CAPM PMI Certified Associate in Project Management (CAPM) Free Practice Exam Questions (2026 Updated)
Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.
Which process involves identifying and documenting the logical relationships between project activities?
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
Who determines which dependencies are mandatory during the Sequence Activities process?
The Perform Quality Assurance process occurs in which Process Group?
Scope, schedule, and cost parameters are integrated in the:
The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
Which of the following statements is true regarding project and product lifecycles?
To ensure stakeholder satisfaction; identified stakeholder needs should all be
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
Which cost is associated with nonconformance?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which tools or techniques will a project manager use for Develop Project Team?
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Which set of tools and techniques is useful for estimating activity durations for the project schedule?
Which two processes should be used to influence costs in the early stages of a project?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Select three elements that apply to agile/ adaptive environments
In project management, a temporary project can be:
The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
After Define Activities and Sequence Activities, the next process is:
A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.
What should the project manager answer?
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Which action should the project manager take after the team finishes executing the scope?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
A project manager is working with the team to prepare the estimates for various work items. The team needs to compare the relative sizing of the items. What should the project manager suggest the team use?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
The primary purpose of the stakeholder register is to:
Identify Risks is part of which Process Group?
Which are the main objectives of Project Risk Management?
A tool and technique used during the Define Scope process is:
The project scope statement and resource calendars are inputs to which Project Time Management process?
Specification of both the deliverables and the processes is the focus of:
Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
What is the project manager ' s responsibility in Project Integration Management?
During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.
What could be missing from the business case?
Agile release planning provides a high-level summary timeline of the release schedule based on.
A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?
What is the most accurate rough order of magnitude (ROM)?
The following is a network diagram for a project.

The critical path for the project is how many days in duration?
Which of the following is an output of the Distribute Information process?
When the business objectives of an organization change, project goals need to be:
When developing a schedule which tools and techniques should a project manager use?
A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.
Which activity is the project team conducting?
Which of the following is used as input to prepare a cost management plan?
What CPI > 1 and SPI < 1 mean?
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
Which process determines the risks that might affect the project?
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
A temporary endeavor that creates a unique product or service is called a:



