Prepare effectively for your PMI CAPM Certified Associate in Project Management (CAPM) certification with our extensive collection of free, high-quality practice questions. Each question is designed to mirror the actual exam format and objectives, complete with comprehensive answers and detailed explanations. Our materials are regularly updated for 2026, ensuring you have the most current resources to build confidence and succeed on your first attempt.

Page: 6 / 7
Total 1320 questions

Which set of competencies should a project manager have?

A.

Leadership, strategic and business management, and technical project management

B.

Expertise in the Industry, leadership and business management, and bilingual skills

C.

Technical project management, expertise in every role, and PMP certification

D.

Expertise in every detail on project activities. PMP certification, and leadership

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Who identifies project requirements in the early phase of the project?

A.

Business analyst, product team, and key stakeholders

B.

Project manager, business analyst, and key stakeholders

C.

Project manager, business analyst, and project sponsor

D.

Project sponsor, business analyst, and key stakeholders

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Risk exists the moment that a project is:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.

What should the project manager do next to avoid project failure?

A.

Adopt a change management approach and delay the project to decide on the direction.

B.

Develop a focus group to face the issue and decide on the appropriate direction.

C.

Request a meeting with top management to state concerns about their ability to handle the situation.

D.

Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.

In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from recurring?

A.

Extend the delivery time for the product since the management reserve allows it.

B.

Temporarily use another team for the next iteration and evaluate their performance.

C.

Observe the project team ' s performance for the next two iterations before taking any action.

D.

Identify possible reasons for the delay and consult the risk register for corrective actions.

An organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:

A.

Project Management Information System

B.

Project Management System

C.

Project Management Office

D.

Project Management Knowledge Area

A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team ' s workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed.

Which element will the project manager handle?

A.

Capacity limit

B.

Pull system

C.

Work in progress

D.

Virtual board

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

A.

Project plan

B.

Business case

C.

Budget requirement

D.

Project charter

When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?

A.

Update the schedule baseline

B.

Review the schedule baseline

C.

Initiate a change request

D.

Update the risk register

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

A.

Create Work Breakdown Structure (WBS)

B.

Create Scope Baseline

C.

Collect Requirements

D.

Define Scope

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

The Human Resource Management processes are:

A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.

B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.

C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.

D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

A business manager wants to start a project to launch a new product. How should the manager initiate the project?

A.

Ask a small team to produce a prototype of the product before full-scale development.

B.

Assign a project manager to the project and ask them to document the project scope.

C.

Prepare a detailed business case to document project objectives and success criteria.

D.

Discuss the project requirements with the team for alternative products in the market.

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

A.

Involvement is needed only during project initiation.

B.

Minimal involvement of stakeholders is sufficient.

C.

They should be continuously engaged.

D.

They should be involved only during phase or deliverable reviews.

Which is a key skill set in PMI’s Talent Triangle?

A.

Project excellence and scope management

B.

Strategic and business management

C.

Scope management and business management

D.

Financial management and people management

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming.

What should the project manager have done to avoid this situation?

A.

Coupled inexperienced team members with individuals having extensive knowledge in the required field

B.

Had open and transparent planning that engages internal and external stakeholders

C.

Held regular meetings more often with team members to check on their progress and obstacles

D.

Diversified more of the project team to capture a broad range of experiences

Make-or-buy analysis is a tool and technique of which process?

A.

Conduct Procurements

B.

Plan Procurement Management

C.

Analyze Procurements

D.

Control Procurements

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Project reporting is a tool that is most closely associated with which process?

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?

A.

The product backlog does not contain a prioritized list of requirements.

B.

The sprint backlog contains items to be completed during the current sprint.

C.

The sprint backlog contains the list of items prioritized by the product owner.

D.

The product backlog is a subset of the sprint backlog.

A procurement management plan is a subsidiary of which other type of plan?

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

What tern describes an intentional activity to modify a nonconforming product or product component?

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

A key benefit of the Manage Communications process is that it enables:

A.

The best use of communication methods.

B.

An efficient and effective communication flow.

C.

Project costs to be reduced.

D.

The best use of communication technology.

Which is a major component of an agreement?

A.

Change request handling

B.

Risk register templates

C.

Lessons learned register

D.

Procurement management plan

One of the objectives of a quality audit is to:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

An output of the Perform Integrated Change Control process is:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

An organization ' s project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?

A.

Organizational systems access

B.

Organizational process assets

C.

Resources management plan

D.

Procurement management plan

What benefit does the Manage Stakeholder Engagement process offer?

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.

$50

B.

$100

C.

$125

D.

$175

Which schedule network analysis technique modifies the project schedule to account for limited resources?

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

What can the cost management plan be established?

A.

Cost baseline

B.

Cost estimates

C.

Basis of estimates

D.

Control thresholds

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.

8

B.

18

C.

36

D.

40

The process of formalizing acceptance of the completed project deliverables is known as:

A.

Validate Scope.

B.

Close Project or Phase.

C.

Control Quality.

D.

Verify Scope.

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?

A.

Send the meeting minutes to all team members to verify that the required information is readily available.

B.

Ask the team members to provide feedback for meetings in the phase retrospective.

C.

Review the actions from the meeting with each of the project team members to ensure their understanding.

D.

Consult the communications management plan to determine the success criteria for meetings.

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

What should be the frequency for meetings when transitioning from Scrum to Kanban?

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Which tools and techniques will a project manager use to develop a project charter?

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

What is the Project Schedule Management practice used to deliver incremental value to the customer ' ?

A.

Resource optimization

B.

Iterative scheduling with a backlog

C.

On-demand scheduling

D.

Critical path method

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

An input to the Estimate Activity Resources process is:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

A.

Failure modes and effects analysis

B.

Design of experiments

C.

Quality checklist

D.

Risk analysis

The process of identifying specific actions to be performed to produce project deliverables is:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

A.

Hold a face-to-face meeting with the project manager and warn them.

B.

Point the director to a link where they can take a look at the reports.

C.

Invite stakeholders to attend monthly progress review meetings.

D.

Ask the project manager to update the monthly status report distribution list.

Which is one of the major outputs of Sequence Activities?

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Which of these is true of project integration management?

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

In the Develop Project Team process, which of the following is identified as a critical factor for a project ' s success?

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

According to the PMI Talent Triangle. leadership skills relate to the ability to:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Page: 6 / 7