal interaction with others in an organization industry, or professional environment is known as:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Which of the following statements correctly characterizes pull communication?

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Which of the following is contained within the communications management plan?

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Which Process Group typically consumes the bulk of a project's budget?

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Which tool is used to develop technical details within the project management plan?

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.

One

B.

Five

C.

Six

D.

Seven

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Which is a tool or technique used in Define Scope?

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

A.

plan

B.

process

C.

program

D.

portfolio

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

A.

Organizational standard processes

B.

Marketplace conditions

C.

Historical information

D.

Templates

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

What is the term assigned to products or services having the same functional use but different technical characteristics?

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Which are examples of processes that may be used once or at predefined points in the project life cycle?

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

What is an output of the plan resource management process

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

Which of the following is an example of facit knowledge?

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

What is a tailoring consideration in Project Integration Management?

A.

Validation and control

B.

Benefits

C.

Technology support

D.

Physical location

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

A.

Project level

B.

Organizational level

C.

Industry level

D.

Influential level

A project manager is identifying the risks of a project. Which technique should the project manager use?

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

What does expert judgment provide as an input to the resource management plan?

A.

Geographic distribution of facilities and resources

B.

Physical resource management policies and procedures

C.

Estimated lead times based on lessons learned

D.

Templates for the resource management plan

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Which two processes should be used to influence costs in the early stages of a project?

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Which is an example of analogous estimating?

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Match each dimension of the communications management plan to its corresponding focus.

In which organizational structure would the project manager have most authority?

A.

Matrix-weak

B.

Matrix-balanced

C.

Matrix-strong

D.

Organic or simple

Which is the correct hierarchy in a project environment, from most to least Inclusive?

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

What is the best tool to calculate the critical path on a project?

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

What purpose does the hierarchical locus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Which is the tool or technique that is used to obtain the list of activities from the work packages?

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

A.

Involvement is needed only during project initiation.

B.

Minimal involvement of stakeholders is sufficient.

C.

They should be continuously engaged.

D.

They should be involved only during phase or deliverable reviews.

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?

A.

Take control of all decisions and product planning.

B.

Build a team that can respond to changes within a collaborative, decision-making environment.

C.

Promote a team with a narrow specialization within a hierarchical environment.

D.

Delegate project decisions to the product owner and sponsor.

When should Project Risk Management be conducted?

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

How should a project manager plan communication for a project which has uncertain requirements?

A.

Include stakeholders in project meetings and reviews, use frequent checkpoints, and co-locate team members only.

B.

Invite customers to sprint planning and retrospective meetings, update the team quickly and on a daily basis, and use official communication channels.

C.

Adopt social networking to engage stakeholders, issue frequent and short messages, and use informal communication channels.

D.

Adopt a strong change control board process, establish focal points for main subjects, and promote formal and transparent communication.

In which type of organization does the project manager have the maximum influence

A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

What organizational asset can influence the Plan Risk Management process?

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

What does an S-curve from a Monte Carlo analysis show?

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time