Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmaspas7

Easiest Solution 2 Pass Your Certification Exams

CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)

Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 5 / 7
Total 1337 questions

Which process involves identifying and documenting the logical relationships between project activities?

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.

8

B.

18

C.

36

D.

40

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Who determines which dependencies are mandatory during the Sequence Activities process?

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

The Perform Quality Assurance process occurs in which Process Group?

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Scope, schedule, and cost parameters are integrated in the:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

A.

Project charter and stakeholder engagement plan

B.

Risk management plan and stakeholder engagement plan

C.

Communications management plan and stakeholder engagement plan

D.

Project charter and communications management plan

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Which of the following statements is true regarding project and product lifecycles?

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

To ensure stakeholder satisfaction; identified stakeholder needs should all be

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

A.

Mitigate

B.

Transfer

C.

Share

D.

Avoid

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Which tools or techniques will a project manager use for Develop Project Team?

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

A.

event.

B.

response,

C.

perception.

D.

impact.

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

A.

Brainstorming, Monte Carlo simulation, analogous estimation

B.

Three-point estimation, resources leveling, iteration burndown chart

C.

Milestone charts, parametric estimation, schedule baseline

D.

Parametric estimation, three-point estimation, meetings

Which two processes should be used to influence costs in the early stages of a project?

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Select three elements that apply to agile/ adaptive environments

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

In project management, a temporary project can be:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

After Define Activities and Sequence Activities, the next process is:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

A.

Activity level

B.

Deliverable level

C.

Task level

D.

Work package level

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Which action should the project manager take after the team finishes executing the scope?

A.

Verify the deliverables to ensure that they are correct and meet the customer ' s satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

A project manager is working with the team to prepare the estimates for various work items. The team needs to compare the relative sizing of the items. What should the project manager suggest the team use?

A.

Project task estimation

B.

Dependency planning

C.

Story point estimation

D.

Sprint planning

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

The primary purpose of the stakeholder register is to:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

Identify Risks is part of which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Which are the main objectives of Project Risk Management?

A.

Increase the probability of positive risks and decrease the probability of negative risks

B.

Avoid all kind of risks

C.

Increase the probability of positive risks and eliminate all negative risks

D.

Identify positive and negative risks

A tool and technique used during the Define Scope process is:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

The project scope statement and resource calendars are inputs to which Project Time Management process?

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Specification of both the deliverables and the processes is the focus of:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

A.

Three-point

B.

Bottom-up

C.

Parametric

D.

Analogous

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

What is the project manager ' s responsibility in Project Integration Management?

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

A.

Work breakdown structure (WBS)

B.

Approval from the stakeholders

C.

Feasibility study of the solution

D.

Root cause analysis of the problem

Agile release planning provides a high-level summary timeline of the release schedule based on.

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Closes Project or Phase

D.

Perform itegrated Change Control

What is the most accurate rough order of magnitude (ROM)?

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17

Which of the following is an output of the Distribute Information process?

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

When the business objectives of an organization change, project goals need to be:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

When developing a schedule which tools and techniques should a project manager use?

A.

Schedule Networfc Analysis and Critical Path Method

B.

Activity list and expert Judgement

C.

Milestone Iist and Risk Register

D.

Basis ot estimates and Rolling Wave Planning

A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.

Which activity is the project team conducting?

A.

Project execution

B.

Benchmarking

C.

Brainstorming

D.

Project initiation

Which of the following is used as input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

What CPI > 1 and SPI < 1 mean?

A.

Under budget ahead of schedule

B.

Over budget, behind schedule

C.

Under budget, behind schedule

D.

Over budget, ahead of schedule

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Which process determines the risks that might affect the project?

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

A temporary endeavor that creates a unique product or service is called a:

A.

Project

B.

Plan

C.

Program

D.

Portfolio

Page: 5 / 7
Total 1337 questions
Copyright © 2014-2026 Solution2Pass. All Rights Reserved